Attachment 7 VAFB Repair Renovate Design Analysis

View the file

Other files for this federal contract opportunity

Other files attached to Renovate Building 8314, newest first.
File Type Posted
FA4610-15-R-0013-0002_Amendment_Conformed_Copy.doc DOC document
FA4610-15-R-0013-0002_Amendment.doc DOC document
Questions_Revised.docx DOCX document
Questions.docx DOCX document
Attch_8_-_SOW_attch_3.pdf PDF
Amendment_FA4610-15-R-0013-0001.doc DOC document
Attch_6_-_Electrical_requirements.pdf PDF
Site_Visit_Sign_in_Sheet.pdf PDF
Site_Visit_Meeting_Minutes.doc DOC document
Attch_2_-_Davis_Bacon.docx DOCX document
Attch_1_-_Statement_of_Work.doc DOC document
FA4610-15-R-0013_Bldg_8314.doc DOC document
Attch_5_-_Specifications.pdf PDF
Attch_3_-_RMDF.pdf PDF
Attch_4_-_Drawings.pdf PDF
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Number: XUMU 11‐1368B May 2013

100% Final Submittal - Design Analysis for

Repair/Renovate Missile Handling Vehicle & Equipment Shop at Vandenberg AFB, California

Submitted to:

Air Force Civil Engineer Center

In Response to:

Contract Number: FA8903-08-D-8793

Task Order: 0023

Submitted by:

Merrick & Company 5970 Greenwood Plaza Blvd • Greenwood Village, CO 8011

Tel: 303-751-0741 • Fax: 303-751-2581 www.merrick.com

MERRICK & COMPANY

Executive Summary

TABLE OF CONTENTS

SECTION 1 EXECUTIVE SUMMARY

SECTION 2 PROGRAMMING NOTES

SECTION 3 CIVIL AND SITE WORK

SECTION 4 ARCHITECTURE

SECTION 5 INTERIORS

SECTION 6 STRUCTURAL

SECTION 7 MECHANICAL AND PLUMBING

SECTION 8 FIRE PROTECTION

SECTION 9 ELECTRICAL AND COMMUNICATIONS

APPENDICIES

PROJECT KICKOFF MEETING MINUTES

ON SITE DATA GATHERING/CHARRETTE MINUTES

35% PRELIMINARY REVIEW MEETING MINUTES

65% INTERMEDIATE REVIEW MEETING MINUTES

95% ADVANCED FINAL REVIEW MEETING MINUTES

100% SUBMITTAL COST ESTIMATE

100% SUBMITTAL CONSTRUCTION SCHEDULE AND PHASING PLAN

SAMPLING AND ANALYSIS PLAN

ASBESTOS & LEAD BUILDING INSPECTION REPORT

DESIGN QUALITY CONTROL

CALCULATIONS:

- STRUCTURAL

- MECHANICAL

- ELECTRICAL

SECTION 1 EXECUTIVE SUMMARY

A. General

This Design Analysis reflects Merrick & Company’s interpretation of the Statement of

Work, information contained in User interviews, site investigations, outbrief, and further development of the design process for Repair/Renovate Missile Handling Vehicle &

Equipment Shop at Vandenberg AFB, California.

B. Facility Summary

This facility is a two story pre manufactured metal building with internal functions consisting of office, conference and maintenance facilities. The current condition of the exterior of the building is relatively good with minor repair needed in areas where the metal siding has been damaged and thermal protection needed. The Interior of the building is in need of being aesthetically updated due to worn and outdated materials while additional work stations will be added. This building is to convey a sense of compatibility and design excellence in the use of complimentary exterior and interior materials, color, and form as described in the Design Excellence Guide and knowledge gained through site research and User meetings. The design for the renovation and repair of facility 8314 shall incorporate materials that are durable, cost effective, and capture as many sustainability principles as possible, while supporting the mission of the building by providing a flexible, efficient, functional, safe, healthy, and comfortable work environment.

C. Discipline Narratives

Included in this document are the following discipline narratives:

Civil and Site Work

Architecture

Interiors

Structural

Mechanical and Plumbing

Fire Protection

Electrical and Communications

This document defines User needs, discipline specific design approach and discipline specific design analyses.

D. Design Changes

Following the completion of the 95% design, the following changes were requested by the Users, and were deemed as changes that would require additional funds (please note that these changes may be requested to be completed in the construction phase of the project):

The dimensions of Rooms 116, 117 and 118 in the building have been requested to be changed from the 100% design.

Room 116 has been requested to become the FMS Equipment & Tool Storage room and be approximately 346.8 square feet in size.

Room 117 has been requested to become the Gen Flight Supt Office and be approximately 175.7 square feet in size.

Room 118 (Gen Flight CC Office) has be requested to be resized to approximately 205.9 square feet.

All three of the above rooms have been requested to have doors that open to

Corridor 114 (with Room 116 having double doors).

With these changes to the scope, it may require additional changes to the HVAC (to move diffusers, re-calculate airflows, and rearrange ductwork as needed), the Electrical

(for new locations for data/comm and outlets), and the Lighting for these three rooms

(including lighting calculations).

Programming Notes

SECTION 2 PROGRAMMING NOTES

A. General

This project is listed as Task Order 0023 under the 4PAE08 program (Contract Number

FA8903-08-D-8793).

B. Scope Summary

The following major elements and their associated scope are from the Statement of

Work dated 24 April 2012 and are contained within this project:

Selective demolition of non-structural walls, ceilings, doors, door frames and other facility components.

Repair existing facility components.

Exterior skin repair and sealing of cracks, gaps and other openings as required.

Construct new walls, new windows, new ceilings, new interior finishes, new millwork, doors and door hardware where applicable.

Construct new exterior stair canopy.

Construct new exterior patio/barbeque pavilion.

Adjust, modify, replace and/or install new HVAC, fire suppression and fire detection systems associated with the reconfiguration of rooms and corridors

Install new/ lights, replace existing electrical, phone and network outlets

C. Design Schedule

On Site Data Gathering/Charrette 16 – 19 October 2012

35% Preliminary Design Submittal 20 November 2012

65% Intermediate Design Submittal 24 January 2013

95% Advanced Final Design Submittal 12 April 2013

100% Final Design Submittal 21 May 2013

Civil and Site Work

SECTION 3 CIVIL AND SITE WORK

A. Existing Site Description

Existing Condition: The building site (Site), existing building 8314, is located at

Vandenberg AFB north of 8th Street, east of Nevada Avenue, south of 6th Street and west of New Mexico Avenue. The Site contains the existing building, existing parking areas, roads, sidewalks, utilities, and general landscaping.

B. Grading

The area adjacent to the access door at Room 113 will be re-graded to provide positive flow away from the building.

C. Parking

This project will not provide additional privately owned vehicle (POV) parking. A portion of the government owned vehicle (GOV) parking on the north side of the building will be re-striped to restrict parking adjacent to the existing fire hydrant. The odd shaped concrete pad located outside Room 124C's double doors will be removed and replaced with a new rectangular 14' long by 10' wide concrete pad.

D. Storm Drainage

1. Existing Storm Drainage

Existing storm water drainage in the project area primarily consists of sheet flow and surface drainage. The area on the west side of the building slopes toward the building allowing water to enter the building at the access to the overhead door at

Room 113.

2. Proposed Storm Drainage Improvements

Site grading will incorporate a positive slope away from the building. The existing asphalt and concrete pavement in the area will be removed, the area will be re-graded, and new pavement will be placed to convey storm flows away from the door.

E. Utilities

1. Water Supply and Distribution

This project will not alter any existing water supply and/or distribution lines or provide any new water lines. New bollards will be installed to protect the existing fire hydrant located on the Building's northeast side, near the exterior staircase.

2. Sanitary Sewer

This project will not alter any existing sanitary sewer lines or provide any new sewer lines.

3. Gas Distribution

This project will not alter any existing gas lines . A new gas line will be provided from the building to the new barbeque pavilion area.

4. Power and Telecommunications Distribution

Refer to Section 9 for power and telecommunications site work.

5. Monitoring Wells, Injection/Extraction Wells and Buried Pipelines

This project will not alter any existing monitoring wells, injection/extraction wells or associated buried pipelines and items shall not be disturbed during construction.

F. Fencing, Screen Walls, and Security Walls

The existing chain-link fencing gate leading to the parking lot on the west side of the building will have its hinges removed and replaced.

G. Landscape Design

The trees that are currently touching the northeast perimeter fence will be pruned. The tree that has grown into the northwest perimeter fence, just off the south corner of

Building 8314's north parking lot will be removed. Trees being pruned or removed shall be done outside of the nesting bird season (February 15 to August 15), if this cannot be done, contact Natural Resources to survey the trees. If nesting birds are found, work may be delayed until the young have fledged. The same applies to any nest that may be found on the building. Any questions contact Rhys Evans. 606-4198

The grassy area located on Building 8314's northeast end will be developed with new landscaping and a barbeque area.

Architecture

SECTION 4 ARCHITECTURE

A. General Reference

DD Form 1391 Project Number XUMU 11-1368B.

Statement of Work Statement Of Work For Design Services,– These services include providing 100% design and construction documents for the Repair and Renovation to the Missile Handling Vehicle & Equipment Shop, Project number XUMU 11-1368B at Vandenberg AFB, California.

Vandenberg AFB design guide Facility Excellence Standards, Oct 2010.

UFC 1-200-01 Design: General Building Requirements, 16 August 2010.

UFC 3-600-01 Design: Fire Protection Engineering for Facilities, 26 September 2006.

UFC 4-010-01 Design: DoD Minimum Antiterrorism Standards for Buildings, 22 January 2007.

IBC 2009 International Building Code, 2009 edition.

NFPA Suite National Fire Protection Association, Complete Suite of Documents, latest edition(s).

NFPA 101 Life Safety Code, 2009 edition.

ABA ABA Accessibility Standard for Department of Defense Facilities.

B. General Description

1. The architectural theme for this building shall convey a sense of compatibility and design excellence in the use of complimentary exterior and interior materials, color, and form as described in the Design Excellence Guide and knowledge gained through site research and User meetings. The design for the renovation and repair of facility 8314 shall incorporate materials that are durable, cost effective, and capture as many sustainability principles as possible, while supporting the mission of the building by providing a flexible, efficient, functional, safe, healthy, and comfortable work environment.

2. The scope of work shall incorporate the repair and renovation of the Missile

Handling Vehicle & Equipment Shop (Facility 8314) which includes selective demolition of non-structural walls, ceilings, doors, door frames, interior finishes and other facility components in order to update the existing facility

(as outlined in the concept drawings provided by Vandenberg AFB). Other items of work include repairing existing facility components and constructing new walls. All new exterior openings shall comply and follow AT/FP requirements.

3. Government Furnished and Government Installed (GFGI) Equipment items include the following:

Computers, monitors, printers

Communication and telephone consoles

Video teleconferencing (VTC) equipment

Telephones and fax machines

Copiers

Shredders and safes

Projectors and projector mounts

Auditorium audio-visual equipment

Retreat Pad sound system

Office Furniture

Interior window blinds where needed.

4. The Facility shall conform to the requirements of the ABA Accessibility

Standard for Department of Defense Facilities.

C. Building Code and Life Safety Analysis

Required Codes: UFC 3-600-01 Fire Protection Engineering for Facilities UFC 1-200-01 General Building Requirements NFPA 101 Life Safety Code, 2012 edition NFPA 1 Fire Code NFPA 10 Portable Fire Extinguishers

IBC 2009 International Building Code UFC 3-420-01 Design: Plumbing Systems

General This project is an Alteration under provisions of IBC 3404.

This requires alterations to comply with the current code so that the unaltered portions of the facility remain no less compliant to code than as previously constructed. In addition, under UFC 3-600-01, 1-3.2.2, this project cost is far less than the 50 percent of replacement cost threshold.

As such, the minimum code requirements for the unaltered portions are the NFPA 101 requirements for existing facilities.

Several storage rooms are identified as “hazmat”. The actual nature of hazard must be determined as this could have significant impact on code compliance provisions. For the present evaluation, these areas are assumed to be ordinary hazard storage.

Assembly occupancy is present due to Conference Room 115 on the Ground Floor having over 50 occupant load.

This room exists and is unaltered, therefore will not impose requirements of new construction on the building.

Fire Dept. Access: Maximum 33 feet from building. (UFC 3-600-01, 2-10) Any part of exterior wall not more than 150 feet from access roads; minimum access road width 20 feet; dead-ends more than 150 feet require turn-around for fire dept.

vehicles. (NFPA 1, 18.2.3.2)

Building Floor area: 39,371 SF Ground Floor; 8,962 SF Second Floor (IBC 502.1). Height = 33 feet, two stories

Occupancy Type: Mixed, non-separated:

NFPA 101 Chapter 13 Existing Assembly, Chapter 38 New Business, Chapter 39 Existing Business; Chapter 40 Industrial, Chapter 42 Storage

IBC A-3, B, F-1 and S-1 (note that there are several rooms identified as “Hazmat” which may require an H occupancy classification)

Construction Type: IBC Construction Type VB, with Full Sprinkler System (Table 601)

Required Fire Ratings: IBC Table 601 requires no fire ratings. Construction type includes wood framed partitions. For exterior walls, the actual minimum separation is 22.5 feet (45 ÷2). Required horizontal separation for which no wall protection is required is 10 feet per IBC Table 602 (If H occupancy applies, for less than 30 feet separation, one hour exterior construction is required).

Basic Allowable Floor Areas: IBC Table 503 basic area 6,000 SF, 1 Story, 40 feet height (not considering the possibility of H occupancy).

IBC Floor Area Increases: Increase due to sprinklers = 200 % Area (IBC 506.3); one additional story and additional 20 feet height (IBC 504.2) Increase due to open perimeter = [525÷570-0.25] x 30÷30 = 0.67 Total Allowable Area = 6000 + [6000 x 0.67] + [6000 x 2] =

22,053 SF (IBC 506.1)

Due to shortfall of allowable floor area, the building would be required to be subdivided by a 2-hour fire wall (IBC 706). The wall along F.3 between the maintenance bay and the corridor/stair is recommended for this treatment.

Note: because this project is an alteration, the requirement for area separation does not apply.

Building Height: IBC Table 503 basic height 1 Story, 40 feet; increase 20-feet and one story for sprinklers or 2 stories and 60 feet

Occupant Load: Per NFPA 101, Table 7.3.1.2

GROUND FLOOR

Industrial Use 21142 SF ÷ 100 SF / pers. = 211 Assembly Use 2137 SF ÷ 15 SF / pers. = 142 Storage Use 3173 SF ÷ 500 SF / pers. = 64 Business Use 12919 SF ÷ 100 SF / pers. = 129

TOTAL 546

SECOND FLOOR

Industrial Use 0 SF ÷ 100 SF / pers. = 0 Assembly Use 513 SF ÷ 15 SF / pers. = 34 Storage Use 597 SF ÷ 500 SF / pers. = 2 Business Use 7852 SF ÷ 100 SF / pers. = 79

TOTAL 115

BUILDING TOTAL 661

Number of Exits: Per NFPA 101, 7.4.1.2, 3 exits required

Width of Exits: Per NFPA 101, 12.2.3 Total: 473 x 0.22 inch = 104 inches (Table 7.3.3.1).

Common Path of Travel: Maximum 100 feet (NFPA 101 38.2.5.3.1, 40.2.5, 42.2.5)

Dead-End Corridors: Maximum 50 feet (NFPA 101, 38.2.5.2.1, 40.2.5)

Travel Distance to Exit: Maximum 250 feet (NFPA 101, 40.2.6)

Egress Width Ground Floor 0.2 x 546 = 109.2 inches; Second Floor 0.3 x 115 = 34.5 inches; minimum stair width = 44

Protection from Hazards: No rating; smoke partition. (NFPA 101, 13.3.2.1, 38.3.2 and 8.7). Note that a one hour rating would be required if for any rooms that include processing or use of hazardous materials.

Interior Finish: Class A or B in corridors and Class A in stairs. Floor finish in exits and corridors shall be not less than Class II (NFPA 101, 13.3.3, 38.3.3 and 10.2)

Detection and Alarms: Fire alarm system required (NFPA 101, 13.3.4.2, 38.3.4, 40.3.4, 42.3.4, 9.6.1); initiation by manual means and sprinkler system with emergency power source; notification by audible and visual alarm; a positive alarm sequence system is permitted. A constantly attended receiving station within the building is required unless deemed impractical by AHJ.

Corridor Construction: Protective construction not required due to sprinkler system.

(NFPA 101, 38.3.6.3, 40.3.6, 42.3.6). However, local governing authorities have instructed Architect to provide a One Hour F.R.

egress corridor(s) with 20 min FR Doors.

Doors: Doors within altered or new spaces are required to swing in direction of travel for occupant loads of 50 or more. (NFPA 101, 38.2.2.2)

Roof Access: Not required due to less than three stories. (UFC 3-600-01, 2-9)

Fire Extinguishers: Class A fires (ordinary combustible materials); maximum 11,250 SF per extinguisher; maximum 75 foot travel distance to extinguisher; maximum 3,000 SF per unit of A (NFPA 10).

Recessed or semi-recessed cabinets required. (UFC 3-600-01, 4-9.1)

Plumbing Requirements: Requirements per UFC 3-420-01; female occupants – 198 (30%); male occupants – 463 (70%); total population – 661:

Female Male

Water Closets 8 10

Urinals 4

Lavatories 7 13

Drinking fountains 9

Service Sink (per floor) 1

Note: existing restroom fixture count is below the requirement for new construction, however because this is an alteration which does not affect the restrooms, increase of fixture count is not required.

D. General Building Description

1. Building 8313 is a two story structure; approximately 48,736 SF built in 1960. The building is constructed of block wall, poured in place concrete, and steel framing with corrugated metal wall panels with exposed fasteners on the exterior. The exterior work shall consist of replacing some of the doors, windows, louvers and metal panels in areas of unsightly wear and existing damage. The lean-to structure on the northeast side of the high bay structure will not receive any work apart from some minor exterior repair to the exterior metal panels.

2. Existing interior wall finishes include; gypsum board and painted CMU walls with floor finishes that include carpeting, resinous coating, ceramic tile and vinyl tile.

Existing ceilings are either suspended 2’x4’ acoustical tile or metal framed gypsum board. The existing suspended acoustical ceiling systems shall be replaced in areas of wall demolition and replaced with matching, new 2’x4’ acoustical tile system. Some intersecting corridor areas will include suspended gypsum board bulk heads in the ceiling to provide a termination point for different ceiling grid layouts.

3. AT/FP standards are used in the specification of windows, window frames, curtain wall and glazing and their connections to structure. Windows are fixed with heavy aluminum framing with minimum 70 percent polyfluorovinylidine bronze finish to match the roof and trim color. The windows are glazed with 1 inch thick insulating units. The outer pane is gray tinted, low-e coated, ¼ inch thick, heat strengthened glass. There will be an inter-layer of ½ inch dehydrated air. The inner pane is nominal 1/4 inch, clear laminated glass.

Interiors

SECTION 5 INTERIORS

A. General

Excellence in interior design and meeting the requirements outlined in the scope of work are the primary goals for the project. The design shall incorporate and include applicable building codes/regulations and LEED responsible material resourcing.

The Structural Interior Design package includes the selection, specification and coordination of interior finishes and equipment that are integral to or attached to the building structure. The general interior features that are within this scope-of-work are: replacement of some walls, wall finishes, floor finishes, ceilings, trim, doors, door frames, door hardware, installed equipment, light fixtures, plumbing fixtures and signage as outlined in the concept drawings provided by Vandenberg AFB. All products shall be specified to comply with all applicable building codes and regulations as stipulated in the project scope of work. The documents required to articulate the Structural Interior Design intent and the specific details include:

Architectural Floor Plans, Interior Finish Plans, Signage Location Plans, Interior Elevations, Schedules, Legends, and Details. Written product specifications and physical samples are keyed to the drawings and other documents for reference. All necessary submittal documents, construction document drawings, details, Interior Elevations, Interior Finish

Selections, Specifications, coordination, RFP response, cost controls and adherence to the budget for the Interior Design of this project, are being provided by and all responsibilities assumed by the Owner.

B. STRUCTURAL INTERIOR DESIGN (SID) INTENT:

The design intent is based upon discussions with the end-user regarding their functional needs to support the mission. The end-user selected conceptual design intent for the interior finishes color scheme. The color scheme acts as a psychological counterpoint to the end-user’s mission. Neutral wall colors balance the saturated accent colors and maintain a professional atmosphere. Dark neutral floorcoverings with bright accent colors create visually stimulating patterns and are low maintenance. The industrial/technological environment is continued in the administrative and ancillary support areas with the same color-palette and limited use of saturated colors. Practical and durable material selections withstand the

Interiors physical demands of the mission and reflect the specific functional requirements of each space. All materials are low maintenance and have high ROI through their life-cycle cost.

Areas that are subject to high-abuse/wear have appropriate hard-wearing finishes include solid vinyl tile and/or porcelain pavers, high-abrasion-resistant paints and specialty coatings, special wall-guard coverings and corner guards. Administrative/office areas have solution-dyed modular carpet, abrasion-resistant paint and corner guards. Rubber cove base is specified for solid vinyl tile flooring and epoxy floor paint. Carpet base is specified for areas receiving carpet flooring. Porcelain base is specified with porcelain paver floors. Restrooms have solid surface counter tops, ceramic tile wainscoting and stainless steel toilet accessories. All interior design finishes will be selected by the Owner who has assumed all responsibility for their ability to perform and meet all design criteria established by the Design

Guidelines.

Structural

SECTION 6 STRUCTURAL

A. General Reference

1. The following Unified Facilities Criteria (UFC) are used as design criteria:

UFC 1-200-01, General Building Requirements (16 August 2010), with Change 2 (28 November 2011)

UFC 3-301-01, Structural Engineering (27 January 2010), with Change 3 (31 January 2012)

UFC 3-310-04, Seismic Design for Buildings (1 May 2012)

UFC 4-010-01, DoD Minimum Antiterrorism Standards for Buildings (9 February 2012)

UFC 4-010-02, DoD Minimum Antiterrorism Standoff Distances for Buildings (9 February 2012)

UFC 4-020-01, DoD Security Engineering Facilities Planning Manual (11 September 2008)

2. The following industry standards, codes, and specifications will also be used as design criteria:

American Concrete Institute (ACI) Publications

ACI 318, Building Code Requirements for Structural Concrete and Commentary (2008)

ACI 347, Guide to Formwork for Concrete (2004)

ACI 530/530.1, Building Code Requirements for Masonry Structures and Specifications for Masonry Structures and Related Commentaries (2008)

ACI SP-4, Formwork for Concrete (2005)

ACI SP-66, ACI Detailing Manual (2004)

American Institute of Steel Construction (AISC) Publications

AISC Steel Construction Manual (13th Edition, 2005)

AISC Seismic Design Manual (2006)

AISC Steel Design Guide 3, Serviceability Design Considerations for Steel Buildings (2nd Edition, 2003)

American Iron and Steel Institute (AISI) Publications

AISI Design Guide D110-07, AISI Cold-Formed Steel Design Guide – Second Edition and Referenced Standards

American Society of Civil Engineers (ASCE) Publications

ASCE 7 Minimum Design Loads for Buildings and Other Structures (2005)

American Welding Society (AWS) Publications

AWS D1.1/D1.1M, Structural Welding Code – Steel (2004)

AWS D1.3/D1.3M, Structural Welding Code – Sheet Steel (1998)

FM Global (FM) Publications

FM DS 1-28, Property Loss Prevention Data Sheet 1-28 Design Wind Loads (2005)

International Code Council (ICC) Publications

IBC 2009, International Building Code (2009)

Steel Deck Institute (SDI) Publications

Steel Deck Institute (DDM2), Diaphragm Design Manual (2nd Edition, 1987)

Steel Deck Institute (DDM3), Diaphragm Design Manual (3rd Edition, 2004)

Steel Deck Institute (DM), Design Manual for Composite Decks, Form Decks, and Roof Decks (Publication No. 30, 2000)

Underwriters Laboratories (UL) Publications

UL 580, Standard for Tests for Uplift Resistance of Roof Assemblies (1994;

with Revisions through Feb. 1998)

B. Design Criteria

1. Structural design loading criteria shall be developed using site and project specific criteria in conjunction with the codes and design criteria indicated above.

2. The Missile Handling Facility is classified as a Category II building for wind and seismic per ASCE 7-05, and UFC 3-301-01.

3. Dead Loads

Minimum dead loads are in accordance with ASCE 7-05. Dead loads include the weight of all permanent materials and equipment supported in or on a structure, including the structures own weight.

4. Live Loads

Minimum live loads are in accordance with UFC 3-301-01 and ASCE 7-05 as follows:

AREA LOADS

Stairs and Landings 100 psf, minimum; 300lbs concentrated load on stair tread

Slabs on Grade 125 psf (per original As-built drawings)

Roof Per ASCE 7, min. 20 psf

5. Wind Loads

Wind loads are designed for a Basic Wind Speed (3-Second Gust Speed) of 85 mph and Exposure C in accordance with UFC 3-301-01 and IBC 2009.

6. Seismic Loads

Minimum building seismic requirements are in accordance with UFC 1-200-01, UFC 3-301-01, and IBC 2009. The building classification and applicable ground motion are determined by their use and geographical location. Per UFC 3-301-01, seismic accelerations are as follows: Ss = 1.38g (maximum), Ss = 1.05g

(minimum), S1 = 0.49g (maximum) and S1 = 0.36 (minimum).

7. Lateral Partition Loads

Minimum design pressure on interior stud partition walls is 5 psf.

8. Deflection Criteria

Roof, floor, and lateral deflections shall conform with Section 2-1.2.3 of UFC 3-

301-01.

9. Foundation Design Criteria

The design of new foundations for the stair canopy and barbeque pit are based on the recommendations provided in the soils report for a facility near the project site in conjunction with the soils information provided in the original As-built drawings, dated June 1959. Due to the secondary nature of these structures, the soils information provided in the above documents is sufficient.

C. Basic Materials of Construction

1. Concrete

Materials, design and construction complies with ACI 318. Detailing of reinforcement complies with ACI SP-66 in addition to ACI 318. Formwork complies with ACI 347R and ACI SP-4.

Concrete: Minimum 28 day compressive strength will vary depending on the structural element. The concrete strengths are f’c = 3000 psi for foundations and f’c = 4000 psi for concrete slab on grade repairs and concrete trench infill.

Reinforcing Steel: ASTM A615, Grade 60, deformed, including stirrup and ties. Use ASTM A706, Grade 60 for reinforcing requiring welding, where required.

2. Masonry

Materials, design and construction comply with UFC 3-301-01.

Mortar: ASTM C270, Type S.

Normal weight masonry units.

Wall assembly compressive strength, f’m = 1,500 psi.

3. Metals

Structural steel grades shall be the “preferred” grade per Table 2-3 of the

AISC Steel Construction Manual.

Anchor Bolts: ASTM F1554, Grade 36.

D. Structural System Description for New Structural Elements

1. Foundations provided for the exterior stair canopy and barbecue pit will be based on an existing soils report for an adjacent site, which will be provided by the base, still pending. Together with the information provided in the as-built built drawings, conservative soil design parameters have been deduced. The soils in the area where the project site is located appear to be non-expansive in nature; and the existing facility is founded on a shallow foundation system. It is anticipated that the foundation system for the new elements will be a shallow system as well.

2. The new canopy over the existing exterior stairs utilize a light tube steel framing system. The structural system shall be composed of a mono-sloped steel roof deck and exposed structural tube steel beams and columns. Structural steel moment resisting and braced frames shall be used to resist lateral loads. Existing building elements will be taken into consideration with regards to adversely loading/overloading these elements with the new canopy framing and loads.

Where feasible, the existing stair bracing will be utilized as part of the lateral system of the canopy to help control deflection.

3. The new barbecue pit will consist of a reinforced CMU base and back-splash wall and a reinforced concrete slab countertop, similar to an existing barbecue located elsewhere on base.

4. New architectural, mechanical, and electrical elements hung from the existing structure shall be braced per the ATFP requirements and seismic requirements.

E. Antiterrorism Force Protection

The modified and added elements of the facility shall meet all requirements of the “DoD

Minimum Antiterrorism Standards for Buildings” (UFC 4-010-01). The building shall be located within a controlled perimeter. The site layout shall provide adequate standoff distance for the building so that conventional construction may be used. The building

Level of Protection shall be determined in accordance with the “Minimum Antiterrorism

Standards for Buildings”. Per the ATFP officers, a 220-pound explosive weight shall be used in the design of the glazed opening supports.

Mechanical and Plumbing

SECTION 7 MECHANICAL AND PLUMBING

A. Mechanical Design Criteria

1. Heating, ventilating, air conditioning (HVAC) and plumbing systems are designed to conform to the publications listed.

Codes, Standards and Regulations

ASHRAE Latest edition of handbooks and standards.

IMC International Mechanical Code, 2009.

IPC International Plumbing Code, 2009.

NFPA National Fire Protection Association, applicable sections.

SMACNA Latest edition of handbooks and standards.

2. Space Design Conditions

Room 113 PREL Laboratory:

Summer & Winter: 67°F*, (No limit control for RH)

*The PREL Laboratory requires that the room be able to maintain a temperature range between 60°F and 74°F. Thus, the design condition was set in the middle of the required temperature range.

Service Areas Provided with Heating and Ventilation : FMS Equipment, Tool &

Hazmat Storage and EMT Equipment, tool & Hazmat storage

Summer: 76°F, No low limit control for RH Winter: 68°F, No low limit control for RH

Occupied Areas with HVAC, served by existing system: New offices

Summer: 75°F Winter: 68°F

3. Outdoor Design Conditions

Summer (1% DB): 76°F Dry Bulb (DB), 60°F Wet Bulb (WB) Winter: 37°F

4. Energy Sources

The available energy sources are electricity and natural gas.

5. Design Calculations

HVAC heating and cooling load calculations are accomplished using the Trane

Trace 700 Comprehensive Building Analysis, Version 6.2.8.3.

6. General interior loads.

Space Type Equipment Lighting

Room 113 11.0 W/sq.ft. 1.0 w/sq. ft.

7. Minimum Ventilation/Exhaust Quantities

Space Type Min. CFM/sq. ft.

General Per ASHRAE 62.1-2007 Restrooms 75 cfm/toilet, minimum 2 CFM/sq. ft.

Storage (107,113, 119, 124C) Per ASHRAE 62.1-2007 1.5 CFM/sq. ft

8. Sound Criteria

The following Noise Criteria (NC) establishes the maximum permissible ambient noise levels within the buildings:

All spaces except below NC-40 Lobbies, classrooms NC-35 Auditorium NC-25 Offices/Conference Rooms NC-35 Toilets, corridors NC-45 Mechanical / electrical rooms Service / mechanical space NC-60

9. Ventilation System

The existing building is provided with ventilation air, and it is assumed to meet the minimum requirements of ASHRAE Standard 62.1. Because the building occupancy will not increase, it is assumed the current ventilation provided by the existing variable air volume system is sufficient and will not need to be increased.

The exhaust fan serving the existing restroom system will be replaced.

The PREL laboratory has been designed for a storage ventilation rate per

ASHRAE Standard 62.1 as air classification 4. Per the information provided, the design assumes the chillers tested in the room will have a total quantity R-22 and

R-134a under the threshold for the requirements of a machinery room per

ASHRAE and the IMC.

The equipment and tool storage rooms (107, 119, 124C) have been designed for a storage ventilation rate per ASHRAE Standard 62.1 as air classification 4. Air class 4 air shall not be recirculated or transferred to any space nor recirculated within the space of origin. A dedicated exhaust fan for the rooms that is spark proof and explosion proof is provided. The makeup air for the rooms shall come from the adjacent spaces ceiling plenum. Exhaust fans shall run 24 hours per day, 7 days per week and shall signal an alarm if de-energized due to failure.

10. DDC Systems

New equipment will be connected to the existing Direct Digital Control (DDC) system.

B. HVAC System

The existing, non-operational heating and ventilating unit HV-1, shall be removed. The

PREL laboratory shall be provided with a new dedicated, split system heat pump.

Multiple evaporative units in combination with heat pumps will provide conditioned air to the room. The heat pump units located outside next to the building will have an anticorrosion treatment to protect against salt corrosion.

The remaining spaces that were served by HV-1 (Room 107, Room 119, Room 120, and Room 124C) shall be served by a new heating and ventilating unit.

The new offices and FMS storage (Room 116, Room 117 and Room 118) will be conditioned by the existing variable volume Air Handling Units (AHUs). A new VAV terminal unit will be provided for these offices.

To evaluate the cooling provided in Room 110, per the statement of work, a heat gain calculation was completed for the room. The calculation assumed that the heat gain from the 500 kVA transformer located in the room was 25 Watts per kVA. The results of the calculation indicated that the current airflow provided to the room from the existing

VAV system would be sufficient for cooling the equipment as required.

C. Plumbing System

1. General Plumbing Fixtures

a. Existing manual water closets and Urinal flush valves will be replaced with infra-red sensor/ manual push button (1.6 gallons per flush for water closets and 0.25 gallons per flush for urinals) flush valves. It is assumed that existing water pressure is sufficient for proper system operation.

b. Existing lavatory sinks and faucets will be replaced. New lavatories will be countertop-style with infra-red sensor activated electronic faucets.

c. Existing inoperative water fountains will be removed. New combination filtered water cooler and bottle filling station will be provided.

d. A natural gas line will be provided to the Bar-B-Que pavilion. Refer to civil for more information.

SECTION 8 FIRE PROTECTION

A. Fire Protection Design Criteria

The Fire Protection (FP) system is designed to conform to the publications listed.

Codes, Standards and Regulations

NFPA 10 Portable Fire Extinguishers, 2010.

NFPA 13 Installation of Sprinkler Systems, 2010.

NFPA 72 National Fire Alarm Code, 2010.

NFPA 101 2009 Life Safety Code.

UFC-3-600-01 Design: Fire Protection Engineering for Facilities, Change 1, 14 July 2009.

UFC 4-021-01 UFC Mass notification systems, 2008.

2009 IBC International Building Code.

B. Building Description

1. A detailed building code analysis is provided in the Architecture Section. This section includes a narrative on occupancy type, occupancy load, egress requirements, construction type, required fire ratings and fire extinguisher requirements.

2. The building is protected by an existing wet pipe sprinkler system.

C. Occupancy Hazard Classification

The building has two types of occupancy hazards. For the purposes of determining automatic sprinkler densities the following classifications are used:

Light Hazard - Offices, classrooms, break area, toilets.

Ordinary Hazard, Group 1 – Storage Rooms, Communications Room, Mechanical Room, Electrical Room.

D. Water Flow Demand Criteria

1. Light Hazard

Design Density: 0.10 gpm/square foot

Design Area: 3000 square feet

Hose Allowance: 250 gpm

Duration: 60 minutes

2. Ordinary Hazard, Group 1

Design Density: 0.15 gpm/square foot

Design Area: 3000 square feet

Hose Allowance: 500 gpm

Duration: 60 minutes

E. Fire Suppression System

The existing fire suppression system shall be modified to accommodate the new room layout. The design density and design area correlating to the hazard level of the new room layout shall be used to determine if additional sprinkler heads or increased flow are required. In rooms where drop ceilings are added, upright pendant heads shall be replaced with recessed sprinkler heads to match those installed in other finished areas.

Installation, testing, and bracing of the sprinkler system shall be in accordance with

NFPA 13.

F. Fire Alarm and Mass Notification System

An existing Cerberus Pyrotronics (now part of Siemens Fire Safety division) fire alarm control panel (FACP) is located in the main Electrical Room. It is assumed that the existing FACP has adequate space for the new devices. The existing FACP will monitor all new devices including manual pull stations, horn/strobe devices and strobes for the first and second floor renovated spaces. Existing devices labeled for demolition shall be removed and the contractor shall be required to provide a new circuit and battery calculation with the new devices added.

Occupant notification utilizing a combination of strobes and horn/strobes with white faceplates marked “FIRE” are provided throughout the renovation in accordance with

NFPA 72, and the UFC’s. All strobes employ clear lenses. Occupant notification is activated upon any fire alarm signal initiated by a manual pull station, sprinkler water flow switch, or common area smoke or heat detector. All Signaling Line Circuits (SLCs) are Class A, Style 6 and Notification Appliance Circuits (NACs) are Class A, Style Z.

The facility does not currently have a mass notification system (MNS). The scope of work did not call for a MNS to be provided under this design. Per UFC 4-010-01, the non-bay area is considered an inhabited building. UFC 4-021-01 requires that all renovations exceeding 50% of the replacement value (as defined in UFC 4-021-01) shall have a MNS installed. As this project does not pass that threshold, a MNS is recommended but not required.

SECTION 9 ELECTRICAL AND COMMUNICATIONS

A. General

1. The following industry standards are used as the design criteria for the project:

ANSI C2 National Electrical Safety Code (2012)

BICSI Telecommunications Distribution Methods Manual (TDMM), 12th Edition

ETL 02-12 Communication and Information System Criteria for Air Force Facilities (Jun 2002)

IESNA Illumination Engineering Society of North America Lighting Handbook, 10th Edition

UFC 3-501-01 Electrical Engineering (2010)

UFC 3-520-01 Interior Electrical Systems (2010)

UFC 3-530-01 Interior and Exterior Lighting Controls (2006)

UFC 3-580-01 Telecommunications Building Cabling Systems Planning and Design (2007)

UFC 4-010-01 DoD Minimum Antiterrorism Standards for Buildings (2012)

NFPA 70 National Electric Code (2011)

NFPA 72 National Fire Alarm Code (2010)

NFPA 101 Life Safety Code (2012)

TIA/EIA 568-C Commercial Building Telecommunications Cabling Standard (2009)

TIA/EIA 569-C Commercial Building Standard for Telecommunications

Spaces and Pathways (2009)

J-STD-607-A Commercial Building Grounding and Bonding

Requirements for Telecommunications (2002)

Vandenberg FES Vandenberg AFB Facilities Excellence Standards (2010)

B. Electrical Power Systems

1. Existing Interior Power: The facility has an existing power distribution system consisting of panels, conduits and conductors from the original construction as well as from various upgrades. The existing system consists of 12kV to 480/277V

750kVA utility transformer terminating in a 1000A Main Switch Board (MSB) with a

900A trip main circuit breaker. The system contains 480/277 volts, 3-phase, 4-wire with 208Y/120 volt step down, dry type transformers located throughout the facility to accommodate general receptacle and smaller power loads. Lighting and transformer loads are served at 480/277 volts. Small motor loads and convenience receptacles are served at 120/208 volts. Many of the distribution panels were upgraded during a 1998 renovation. The MSB and select main distribution panels (DP) were not replaced at this time.

2. New Interior Power: The new electrical work shall consist of the following to support the project renovation:

Branch circuiting for the renovated spaces. The demolished circuits and new circuits shall originate from the panels provided in the 1998 renovation. These panels appear to be in good physical condition and will not be replaced.

Lighting loads shall be provided at 277V.

Convenience receptacles shall be provided at 120V. Receptacles shall be

NEMA 5-20R. Each new office shall be provided with a minimum of (4) general-purpose duplex outlets in each room. One duplex receptacle shall be located every 50ft of wall space in corridors with a minimum of one receptacle per corridor. Receptacle locations shall be coordinated with conference room equipment, including wall and/or ceiling mounted devices.

Select conduits and conductors will be re-used for receptacles. These circuits will remain but the receptacle and faceplates will be replaced.

Two existing panels (P1D and L1C) will be removed and reinstalled on a new wall. A new pull box shall be provided to intercept and extend the conduits and conductors associated with these panels. Pull box shall be located in ceiling above existing panel locations.

Existing transformer (T-4) shall be relocated from its current location in room 113 to electrical room 123 and provided with a concrete housekeeping pad. It is anticipated that the existing primary conductors shall be reused. New secondary conduit and conductors shall be provided from the transformer to the load in the PREL Lab.

Power distribution to all renovated areas, including all feeders and branch circuit wiring shall be in conduit. Conduit concealed in walls shall be of type

EMT with minimum size of 3/4” in. Conduit exposed in electrical rooms, shall be rigid galvanized steel conduit (RGS). All conductors shall have

THHN or THWN 75 degree C insulation and all branch circuits shall be minimum #12 AWG. Conductors shall be color coded by voltages as required per code.

Each new or altered piece of floor mounted electrical equipment shall be secured to a concrete housekeeping pad.

Ground Fault Circuit Interrupters shall be either the receptacle type or the circuit breaker type, as appropriate.

New electrical equipment shall be installed to meet seismic standards.

To the best of the engineer’s ability, the facility’s electrical power distribution system shall be designed with a minimum 20% spare capacity and a minimum 20% spare circuit breaker spaces.

3. Power Quality and Grounding. All feeders and branch circuits to lighting, receptacles, and switches shall be provided with a copper ground conductor.

Raceway system shall not be used for a ground path. Oversized neutral conductors shall be used for non-linear load electrical circuits to ensure that current harmonics do not exceed system ampacity.

4. Special Conditions. Some of the spaces have been labeled as Classification 1, Division 2 (C1/D2) due to the chemicals being stored in the spaces. These spaces shall be outfitted with the proper C1/D2 pathways, including explosion proof junction boxes, sealed fittings, etc.

C. Lighting Systems

1. Interior Lighting: The new interior lighting work shall be as follows to support the project renovation:

Dual technology (passive infrared/ultrasonic) occupancy sensors shall be provided in rooms based upon users’ needs and room functions.

Otherwise, local switching shall be provided to enable the user to control energy usage by turning off lights when not required.

Circulation areas shall utilize ‘night lighting’ in order to maintain NFPA

101 ‘Life Safety’ requirements.

Provide lighting systems throughout the facility in accordance with UFC

3-530-01, Interior and Exterior Lighting and Controls, the Illuminating

Engineering Society (IESNA). UFC 3-530-01 provides minimum target lighting levels. Standardize on fewest possible lamp and wattage types to simplify stocking of replacement lamps. Exit lighting fixtures shall be located per NFPA 101 requirements and shall be low energy LED type.

General open and private offices, conference rooms and corridors shall be illuminated with 2’ x 4’ fluorescent luminaires with high efficiency electronic ballasts and 27 cell parabolic reflectors. While this does deviate from the Facilities Excellence Standard, it does conform to the currently installed lighting system in the facility. Select hallways locations shall utilize compact fluorescent downlights. Conference rooms shall utilize multiple lighting zone and use fluorescent luminaires with perimeter fixtures wired to a separate lighting zone. Restrooms shall be outfitted with compact fluorescent downlights near the sinks.

All linear fluorescent lamps shall be T8 high efficiency, low/reduced mercury type with a color temperature of 3500 degrees Kelvin and a

CRI of 80 or better. All lighting shall be powered by 277V circuiting for high efficiency power distribution. Select fixtures throughout the facility shall be used for emergency egress and night lighting; these fixtures shall be equipped with battery back-up. All exit luminaires shall be equipped with battery backup and shall use green LED’s on a white field for illumination. Recessed, directional lighting shall be provided where casework or artwork are present.

Utility areas having unfinished ceilings such as electrical, storage and other utility rooms shall have industrial fluorescent fixtures with wire guard.

Areas determined to be Class 1, Division 2 (C1/D2) shall be provided with fixtures qualified to be installed in this environment.

The following maintained illumination levels are based on IESNA recommendations and shall be used during design:

Area Luminaire Illumination Level

General Use Area parabolic 30 fc

Corridors parabolic 20 fc

Storage spaces parabolic 25 fc

Conference parabolic 0-30 fc stepped

2. Exterior Lighting: The new exterior lighting work shall be as follows to support the project renovation:

The exterior stairway shall be illuminated with LED fixtures. One LED wall pack will be removed to accommodate the new stairway structure.

LED fixtures shall be provided under the canopies at each stairway landing, affixed to the new stairway canopy structure, to illuminate the pathway.

D. Communications and Data Systems

1. Telecommunication Existing Conditions: There are two existing telecommunications rooms within the facility, one per floor. Each room is equipped with an open frame rack. There is adequate space for additional equipment. Based on site observation, the cabling is a mixture of CAT-3 and CAT-

5e. The telecommunications room is shared with electrical distribution equipment.

2. Telecommunications Interior Requirements: The new telecommunications work shall be as follows to support the project renovation:

Coordinate all communications and data requirements with 30th Space

Communications Squadron.

Telecommunications infrastructure includes wired jacks throughout the renovated spaces with jacks for each workstation or desk. The government furnished, government installed systems furniture does not have a space allocated for furniture integrated jacks. Jacks for these items will be provided at the wall and the user will provide patch cords.

Jacks shall be provided for all offices, workstations, conference rooms, etc. Wall jacks shall be located as needed to support furniture, printing and copy areas. Telecomm wiring shall be routed in a combination of conduit, cable tray and j-hooks and terminated at the existing rack.

New patch panels shall be provided at each rack for new CAT-6 cabling.

New telecommunications cabling shall be Category 6, plenum rated, Unshielded Twisted Pair (UTP) for voice/data communications. Both voice and data shall be blue in color.

Cabling Requirements: The voice/data system shall conform to EIA/TIA

568C1 Category 6 and shall utilize 4-pair 24 AWG copper cables.

Category 6 cable shall terminate on rack mounted 8P8C category 6 modular patch panels in the telecommunications rooms.

Outlet Requirements: All outlets shall have one Category 6 data cable and one Category 6 voice cable terminated on Category 6 - 8P8C jacks.

Cable Pathways: In general, voice and data cabling shall be routed from the outlet locations in a combination of conduit, cable tray and j-hooks to the telecommunications rooms and terminated at LAN rack patch panels. Patch panels shall be provided with 20% spare capacity.

P ro je ct

K ic ko ff

M ee ti n g M in u te s

Meeting Minutes

Repair/Renovate Missile Handling Vehicle & Equipment Shop – Vandenberg AFB 11 September 2012 – 10:30 AM Project Name Meeting Date & Time

Teleconference 62017525 Location of Meeting Merrick Project Number

Kickoff Teleconference 1 of 2 Type of Meeting Page

Attendees:

Doug Reniker – AFCEE Roby Gregg – AFCEE Guy Cecil - VAFB Sergeant Hagger - VAFB Richard Heslop - VAFB Major Henderson - VAFB Luke Souhrada – Merrick John Greenlee – Merrick Kevin Breslin – Merrick Russ Odum – Merrick Megan Huerter – Merrick Brenda Rollheiser – Merrick Eric Maughan – North Wind

Introduction:

The members of the team were all introduced and their roles in the project were briefly discussed.

Richard Heslop will be filling in for Jeremy Belton for the beginning of this project.

Doug Reniker stated that any changes that affect the cost or period of performance for the project can only come from the Contracting Officer.