FA4610-15-R-0006_Conformed_Through_Amendment_0001.pdf
PDF 661 KB Posted
- Attached to
- Replace Waterline at Space Launch Complex (SLC) 2 Federal contract opportunity
- Solicitation number
- FA4610-15-R-0006
About this file
FA4610-15-R-000 6 Conformed Through Amendment 1
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SLC-2_Area_Utilities.pdf | ||
| Questions_and_Answers.docx | DOCX document | |
| FA4610-15-R-0006-0001.pdf | ||
| Att_3_35percent_Design_Drawings 1 .pdf | ||
| Att_4_RMDF.pdf | ||
| Att_5_DBA_CA150023_2_Feb_15.pdf | ||
| Att_2_35percent_Technical_Specifications 1 .pdf | ||
| Att_1_SOW_XUMU131186B1_WaterlineSLC2.pdf | ||
| FA4610-15-R-0006.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA4610-15-R-0006-0001
F4D3D95028AG03
1. This requirement is being set aside in accordance w ith FAR 19.1505(b) and is being considered for aw ard to an eligible Economically
Disadvantaged Woman-Ow ned Small Business.
2. Aw ard of this solicitation w ill result in a f irm-fixed-price contract.
3. Negotiable Period of Performance of 240 calendar days.
4. Specif ications: See Section J.
5. The magnitude of construction is betw een $1,000,000 and $5,000,000.
6. NAICS: 237110, Size Standard $36.5M
7. A tentative pre-proposal site visit is scheduled for 15 May 2015 at 0900.
8. This solicitation is being issued in accordance w ith Authority to Advertise letter dated 19 December 2014.
9. Notice to offeror(s)/supplier(s): Funds are not presently available for this effort. No aw ard w ill be made under this solicitation until funds are available. The Government reserves the right to cancel this solicitation, either before or after the closing date for receipt of proposals. In the event the Government cancels this solicitation, the Government has no obligation to reimburse an offeror for any costs.
10. The proposal price needs to be good through 30 September 2015.
NATALIE N. BERNAL 805-606-1603
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
07-May-2015
(RFP)
(IFB)
X
CALL:
Replace Waterline in SLC2 Area
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________240 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________08 Jun 2015 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, X is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______113 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
FA4610 - 30TH CONS
1515 ICELAND AVE. (BLDG 8500), RM 150
VANDENBERG AFB CA 93437-5212
FA4610
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
03:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
XUMU13-1186B1
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: TEL: FAX:
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued)
(Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
FA4610-15-R-0006
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job Replace SLC 2 Waterline
FFP
The contractor shall replace the SLC 2 waterline in accordance with the Statement of Work in Section C and other attachments identified in Section J.
FOB: Destination
NSN: Z2JZ-00-000-0000
PURCHASE REQUEST NUMBER: F4D3D95028AG03
SIGNAL CODE: A
NET AMT
PSC Code: Z2JZ
Section C - Descriptions and Specifications
STATMENT OF WORK
STATEMENT OF WORK
Delivery Method: Design-Build (D-B), FFP
Replace Waterline in SLC2 Area
Vandenberg AFB, CA
Project # XUMU 13-1186B1
28 May 2015
1.0 INTRODUCTION
The work to be conducted under this Contract shall be done under the general conditions contained herein. This
Contract shall be accomplished using the Design-Build (DB) delivery method.
2.0 SCOPE OF WORK
2.1 SCOPE & APPLICABLE DOCUMENTS
This Statement of Work (SOW) sets forth the requirements for a FFP Contract design and construction effort at
Vandenberg AFB, CA. The Contractor is to provide the government with a complete engineering design, construction, and warranty for the waterline replacement to meet current Air Force Standards identified below.
2.2 DESCRIPTION OF WORK
As part of the proposed effort on this contract, the Contractor shall implement the following tasks for the completion of this project. The Contractor’s proposal shall include information on each type of equipment they are bidding to install (i.e. cut sheets from the manufacture).
2.2.1 General Description of Project:
The Contractor is to design and build (D/B) improved replacements to a portion of the existing potable domestic water distribution system at Vandenberg Air Force Base, (VAFB) CA in accordance with the criteria contained in the
35% Concept Design, 35% Technical Specifications, and industry standards. Existing piping material is primarily ductile iron (DI), cast iron (CI), asbestos cement (AC), and polyvinyl chloride (PVC) that has reached the end of its life and is to be capped and abandoned in-place after replacement with new high density polyethylene (HDPE) piping. The waterline replacement consists of designing and replacing portions of waterlines of various sizes
(approx. 4” to 14” diameter) and all their associated valves, hydrants, and other appurtenances required for a complete and functioning system. Specifically, the design and construction shall be completed for the sections identified in the 35% Concept Design as A3-Line Station 10+00 through Station 29+08 only, and L1-Line through
L5-Line. This group of lines is serves facilities within and immediately surrounding the SLC 2 area.
PRINCIPAL FEATURES OF WORK:
1) The Contractor shall be responsible for the professional quality, technical accuracy and coordination of all designs, drawings, specifications and other documents or publications upon which construction is based. The design of the water distribution lines, piping and mechanical features, civil and other engineering features of the work shall be accomplished, reviewed, approved and sealed by engineers who are licensed professionals with a minimum of six years’ experience in the state or California.
2) Contractor shall submit design plans for approval and obtain permits from local jurisdictions to comply with safe drinking water standards. The design and construction of this project shall conform to all requirements of the State of California for permitting as a potable water system and the requirements contained in the solicitation including all referenced criteria. The Contractor’s design shall include all the piping, valves, and appurtenances and shall comprise a complete and functional water distribution system. The drawings attached are notional and show the extent of the system to be replaced. Design and construction shall be phased to minimize outages.
3) The 35% Concept Design indicates the general location of the water distribution lines and appurtenances, approximate sizes and types, approximate locations of service connections and other system parameters. These drawings are preliminary and may not show all required appurtenances for the water system. It is required of the Contractor to complete the design of the system and include any valves, etc. (if any) that are required for a complete functioning system.
The drawings indicate the approximate lengths of piping to be either replaced with new pipe with open trenching or using an approved trenchless technology. The alignment of any new piping shall follow the general location of the existing piping to the extent that is feasible. The Contractor’s design shall be limited to the general extents of the Project site shown in Government’s preliminary design drawings.
4) The Government’s preliminary drawings in the contract documents illustrate intent and functional relationships and do not indicate all necessary construction requirements or components; the 35%
Concept Design and 35% Technical Specifications describe associated technical, performance and systems requirements. The Contractor is responsible for the complete project design, shall retain all responsibilities, and be recognized as the Designer of Record.
5) Routings and sizing of piping shown on attached drawings provide preliminary piping requirements for the distribution system. The Contractor shall perform an engineered hydraulic design analysis of existing conditions at VAFB to confirm the sizing and valving shown on 35%
Concept Design drawings is appropriate for project and site-conditions. The Contractor shall collect needed information from existing system and user needs to design and size new water distribution system to meet pressure and flow requirements of base and Code requirements of potable and fire water distribution systems. The Contractor shall provide calculations leading to sizing of distribution systems, selection of equipment, and domestic water pipe size.
The Contractor shall implement this contract in two phases: the design phase and construction phase.
2.3 DESIGN PHASE
The Contractor shall complete development of plans and specifications in accordance with defined levels of effort necessary to construct the project and provide as-built drawings (both electronically and in hard copy) for retention by the Government. The Contractor shall be responsible for implementation, coordination, and execution of all regulatory reviews, ensure technical adequacy of the final design, and provide quality control of all phases of the contract.
2.3.1 Project Phasing
This project shall be accomplished in phases as agreed upon by the Base engineers and production staff. All telecoms and meetings shall be coordinated by the Contractor with the PM and Base engineering representatives.
The Government shall have 14 calendar days to review each design deliverable. The Contractor shall submit meeting minutes within 7 calendar days after each teleconference or meeting. The Contractor shall complete the work as described below.
2.3.2 Site Survey
The contractor shall also avail themselves for a short site survey on the day of or the day after the Kickoff Meeting.
The site survey will allow the Government and/or Contractor to discuss any specific concerns not previously addressed.
2.3.3 65% Design
The Contractor shall within 60 calendar days from the kick-off meeting provide 65% design for review and comment. The 65% design package shall include drawings 65% complete showing all major details, specifications, and design analysis. The Government shall have 30 calendar days to provide review comments. The Contractor shall schedule and attend review conference at Vandenberg AFB within 7 calendar days of receipt of Government comments.
2.3.4 95% Design
The Contractor shall within 30 calendar days from 65% review meeting provide 95% design for review and comment. The design shall include all drawings, specifications, and design analysis. This package shall be in a
100% design state with the exception of Government corrections/modifications. The design shall be provided to the individuals list below. The Government shall have 21 calendar days to provide review comments. The Contractor shall schedule and attend final review conference meeting at Vandenberg AFB within 7 calendar days of receipt of
Government comments.
2.3.5 100% Design
Within 14 calendar days from the 95% review meeting, the contractor shall provide the 100% Final Design package.
2.3.6 Verification of Existing Conditions and Site Survey
Use of existing condition data provided by the Air Force conveys acceptance and as such does not relieve the
Contractor of liability associated with performance as the Engineer of Record. The Contractor shall be solely responsible for verification and validation of existing conditions, coordination of existing conditions in parallel with proposed requirements, and above and below-grade condition assessment.
2.3.7 Floor Plans/Elevations Design Requirements
Not applicable to this Contract
2.3.8 Architect of Record
The term “Architect of Record” in the context of this contract shall mean the principal professional Architect or
Engineer. The Contractor shall serve as the “Architect of Record” and, as such, will ensure that all completed designs and as-built drawings are signed and sealed by registered professionals. The Contractor is accountable for all aspects of the completed design and as-built drawings under all applicable Federal, State and local laws, regulations and base-specific standards.
2.3.9 Hazardous Materials Surveys
Not applicable to this Contract
2.4 CONSTRUCTION PHASE
Upon the approval of the Contracting Officer (CO), the Contractor may commence onsite construction activities.
The Contractor shall complete the work as described below:
2.4.1 On-Site Field Oversight
The Contractor shall provide the manpower, equipment, material, services, and transportation necessary to ensure oversight services throughout accomplishment of this design/build contract. It is the responsibility of the Contractor to establish and maintain open communications between salient authorities associated with accomplishment of this contract.
2.4.2 Delivery/Warranty
The Contractor shall complete all inspection and commissioning requirements prior to final inspection. Following final inspection, the Contractor shall deliver to the Government the signed and sealed as-built drawings in both hard copy and reproducible format. The Contractor shall provide a warranty in accordance with FAR 52.246-21.
3.0 GENERAL REQUIREMENTS
3.1 QUALIFIED PERSONNEL
The contractor shall ensure that only qualified, competent personnel carry out the tasks outlined in this SOW.
Competent is defined as registered professional or, where registration is not applicable, trained, and/or certified in their respective field.
3.2 AIR FORCE PROPERTY
All materials gathered and/or developed in the performance of these tasks listed shall be returned to and become property of the Air Force; and shall not be used and/or distributed by the contractor without specific written permission of the CO.
Material resulting from demolition activities shall be disposed of by the Contractor through Defense Logistics
Agency (DLA) Disposition Services or off base landfill, as appropriate. The VAFB Base Landfill is no longer available for projects at Vandenberg AFB.
3.3 DESIGN AND CONSTRUCTION REQUIREMENTS
The project shall conform to all applicable Federal, State and local laws, regulations and base-specific standards and applicable Unified Facilities Criteria (UFC). Where there is a conflict between the referenced standards, the most stringent shall take precedence. All work accomplished by the Contractor shall comply with these criteria unless a waiver is obtained from the Air Force when conditions warrant such consideration.
4.0 GOVERNMENT FURNISHED ITEMS
The following is a list of specific items of support that the Base CE will provide:
4.1 AF FORM 103
The Base CE will assist the Contractor with efforts to fully complete the Base Civil Engineering Work Clearance
Request (AF Form 103). The Base CE will locate underground utilities and issue the AF Form 103 to the
Contractor. It is the Contractor’s responsibility to have a completed and approved Form 103 prior to beginning any construction activities including clearing, grubbing, exploratory geophysical work, etc.
4.2 STAGING AREA
The Base CE will identify space on the jobsite or in a base contractor staging area where the contractor may deliver non-hazardous materials within the installation.
4.3 EXISTING ENGINEERING PLANS, ETC.
The Base CE will provide the contractor access to existing engineering plans, drawings, diagrams, aerial photographs, digitized map files, etc., to facilitate evaluation of the site(s), as needed or requested.
4.4 PRECONSTRUCTION MEETING
The Base CE will host a pre-construction (i.e., Kick-Off) meeting to advise and coordinate on local procedures, safety and security requirements, and project coordination activities. The Contracting Officer Representative (COR) will arrange for a suitable Kick-Off meeting location. The COR will ensure the appropriate base agencies attend the
Kick-Off meeting to provide necessary information or briefings to facilitate the success of the contract effort.
4.5 BASE REQUIREMENTS
The Base CE will advise the contractor of the location and processes to obtain the following as needed:
a. Personnel identification badges, vehicle passes, and/or entry permits.
b. Information on base fire prevention/security practices and procedures.
c. Access to utilities (electrical, water, sewer, phone, etc.). This includes a supply (e.g., fire hydrant or stand pipe) of large quantities of potable water.
d. Security escorts for work in restricted areas.
e. Safety training classes for the purpose of allowing access within secure or hazardous areas.
f. A paved area where equipment can be cleaned.
g. A set of keys to locks as necessary.
4.6 TITLE II
Title II Construction Management Services will be provided through an alternate contract vehicle. The Construction
Management Architect-Engineer (A-E) Representative duties and responsibilities are to perform on-site surveillance and inspection of the construction work in-progress and to ascertain that the work is properly executed in conformance with the specifications. The A-E Project Representative is authorized to review and coordinate on monthly status reports from the Contractor and to review AF Form(s) 3064 and 3065 to recommend approval or disapproval to the CO and PM.
5.0 DELIVERABLES
Project deliverables shall be as shown in the table below. A description of each deliverable follows.
TABLE OF DELIVERABLES
Document Title
Copies Per Addressee
Delivery Date
A ir
F o rc e
P M ir
F o rc e
C O
E le ct ro n ic
H ar d C o p y ct ro d C o
Project Management Plan (PMP) 1 2 1 0 14 calendar Days after Award
Kick-Off Meeting 10 calendar days after Award
Progress Meetings Once a week
Meeting Minutes 1 0 1 0 2 calendar days after each meeting
Monthly Status Report 1 0 1 0 15 th of each month
Progress Schedule (AF 3064 or approved equivalent) 1 0 1 0
10 calendar days after award or at the
Kick-Off Meeting, whichever is later.
Updated form shall be submitted on or about the 15 th of each month
Progress Report (AF 3065 or approved equiv.) 1 0 1 0 On or about the 15 th of each month
65% Design 1 3 1 0
Within 60 calendar days after Kick-off
Meeting/Charrette. Hard copies for the design shall be ½ size and full size drawings. The number of each shall be defined at the Kick-off Meeting.
65% Design Review Conference Within 7 calendar days of receipt of Gov.
comments on the 65% Design
The Government will provide review comments within 30 calendar days of 65% Design Submittal
95% Design 1 3 1 0 30 calendar days after 65% Design Review Meeting
TABLE OF DELIVERABLES
Document Title
Copies Per Addressee
Delivery Date ir
F o rc e
P M ir
F o rc e
C O ct ro d C o ct ro d C o
95% Design Review Conference Within 7 Calendar days of receipt of Gov.
comments on the 95% Design
The Government will provide final comments within 21 calendar days of 95% Design Submittal
100% Design, with Signed & Sealed Drawings
& Specifications 1 3 1 0
14 calendar days after receipt of Government
Review Comments from the 95% Design
Material Approval (AF Form 3000) 1 0 1 0 30 calendar days prior to requirement
Incidental Design Documents / Shop Drawings
(AF Form 3000) 1 0 1 0 30 calendar days prior to requirement
Production or Delivery Problem Report 1 0 1 0 Same day as issue or occurrence
Pre-Final Inspection Report 1 0 1 0 5 calendar days before Final Inspection
Daily Logs (AF Form 1477 or approved equivalent) 1 0 1 0 Final Inspection
As-built Drawings 1 2 1 0 30 calendar days after Final Inspection
Transfer & Acceptance of Military Real
Property (DD 1354) 1 1 1 0 Within 15 calendar days of Final Inspection
Final Inspection Report 1 0 1 0 5 calendar days after Final Inspection
5.1 PROJECT MANAGEMENT PLAN
The Project Management Plan shall be as prepared as described in the Specifications.
5.2 CONTRACT PROGRESS SCHEDULE (AF 3064)
The Contractor shall submit a signed AF 3064 Contract Progress Schedule, depicting an overall contract progress schedule for the main elements of work for the period of performance as described in the Table of Deliverables above. The Contractor shall also provide a line graph depicting actual construction progress (solid line) versus scheduled construction progress (dotted line) throughout the period of performance.
The PM and CO shall approve the first (baseline) progress schedule and it shall not be altered without approval of the CO.
The PM and CO shall sign subsequent and periodic updates to the progress schedule.
5.3 CONTRACT PROGRESS REPORT (AF 3065)
The Contractor shall submit AF 3065 as described in the Table of Deliverables above. The work elements and percentages of the total job identified on the AF 3065 shall be identical to the work elements and percentages on the
AF 3064. If the Contractor is more than 5% behind schedule, the Contractor shall note in the Remarks section the reason why and what is being done to get back on schedule. The PM will sign the AF 3065 in the Remark section of the AF 3065 and send to the CS for coordination and approval by the CO. If the contractor requires reimbursement of a high dollar value item, the item shall be identified on the AF 3065, an appropriate percentage applied, and the item must be received and stored on site.
5.4 Monthly Status Report (MSR).
The Monthly Status Reports shall communicate activities accomplished during the previous period, document discussions, identification of problems, proposed solutions, corrective actions taken, outstanding issues, and record issues or concerns. The Monthly Status Report shall include a financial tracking table containing columns with the following headings:
a. Task Breakout
b. Current Project Status (summary of work previously completed and completed during the current reporting period).
c. Task Value
d. Effort % Complete
e. Dollars % Expensed To Date
f. Dollars Earned This Month
g. Dollars Earned To Date
h. Expected work activities for the following month
i. Problems and/or concerns
j. RFI’s and Statuses
k. Updated Submittal Register
l. Safety
m. Photographic Log of Pervious Period Operations
An AF 3064, AF 3065 and a Monthly Status Report shall accompany each invoice. The AF 3064, AF 3065, Monthly Status Report and invoice shall all cover the same period of time.
5.5 KICK-OFF MEETING
The Contractor shall coordinate the date and time of pre-construction (i.e., Kick-Off) meeting with the PM, CS, and
CO. During the meeting, the Contractor shall present a complete overview of the project and review the schedule, highlighting any issues (review periods, material submittals, etc.) which are key to maintaining the schedule. The
Contractor shall take meeting minutes to include the recording of the attendance list.
5.6 CHARRETTE
Not Applicable to this Contract
5.7 PROGRESS MEETINGS
The Contractor shall perform Progress Meetings as described in the Table of Deliverables. These meetings will include all relevant base POC’s and Contracting Personnel on an as needed basis. These meetings will cover the progress made in the past period and will include any pertinent issues which could affect future contract progress.
The following items shall be covered:
a. Meeting Attendees and Contact Information
b. Project Percent Complete (Actual and Scheduled)
c. RFI’s and Statuses
d. Material Submittals and Statuses
e. Two Week Look Ahead
f. Schedule
g. Safety
h. Resolution of Existing Issues
i. New Business
5.8 FORMAT OF DELIVERABLES
An electronic copy of all deliverables shall be provided, formatted for use on the latest version and compatible with the Government’s version of Microsoft Word, Excel, Adobe Acrobat, and AutoCAD. All deliverables shall also be dated. The Contractor will be provided samples of the deliverables, upon request.
5.9 DESIGN SUBMITTAL REQUIREMENTS
In addition to the requirements of applicable UFC’s, each design package shall include the following:
a. Executive summary with statement of work and all modifications.
b. Table of Contents
c. Minutes and sign-in sheets of all meetings pertaining to the development of the design.
d. Previous government review comments and contractor responses.
e. All appropriate Engineering Calculations.
f. Design Drawings.
5.10 PRE-FINAL INSPECTION
The Contractor shall conduct a pre-final walk through inspection with Base personnel and publish the pre-final inspection findings in a pre-final inspection (punch list) report. The Contractor shall include a draft DD Form 1354, Transfer and Acceptance of Real Property to the PM for review.
5.11 FINAL INSPECTION
The Contractor shall conduct a final inspection with base personnel and publish the findings in a final inspection report. The inspection shall concentrate on the items identified at the pre-final inspection and recorded in the pre-final inspection (punch list) report. A final inspection shall not be performed until the pre-final inspection (punchlist) report has been resolved. At the final inspection, the Contractor shall present a completed DD Form 1354, Transfer and Acceptance of Real Property to the Base Civil Engineer (BCE) or other appropriate organization for signature and acceptance, if required.
Section E - Inspection and Acceptance
INSPECTION & ACCEPTANCE
E-1 DESIGNATION OF GOVERNMENT INSPECTOR
The Project Manager or authorized representative is designated as the representative of the Contracting Officer for the purpose of surveillance and inspection of performance of work on the contract. This designation does not include authority to direct or authorize the Contractor to make changes in the scope or terms of the contract. The inspector will perform duties including technical surveillance, ensuring compliance with workmanship requirements and standards and with the plans and specifications of this contract. This provision does not authorize anyone other than the Contracting Officer to commit the Government to changes in the terms of the contract. Contractor shall notify the appropriate Project Manager for 30 CES/CENMP and Contract Specialist for 30 CONS/LGCA at least 24 hours in advance of the date work will commence under this contract; Contractor shall also notify that office at earliest possible time of anticipated absence(s) from the job site.
E-2 PRE-FINAL, INTERIM, AND FINAL INSPECTIONS
1. The Contractor shall conduct their own quality control pre-final inspection prior to requesting a pre-final inspection with the Government. The Government may accompany the Contractor on the pre-final inspection.
Notify the Government seven (7) calendar days prior to conducting the pre-final inspection. Any discrepancies noted shall be corrected prior to any final inspection.
2. Prior to covering, enclosing, or hiding any of type work, the Contractor shall contact the Project Manager, authorized representative (if applicable) and the Contract Specialist at least five working days in advance to perform an interim inspection. Failure to contact the appropriate Government personnel to perform an interim inspection prior to concealment may result in the Contractor being required to uncover performed work sufficiently to allow for proper inspection.
3. The contractor shall have the as-builts approved prior to scheduling a final inspection. When ready for final inspection, the Contractor shall request final inspection in writing to the Contracting Officer. The final inspection shall normally be requested a minimum of seven (7) calendar days before the desired date or as otherwise negotiated with the Contracting Officer.
4. The final inspection will be at the project location with the Contractor, the Project Manager, the authorized representative (if applicable) and Contract Specialist. The Government end user or customer is highly encouraged to attend.
5. The Contractor shall ensure that all inspections are completed prior to the end of the contract’s performance period.
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government
CLAUSES INCORPORATED BY REFERENCE
52.246-12 Inspection of Construction AUG 1996
52.246-21 Warranty of Construction MAR 1994
Section F - Deliveries or Performance
DELIVERIES OR PERFORMANCE
F-1 INSURANCE REQUIREMENTS
In accordance with the requirements of FAR 52.228-5 - Insurance Work on a Government Installation, the specific types and amounts of insurance contemplated under this contract are set forth as follows:
General liability:
Liability insurance coverage written on the comprehensive form of policy of at least $500,000 per occurrence.
Property damage liability insurance shall be required only in special circumstances as determined by the agency.
Automobile liability: Automobile liability insurance written on the comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage. The amount of liability coverage on other policies shall be commensurate with any legal requirements of the locality and sufficient to meet normal and customary claims.
F-2 ON-BASE PERFORMACE
1. Working Hours: The offeror shall perform functions called out in the contract during standard working hours. Core hours of work are 7:00 a.m. and 4:30 p.m. Pacific Standard Time (PST), excluding Saturdays, Sundays, and Federal Holidays. Standard hours for performance may be scheduled outside the core hours, but may not exceed eight hours in a workday or 40 hours in a workweek. Any work desired to be accomplished that would exceed 8 hours in a work day or 40 hours in a work week will require prior approval of the Contracting Officer. The Contractor must submit a written request to the Contracting
Officer at least three (3) business days in advance.
2. Proposal Schedule: Offeror shall perform any or all functions described in the contract, specifications, and the contractors proposed work, during standard working hours in accordance with the scope specified in this contract.
3. The Contractor’s performance may be interrupted from time to time because of high priority mission schedules. For each calendar day and/or portion of a calendar day that the Contractor is removed from the job site, the contract schedule will be adjusted by one (1) calendar day.
F-3 CONSTRUCTION PERMITS
In accordance with (IAW) FAR 52.236-7 – Permits and Responsibilities, the Contractor shall obtain a construction permit for any construction work on Vandenberg Air Force Base. An AF Form 103 – Base Civil Engineering Work
Clearance Request – must be submitted with all required signatures, to the Project Manager prior to beginning of performance on the job site. No work shall begin until approval of the AF Form 103 has been granted. An AF form
813 Request for Environmental Impact Analysis; will be provided prior to award, however, it is the Contractor’s responsibility to coordinate environmental issue through the base environmental office.
F-4 UTILITIES
Power and water may not be available at certain job sites depending on the location of the project, nor will they be made available by the Government. Contractor is responsible for providing temporary lighting for working at night, portable generators, and potable water.
F-5 SALVAGE MATERIALS
1. Any materials demolished or to be removed and disposed of by the Contractor shall remain the property of the Government and the Contractor shall coordinate with Defense Logistics Agency, 606-9852, Vandenberg
AFB and disposed of legally.
2. The Contractor shall recycle all construction/demolition debris to the maximum extent practicable. The
Contractor shall make every effort to recycle materials, such as, but not limited to concrete, bricks, asphalt, wood, and metals. Contact Recycling Center, 805-606-8438, for assistance.
F-6 HAZARDOUS WASTE REMOVAL
In addition to other contract requirements related to property disposal, including 52.223-5 – Pollution Prevention and
Right-to-Know Information, and 52.236-13 – Accident Prevention, Alt 1, the Contractor shall dispose of all hazardous waste in accordance with all applicable local, federal, and state environmental laws and regulations, including but not limited to 40 CFR 260-268, Hazardous Waste Management. The Contractor shall assume the responsibility of determining what constitutes hazardous waste and complying with all environmental laws and regulations governing its removal.
F-7 WEATHER DELAYS
The Contractor’s progress schedule must take anticipated adverse weather delays into account in all weather-dependent activities to ensure timely completion of the job.
Upon acknowledgement of Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on his Daily Report, the occurrence of adverse weather and resultant impact to normally scheduled work.
Actual adverse weather delay days must prevent work on critical activities for fifty percent or more of the
Contractor’s scheduled workday and must cause a delay in the work activities critical to contract completion. In order to obtain relief from contract schedule requirements, the Contractor will have to demonstrate not only that the anticipated amount of weather delay was exceeded by actual weather interruption, but also that reasonable efforts were made to compensate for such excess interruptions through changes in work hours, changes in the planned sequence of work, increased concurrent activities, or other available measures. Contemporaneous documentation of such efforts and prompt coordination with Government inspectors is encouraged (see below).
In the event that all reasonable effort to complete the required performance on schedule fail and it is determined that excessive inclement weather was the cause of that failure, the Contractor may request an extension of the project performance period for any weather delays suffered because of adverse weather beyond the number of days indicated on the chart. The number of workdays of delay added to the schedule shall be converted to calendar days by adding the appropriate number of weekend days associated with that number of workdays.
1. Adverse weather days will not be granted for other than normal workdays that the Contractor requested to work solely for the Contractor’s convenience to meet the contract performance period.
2. Any extensions to the contract because of change orders will have the normal adverse weather days figured into the extension period.
3. If the contract dictates an alternate performance period other than a normal Monday through Friday five-day workweek, an extension will be considered based on the contract requirement for a workday.
Consistent with FAR 52.249-10, Default (Fixed-Price Construction), upon the written request of the Contractor for an adjustment to the contract schedule made within ten (10) days from the beginning of the delay, the Contracting
Officer will review the Contractor's documentation of weather delays and circumstances relevant to the availability of workarounds. If the Contractor requests an adjustment to the contract schedule based on the Project Manager’s review, the Contractor shall notify the Contracting Officer in writing and provide relevant information and recommendations regarding the request. The Contracting Officer shall determine whether the request should be promptly granted, deferred pending determination of cumulative weather effects during the contract performance period, denied, or some combination thereof. The reason for any deferral or denial will be simultaneously communicated to the Contractor in writing.
Upon any extension, the Contractor shall immediately submit to the Contracting Officer a revised project schedule, to meet the revised performance period.
F-8 SUBMITTALS
Submittals shall be submitted within ten (10) days of contract award, IAW Section 01 33 00, Submittal Procedures, paragraph 1.6. A schedule of submittals, shall include all project submittals from award to closeout, to include as-builts. All material submittals shall be submitted on an AF 3000 or equivalent. This shall include, but is not limited to, test reports, manufacturer’s instructions, Operation and Maintenance Data, Close-out submittals, and samples.
An electronic copy of the submittal and supporting documents, with a wet signature, shall be submitted via e-mail to the Contract Specialist with courtesy copy to the Contracting Officer who will distribute the submittal to the Project
Manager. Government approval shall be annotated with a wet signature.
F-9 BONDING
The Contractor shall furnish all executed bonds to the Contracting Officer within 10 calendar days after award and before starting work.
Prior to the Government issuing a Notice to Proceed, the bonds shall be in the form of firm commitment, supported by corporate sureties whose names appear on the list contained in Treasury Department Circular 570, individual sureties, or by other acceptable security such as postal money order, certified check, cashier’s check, irrevocable letter of credit, or, in accordance with Treasury Department regulations, certain bonds or notes of the United States.
Treasury Circular 570 is published in the Federal Register, or may be obtained on-line at
Surety.Bonds@fms.treas.gov or from the U.S. Department of Treasury, Financial Management Services, Surety
Bonds Branch, 3700 East West Highway, Room 6F01 Hyattsville, MD 20782.
The offeror shall furnish two bonds each with surety or sureties acceptable to the Government in the form of a
Performance Bond (Standard Form 25) and a Payment Bond (Standard Form 25A). The penal sums of such bonds shall be as follows:
Performance Bond: The penal sum of the Performance Bond shall equal one hundred percent (100%) of the
Payment Bonds: The penal sum of the Payment Bond shall equal one hundred percent (100%) of the contract.
F-10 IMPLEMENTING PROCEDURES FOR THE BASE ANTI-TERRORISM PROGRAM, NON
MISSION ESSENTIAL SERVICES
1.0 Policy and Scope. Terrorism is criminal activity, which can occur at anytime, anywhere, and involve any person or organization. Air Force policy is to protect, to the best of its ability, U.S. Air Force personnel, their dependents, facilities, and equipment from terrorist acts.
1.1 Concerned Individuals. This includes non-Air Force, and contractor organizations, and their personnel working on the installation at the time of a terrorist action, planned or actual.
1.2 Exercises. Based upon terrorist threat assessment guidelines, the chance of a terrorist organization committing an act of aggression on Vandenberg AFB is almost negligible. Nonetheless, there are no guarantees. We must be prepared. There is no better protection than prevention through training. Accordingly, the base anti-terrorism program will be periodically exercised (tested). Air Force and non-Air Force organizations will be expected to participate in these occasional exercises (tests). Contractor organizations, their subcontractors, and their employees who are working on Vandenberg AFB and providing services under contract which have not been specifically designated by the Government to be “essential contractor services” in support of “mission essential functions” in accordance with DFARS SUBPART 237.76 are not required to participate in these exercises but are requested, in the interests of informational awareness, to communicate to their employees and subcontractors at all tiers the information contained in these IMPLEMENTING PROCEDURES.
2.0 Sources of Authority.
2.1 AFI 31-210, The Air Force Anti-terrorism (AT) Program, as supplemented by HQ AFSPC.
2.2 30 SW OPlan 31-101, Vandenberg AFB Installation Security Plan.
2.3 30 SWI 10-218, Installation Alert Notification/Recall Procedures.
3.0 General Information. The AF Anti-terrorism Program is an established DoD policy to protect DoD personnel, dependents, facilities, and equipment from terrorist acts. At Vandenberg AFB, this also includes non-Air
Force, contractor organizations, and their personnel working on the installation. It further seeks to deter or prohibit the success of terrorist acts against the USAF community through the collection and dissemination of timely threat information, informative awareness programs, and implementation of sound defensive measures. These defensive measures are defined in four levels of force protection conditions (FPCONs). The four levels of FPCONs are
ALPHA, BRAVO, CHARLIE and DELTA.
3.1 FPCON Definitions.
3.1.1 ALPHA. A general threat of possible terrorist activity against personnel and facilities exists, the nature and extent of which are unpredictable. Circumstances do not justify full implementation of FPCON BRAVO measures, but certain measures from higher FPCONs may be necessary based on intelligence reports, or as a deterrent.
3.1.2 BRAVO. An increased and more predictable threat of terrorist activity exists.
3.1.3 CHARLIE. An incident occurs, or intelligence is received that indicates imminent terrorist acts against personnel and facilities.
3.1.4 DELTA. A terrorist attack occurred or intelligence indicates that terrorist action against a specific location or person is likely. Normally, this FPCON is a local condition.
3.2 FPCON Defense Measures. The terrorism FPCONs listed below describes progressive levels of defensive security measures in response to a terrorist threat to Vandenberg AFB and its assigned and attached personnel
Directors or Program Managers of contractor organization will implement the defense measures on a “best effort” basis. In other words, provide uninterrupted operations support. FPCON actions will be accomplished as a secondary initiative to mission accomplishment.
3.2.1 ALPHA
a. Brief all contractor personnel of current FPCON
b. Post 30 SW VA 10-1, , FPCON warning (“Real World” ALPHA)
c. Secure unused buildings, rooms, and storage areas under contractor’s control
d. Make periodic checks of parking areas under contractor’s control for unknown or suspicious vehicles
e. Identify all unknown or suspicious persons in facilities and work areas to Vandenberg AFB law enforcement at 911 or 606-3911
3.2.2 BRAVO.
a. Continue all actions required by FPCON ALPHA
b. Post 30 SW VA 10-2, FPCON warning (“Real World” BRAVO)
c. Move vehicles and objects such as crates, trash containers at least 10 meters (33 feet)
d. from buildings and 25 meters (82 feet) from certain critical buildings, especially those of a sensitive nature listed in the 30 th
Space Wing FPCON checklist Attachment 1
e. Remind drivers to lock parked vehicles, and check inside or outside of vehicles for suspicious packages that could be explosive or of similar harmful nature prior to operation; inform Vandenberg AFB law enforcement at 911 or 606-3911 if such is found
3.2.3 CHARLIE.
a. Continue all actions required by the previous FPCONs
b. Post 30 SW VA 10-3 FPCON warning (“Real World” CHARLIE)
c. If connected to a fire hydrant as part of construction activities, disconnect until FPCON returns to BRAVO or lower
3.2.4 DELTA.
a. Continue all actions required by the previous FPCONs
b. Post 30 SW VA 10-4, FPCON warning (“Real World” DELTA)
c. Make frequent checks of the exterior of buildings and parking area under the contractor’s control for suspicious packages that could be explosive or of similar harmful nature; inform Vandenberg AFB law enforcement at 911 or 606-3911 if such is found
d. Discontinue all administrative travel outdoors to prevent exposure to the terrorist threat
a) orist threat
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC
0001 N/A N/A N/A N/A
CLAUSES INCORPORATED BY FULL TEXT
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within ten (10) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than Two-Hundred Forty (240) Calendar Days from date of the notice to proceed, the time stated for completion shall include final cleanup of the premises.
(End of clause)
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $526.50 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
52.242-14 SUSPENSION OF WORK (APR 1984)
(a) The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this contract for the period of time that the Contracting Officer determines appropriate for the convenience of the Government.
(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted (1) by an act of the Contracting Officer in the administration of this contract, or (2) by the Contracting
Officer’s failure to act within the time specified in this contract (or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly.
However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the Contractor, or for which an equitable adjustment is provided for or excluded under any other term or condition of this contract.
(c) A claim under this clause shall not be allowed—
(1) For any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order); and
(2) Unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the suspension, delay, or interruption, but not later than the date of final payment under the contract.
Section G - Contract Administration Data
252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (MAY 2013)
(a) Definitions. As used in this clause--
Department of Defense Activity Address Code (DoDAAC) is a six position code that uniquely identifies a unit, activity, or organization.
Document type means the type of payment request or receiving report available for creation in Wide Area WorkFlow
(WAWF).
Local processing office…
This is the start of the file's text. The full file is on GovTribe.