This document is an Amendment of Solicitation/Modification of Contract for a construction project at Offutt Air Force Base, Nebraska. The amendment modifies several key aspects of the original solicitation, including extending the on-site construction work period from 30 to 45 calendar days. The project has a total performance period ending on 01 June 2026, with a project magnitude between $100,000 and $250,000.

Key details include a mandatory site visit on 11 September 2025 at 10:30 AM CST, located at Quarters 16, 16 Custer Dr., Offutt AFB. Offerors without current base access must submit a completed vendor screening form by 2:00 PM CST on 03 September 2025. Electronic bid submissions are required via email, with fax and hardcopy bids being rejected. Questions about the solicitation must be submitted no later than 12:00 PM CST on 16 September 2025 to specific Air Force personnel. The solicitation and all related information will be posted on SAM.gov.

View the file

Other files for this federal contract opportunity

Other files attached to Quarters 16 Generator Installation Offutt AFB, NE, newest first.
File Type Posted
OF 1419A Abstract Continuation Sheet 2-4.pdf PDF
OF 1419A Abstract Continuation Sheet 4-4.pdf PDF
OF 1419 Abstract of Offers - 1-4.pdf PDF
OF 1419A Abstract Continuation Sheet 3-4.pdf PDF
Bid Abstract - Certified.pdf PDF
Q16 RFI 001 - Attachment 01.pdf PDF
Q16 RFI 001 - Gov Response.pdf PDF
Solicitation Amendment - FA460025B00030004.pdf PDF
Q16 RFI 001 - Attachment 02.pdf PDF
Solicitation Amendment FA460025B00030004 SF 30.pdf PDF
Site Visit Attendance Roster.pdf PDF
DSC03163.JPG JPG image
DSC03160.JPG JPG image
DSC03158.JPG JPG image
DSC03157.JPG JPG image
DSC03156.JPG JPG image
DSC03155.JPG JPG image
DSC03159.JPG JPG image
Solicitation Amendment FA460025B00030003 SF 30.pdf PDF
DSC03162.JPG JPG image
DSC03161.JPG JPG image
Conformed Solicitation - FA460025B00030003.pdf PDF
Solicitation Amendment FA460025B00030001 SF 30.pdf PDF
Solicitation - FA460025B00030002.pdf PDF
Solicitation Amendment 001 FA460025B00030001 SF 30.pdf PDF
Solicitation - FA460025B00030001.pdf PDF
Specifications.pdf PDF
55 SFS NCIC Screening Pass Request.pdf PDF
Drawings.pdf PDF
Wage Determination.pdf PDF
Show all 30

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

The purpose of this amendment is to: Block 14 (Description of Amendment/Modification):

- Amend the on-site construction work from 30 days to 45 days.

- Remove the following clauses:

52.203-6, Alternate 1 52.204-2 52.214-28 52.223-10 52.232-23, Alternate 1 52.236-13, Alternate 1 52.249-1 252.223-7998 252.232-7004 252.204-7021 252.223-7997 252.225-7055 252.225-7059

- Add the following clauses:

252.225-7013

Section A - Solicitation/Contract Form

The following modifications were made:

Information From To

Contract Description

**ELECTRONIC BID SUBMISSIONS ONLY. SUBMIT VIA

EMAIL AS DETAILED IN SECTION L - INSTRUCTIONS,

CONDITIONS, AND NOTICES TO OFFERORS.**

FAX AND HARDCOPY BIDS WILL BE REJECTED

1. SITE VISIT:

A site visit will be held on 11 September 2025, 10:30 AM CST at Quarters 16. The address is 16 Custer Dr., Offutt AFB, Nebraska. See below for base access.

2. BASE ACCESS:

Offerors without current base access shall submit the completed Attachment 04 – 55 SFS Contractor/Vendor NCIC Screening and Pass Request to SrA Victor Medina (victor.medina.6@us.af.mil) and Blaine Terry (blaine.terry.2@us.af.mil) no later than 2:00 PM CST on 03 September 2025. Late submissions will not be accepted. No exceptions.

3. PERIOD OF PERORMANCE:

The overall project performance period begins upon issuance of the Notice to Proceed. Prior to any on-site physical work, the contractor is responsible for equipment procurement, permit acquisition, and obtaining material submittal approvals. Once on-site physical work begins, the contractor has 30 calendar days to complete all such work.

Regardless of when on-site work commences, the entire project must be fully completed by 01 June, 2026.

4. The magnitude of construction for this project is between $100,000 and $250,000.

5. Questions regarding this solicitation shall be send to SrA Victor Medina (victor.medina.6@us.af.mil) and Blaine Terry (blaine.terry.2@us.af.mil) no later than 12:00 PM CST on 16 September 2025.

THIS SOLICITATION AND ALL INFORMATION, NOTICES,

AND AMENDMENTS FOR THIS IFB WILL BE POSTED AT

HTTPS://SAM.GOV.

**ELECTRONIC BID SUBMISSIONS ONLY. SUBMIT VIA

EMAIL AS DETAILED IN SECTION L - INSTRUCTIONS,

CONDITIONS, AND NOTICES TO OFFERORS.**

FAX AND HARDCOPY BIDS WILL BE REJECTED

1. SITE VISIT:

A site visit will be held on 11 September 2025, 10:30 AM CST at Quarters 16. The address is 16 Custer Dr., Offutt AFB, Nebraska. See below for base access.

2. BASE ACCESS:

Offerors without current base access shall submit the completed Attachment 04 – 55 SFS Contractor/Vendor NCIC Screening and Pass Request to SrA Victor Medina (victor.medina.6@us.af.mil) and Blaine Terry (blaine.terry.2@us.af.mil) no later than 2:00 PM CST on 03 September 2025. Late submissions will not be accepted. No exceptions.

3. PERIOD OF PERORMANCE:

The overall project performance period begins upon issuance of the Notice to Proceed. Prior to any on-site physical work, the contractor is responsible for equipment procurement, permit acquisition, and obtaining material submittal approvals. Once on-site physical work begins, the contractor has 45 calendar days to complete all such work.

Regardless of when on-site work commences, the entire project must be fully completed by 01 June, 2026.

4. The magnitude of construction for this project is between $100,000 and $250,000.

5. Questions regarding this solicitation shall be send to SrA Victor Medina (victor.medina.6@us.af.mil) and Blaine Terry (blaine.terry.2@us.af.mil) no later than 12:00 PM CST on 16 September 2025.

THIS SOLICITATION AND ALL INFORMATION, NOTICES,

AND AMENDMENTS FOR THIS IFB WILL BE POSTED AT

HTTPS://SAM.GOV.

Section I - Contract Clauses

Header Miscellaneous Text (Modified):

52.222-9 Apprentices and Trainees (July 2005)

(a) Apprentices. (1) An apprentice will be permitted to work at less than the predetermined rate for the work performed when employed-

FA460025B00030002

(i) Pursuant to and individually registered in a bona fide apprenticeship program registered with the U.S. Department of Labor, Employment and Training Administration, Office of Apprenticeship Training, Employer, and Labor Services (OATELS) or with a State Apprenticeship Agency recognized by the OATELS; or

(ii) In the first 90 days of probationary employment as an apprentice in such an apprenticeship program, even though not individually registered in the program, if certified by the OATELS or a State Apprenticeship Agency (where appropriate) to be eligible for probationary employment as an apprentice.

(2) The allowable ratio of apprentices to journeymen on the job site in any craft classification shall not be greater than the ratio permitted to the Contractor as to the entire work force under the registered program.

(3) Any worker listed on a payroll at an apprentice wage rate, who is not registered or otherwise employed as stated in paragraph (a)(1) of this clause, shall be paid not less than the applicable wage determination for the classification of work actually performed. In addition, any apprentice performing work on the job site in excess of the ratio permitted under the registered program shall be paid not less than the applicable wage rate on the wage determination for the work actually performed.

(4) Where a Contractor is performing construction on a project in a locality other than that in which its program is registered, the ratios and wage rates (expressed in percentages of the journeyman's hourly rate) specified in the Contractor's or subcontractor's registered program shall be observed. Every apprentice must be paid at not less than the rate specified in the registered program for the apprentice's level of progress, expressed as a percentage of the journeyman hourly rate specified in the applicable wage determination.

(5) Apprentices shall be paid fringe benefits in accordance with the provisions of the apprenticeship program. If the apprenticeship program does not specify fringe benefits, apprentices must be paid the full amount of fringe benefits listed on the wage determination for the applicable classification. If the Administrator determines that a different practice prevails for the applicable apprentice classification, fringes shall be paid in accordance with that determination.

(6) In the event OATELS, or a State Apprenticeship Agency recognized by OATELS, withdraws approval of an apprenticeship program, the Contractor will no longer be permitted to utilize apprentices at less than the applicable predetermined rate for the work performed until an acceptable program is approved.

(b) Trainees. (1) Except as provided in 29 CFR 5.16, trainees will not be permitted to work at less than the predetermined rate for the work performed unless they are employed pursuant to and individually registered in a program which has received prior approval, evidenced by formal certification by the U.S. Department of Labor, Employment and Training Administration, Office of Apprenticeship Training, Employer, and Labor Services (OATELS). The ratio of trainees to journeymen on the job site shall not be greater than permitted under the plan approved by OATELS.

(2) Every trainee must be paid at not less than the rate specified in the approved program for the trainee's level of progress, expressed as a percentage of the journeyman hourly rate specified in the applicable wage determination. Trainees shall be paid fringe benefits in accordance with the provisions of the trainee program. If the trainee program does not mention fringe benefits, trainees shall be paid the full amount of fringe benefits listed in the wage determination unless the Administrator of the Wage and Hour Division determines that there is an apprenticeship program associated with the corresponding journeyman wage rate in the wage determination which provides for less than full fringe benefits for apprentices. Any employee listed on the payroll at a trainee rate who is not registered and participating in a training plan approved by the OATELS shall be paid not less than the applicable wage rate in the wage determination for the classification of work actually performed. In addition, any trainee performing work on the job site in excess of the ratio permitted under the registered program shall be paid not less than the applicable wage rate in the wage determination for the work actually performed.

(3) In the event OATELS withdraws approval of a training program, the Contractor will no longer be permitted to utilize trainees at less than the applicable predetermined rate for the work performed until an acceptable program is approved.

(c) Equal employment opportunity. The utilization of apprentices, trainees, and journeymen under this clause shall be in conformity with the equal employment opportunity requirements of Executive Order 11246, as amended, and 29 CFR Part 30.

(End of clause)

52.228-13 Alternative Payment Protections (July 2000)

(a) The Contractor submit one of the following payment protections if the resultant contract price is greater than shall $35,000, but not greater than $150,000:

Payment bond or irrevocable letter of credit (ILC)

(a)(1) If the resultant contract price is greater than $150,000, see 52.228-15.

(b) The amount of the payment protection be 100 percent of the contract price. shall

(c) The submission of the payment protection is required within days of contract award. 10

(d) The payment protection provide protection for the full contract performance period plus a one-year period. shall

(e) Except for escrow agreements and payment bonds, which provide their own protection procedures, the is authorized to access funds under the payment protection when it has been alleged by Contracting Officer in writing a supplier of labor or material that a nonpayment has occurred, and to withhold such funds pending resolution by administrative or judicial proceedings or mutual agreement of the parties.

(f) When a tripartite escrow agreement is used, the Contractor utilize only suppliers of labor and material that shall signed the escrow agreement.

(End of clause)

52.249-10 Default (Fixed-Price Construction) (Apr 1984)

(a) If the Contractor refuses or fails to prosecute the work or any separable part, with the diligence that will insure its completion within the time specified in this contract including any extension, or fails to complete the work within this time, the Government , by written notice to the Contractor, terminate the right to proceed with the work (or the may separable part of the work) that has been delayed. In this event, the Government take over the work and may complete it by contract or otherwise, and take possession of and use any materials, appliances, and plant on may the work site necessary for completing the work. The Contractor and its be liable for any damage to the sureties shall Government resulting from the Contractor's refusal or failure to complete the work within the specified time, whether or not the Contractor's right to proceed with the work is terminated. This liability includes any increased costs incurred by the Government in completing the- work.

(b) The Contractor's right to proceed not be terminated nor the Contractor charged with damages under this shall clause, if-

(1) The delay in completing the work arises from unforeseeable causes beyond the control and without the fault or negligence of the Contractor. Examples of such causes include-

(i) Acts of God or of the public enemy,

(ii) Acts of the Government in either its sovereign or contractual capacity,

(iii) Acts of another Contractor in the performance of a contract with the Government,

(iv) Fires,

(v) Floods,

(vi) Epidemics,

(vii) Quarantine restrictions,

(viii) Strikes,

(ix) Freight embargoes,

(x) Unusually severe weather, or

(xi) Delays of subcontractors or suppliers at any tier arising from unforeseeable causes beyond the control and without the fault or negligence of both the Contractor and the subcontractors or suppliers; and

(2) The Contractor, within 10 days from the beginning of any delay (unless extended by the ), Contracting Officer notifies the of the causes of delay. The ascertain the facts and Contracting Officer in writing Contracting Officer shall the extent of delay. If, in the judgment of the , the findings of fact warrant such action, the time for Contracting Officer completing the work be extended. The findings of the be final and conclusive on the shall Contracting Officer shall parties, but subject to appeal under the Disputes clause.

(c) If, after termination of the Contractor's right to proceed, it is determined that the Contractor was not in default, or that the delay was excusable, the rights and obligations of the parties will be the same as if the termination had been issued for the convenience of the Government.

(d) The rights and remedies of the Government in this clause are in addition to any other rights and remedies provided by law or under this contract.

(End of clause)

5352.223-9000 Elimination of Use of Class I Ozone Depleting Substances (ODS) (JUN 2024)

(a) Contractors shall not:

(1) Provide any service or product with any specification, standard, drawing, or other document that requires the use of a Class I ODS in the test, operation, or maintenance of any system, subsystem, item, component, or process; or

(2) Provide any specification, standard, drawing, or other document that establishes a test, operation, or maintenance requirement that can only be met by use of a Class I ODS as part of this contract/order.

(b) For the purposes of Department of the Air Force policy, the following products that are pure (i.e., they meet the relevant product specification identified in AFI 32-7086) are Class I ODSs:

(1) Halons: 1011, 1202, 1211, 1301, and 2402;

(2) Chlorofluorocarbons (CFCs): CFC-11, CFC-12, CFC-13, CFC-111, CFC-112, CFC-113, CFC-114, CFC-115, CFC-211, CFC-212, CFC-213, CFC-214, CFC-215, CFC-216, and CFC-217, and the blends R-500, R-501, R-502, and R-503; and

(3) Carbon Tetrachloride, Methyl Chloroform, and Methyl Bromide.

[NOTE: Material that uses one or more of these Class I ODSs as minor constituents do not meet the Department of the Air Force definition of a Class I ODS.]

(End of clause)

5352.242-9000 Contractor Access to Department of the Air Force Installations (JUN 2024)

(a) The contractor shall obtain base identification and vehicle passes, if required, for all contractor personnel who make frequent visits to or perform work on the Department of the Air Force installation(s) cited in the contract. Contractor personnel are required to wear or prominently display installation identification badges or contractor-furnished, contractor identification badges while visiting or performing work on the installation.

(b) The contractor shall submit a written request on company letterhead to the contracting officer listing the following: contract number, location of work site, start and stop dates, and names of employees and subcontractor employees needing access to the base. The letter will also specify the individual(s) authorized to sign for a request for base identification credentials or vehicle passes. The contracting officer will endorse the request and forward it to the issuing base pass and registration office or Security Forces for processing. When reporting to the registration office, the authorized contractor individual(s) should provide a valid driver's license, current vehicle registration, valid vehicle insurance certificate, and [ insert any additional requirements to comply with local security procedures ] to obtain a vehicle pass.

(c) During performance of the contract, the contractor shall be responsible for obtaining required identification for newly assigned personnel and for prompt return of credentials and vehicle passes for any employee who no longer requires access to the work site.

(d) When work under this contract requires unescorted entry to controlled or restricted areas, the contractor shall comply with [insert any additional requirements to comply with AFI 31-101 , Integrated Defense, and DODMAN5200.02_AFMAN 16-1405 , Air Force Personnel Security Program ] citing the appropriate paragraphs as applicable.

(e) Upon completion or termination of the contract or expiration of the identification passes, the prime contractor shall ensure that all base identification passes issued to employees and subcontractor employees are returned to the issuing office.

(f) The contractor shall provide an after-hours contact number or after-hours email in the Emergency Mass Notification System (EMNS) for each of their personnel, whose normal place of duty is on a DoD installation or within a DoD facility. The contractor shall comply with any additional requirements in DAFMAN 10-206 for emergency operational reporting. Foreign Nationals may participate and may remove themselves from the Emergency Mass Notification System at any time. To update information, personnel can access the globe icon on their system desktop screens and choose the "Access Self-Service" option.

(g) Failure to comply with these requirements may result in withholding of final payment.

(End of clause)

252.225-7013 Duty-Free Entry (NOV 2023)

(a) Definitions. As used in this clause--

"Component," means any item supplied to the Government as part of an end product or of another component.

"Customs territory of the United States" means the 50 States, the District of Columbia, and Puerto Rico.

"Eligible product" means--

(1) "Designated country end product," as defined in the Trade Agreements (either basic or alternate) clause of this contract;

(2) Free Trade Agreement country end product, other than a Bahraini end product, a Moroccan end product, a Panamanian end product, or a Peruvian end product, as defined in the Buy American--Free Trade Agreements--Balance of Payments Program (either basic or alternate II) clause of this contract; or

(3) Free Trade Agreement country end product other than a Bahraini end product, Korean end product, Moroccan end product, Panamanian end product, or Peruvian end product, as defined in the Buy American--Free Trade Agreements--Balance of Payments Program (either alternate IV or alternate V) clause of this contract.

"Qualifying country" and "qualifying country end product" have the meanings given in the Trade Agreements clause, the Buy American and Balance of Payments Program clause, or the Buy American--Free Trade Agreements--Balance of Payments Program clause of this contract, basic or alternate.

(b) Except as provided in paragraph (i) of this clause, or unless supplies were imported into the customs territory of the United States before the date of this contract or the applicable subcontract, the price of this contract shall not include any amount for duty on--

(1) End items that are eligible products or qualifying country end products;

(2) Components (including, without limitation, raw materials and intermediate assemblies) produced or made in qualifying countries, that are to be incorporated in U.S.- made end products to be delivered under this contract; or

(3) Other supplies for which the Contractor estimates that duty will exceed $300 per shipment into the customs territory of the United States.

(c) The Contractor shall--

(1) Claim duty-free entry only for supplies that the Contractor intends to deliver to the Government under this contract, either as end items or components of end items; and

(2) Pay duty on supplies, or any portion thereof, that are diverted to nongovernmental use, other than--

(i) Scrap or salvage; or

(ii) Competitive sale made, directed, or authorized by the Contracting Officer.

(d) Except as the Contractor may otherwise agree, the Government will execute duty-free entry certificates and will afford such assistance as appropriate to obtain the duty-free entry of supplies--

(1) For which no duty is included in the contract price in accordance with paragraph (b) of this clause; and

(2) For which shipping documents bear the notation specified in paragraph (e) of this clause.

(e) For foreign supplies for which the Government will issue duty-free entry certificates in accordance with this clause, shipping documents submitted to Customs shall--

(1) Consign the shipments to the appropriate--

(i) Military department in care of the Contractor, including the Contractor's delivery address; or

(ii) Military installation; and

(2) Include the following information:

(i) Prime contract number and, if applicable, delivery order number.

(ii) Number of the subcontract for foreign supplies, if applicable.

(iii) Identification of the carrier.

(iv)(A) For direct shipments to a U.S. military installation, the notation: "UNITED STATES GOVERNMENT, DEPARTMENT OF DEFENSE Duty-Free Entry to be claimed pursuant to Section XXII, Chapter 98, Subchapter VIII, Item 9808.00.30 of the Harmonized Tariff Schedule of the United States. Upon arrival of shipment at the appropriate port of entry, District Director of Customs, please release shipment under 19 CFR Part 142 and notify Commander, Defense Contract Management Agency (DCMA), St. Louis, MO, ATTN: Duty Free Entry Team, 1222 Spruce Street, Room 9.300, St. Louis, MO 63103-2812, for execution of Customs Form 7501, 7501A, or 7506 and any required duty-free entry certificates."

(B) If the shipment will be consigned to other than a military installation, e.g., a domestic contractor's plant, the shipping document notation shall be altered to include the name and address of the contractor, agent, or broker who will notify Commander, DCMA New York, for execution of the duty-free entry certificate. (If the shipment will be consigned to a contractor's plant and no duty-free entry certificate is required due to a trade agreement, the Contractor shall claim duty-free entry under the applicable trade agreement and shall comply with the U.S. Customs Service requirements. No notification to Commander, DCMA New York, is required.)

(v) Gross weight in pounds (if freight is based on space tonnage, state cubic feet in addition to gross shipping weight).

(vi) Estimated value in U.S. dollars.

(vii) Activity address number of the contract administration office administering the prime contract, e.g., for DCMA Dayton, S3605A.

(f) Preparation of customs forms.

(1)(i) Except for shipments consigned to a military installation, the Contractor shall--

(A) Prepare any customs forms required for the entry of foreign supplies into the customs territory of the United States in connection with this contract; and

(B) Submit the completed customs forms to the District Director of Customs, with a copy to DCMA NY for execution of any required duty-free entry certificates.

(ii) Shipments consigned directly to a military installation will be released in accordance with sections 10.101 and 10.102 of the U.S. Customs regulations.

(2) For shipments containing both supplies that are to be accorded duty-free entry and supplies that are not, the Contractor shall identify on the customs forms those items that are eligible for duty-free entry.

(g) The Contractor shall--

(1) Prepare (if the Contractor is a foreign supplier), or shall instruct the foreign supplier to prepare, a sufficient number of copies of the bill of lading (or other shipping document) so that at least two of the copies accompanying the shipment will be available for use by the District Director of Customs at the port of entry;

(2) Consign the shipment as specified in paragraph (e) of this clause; and

(3) Mark on the exterior of all packages--

(i) "UNITED STATES GOVERNMENT, DEPARTMENT OF DEFENSE"; and

(ii) The activity address number of the contract administration office administering the prime contract.

(h) The Contractor shall notify the Administrative Contracting Officer (ACO) in writing of any purchase of eligible products or qualifying country supplies to be accorded duty-free entry, that are to be imported into the customs territory of the United States for delivery to the Government or for incorporation in end items to be delivered to the Government. The Contractor shall furnish the notice to the ACO immediately upon award to the supplier and shall include in the notice--

(1) The Contractor's name, address, and Commercial and Government Entity (CAGE) code;

(2) Prime contract number and, if applicable, delivery order number;

(3) Total dollar value of the prime contract or delivery order;

(4) Date of the last scheduled delivery under the prime contract or delivery order;

(5) Foreign supplier's name and address;

(6) Number of the subcontract for foreign supplies;

(7) Total dollar value of the subcontract for foreign supplies;

(8) Date of the last scheduled delivery under the subcontract for foreign supplies;

(9) List of items purchased;

(10) An agreement that the Contractor will pay duty on supplies, or any portion thereof, that are diverted to nongovernmental use other than--

(i) Scrap or salvage; or

(ii) Competitive sale made, directed, or authorized by the Contracting Officer;

(11) Country of origin; and

(12) Scheduled delivery date(s).

(i) This clause does not apply to purchases of eligible products or qualifying country supplies in connection with this contract if--

(1) The supplies are identical in nature to supplies purchased by the Contractor or any subcontractor in connection with its commercial business; and

(2) It is not economical or feasible to account for such supplies so as to ensure that the amount of the supplies for which duty-free entry is claimed does not exceed the amount purchased in connection with this contract.

(j) The Contractor shall--

(1) Insert the substance of this clause, including this paragraph (j), in all subcontracts for--

(i) Qualifying country components; or

(ii) Nonqualifying country components for which the Contractor estimates that duty will exceed $200 per unit;

(2) Require subcontractors to include the number of this contract on all shipping documents submitted to Customs for supplies for which duty-free entry is claimed pursuant to this clause; and

(3) Include in applicable subcontracts--

(i) The name and address of the ACO for this contract;

(ii) The name, address, and activity address number of the contract administration office specified in this contract; and

(iii) The information required by paragraphs (h)(1), (2), and (3) of this clause.

(End of clause)

Additional Regulation or Supplemental Clauses Incorporated by Full Text

The following Clause(s) were deleted:

FAR Clauses Incorporated by Reference

Number Title Effective Date Alternate/ Deviation

Variation Effective Date

52.203-6 Restrictions on Subcontractor Sales to the Government. (Alternate I) Jun 2020 Alternate I Nov 2021

52.214-28 Subcontractor Certified Cost or Pricing Data -- Modifications -- Sealed Bidding

(DEVIATION 2022-O0001)

Jun 2020 Deviation 2022-O0001 Oct 2021

52.223-10 Waste Reduction Program. (DEVIATION 2025-O0004) May 2024 Deviation 2025-O0004 Mar 2025 52.232-23 Assignment of Claims. (Alternate I) May 2014 Alternate I Apr 1984 52.236-13 Accident Prevention. (Alternate I) Nov 1991 Alternate I Nov 1991 52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form). Apr 1984

DFARS Clauses Incorporated by Reference

Number Title Effective Date Alternate/ Deviation

Variation Effective Date

252.223-7998 Prohibition on Procurement of Certain Items Containing Perfluorooctane Sulfonate or Perfluorooctanoic Acid. (Deviation 2022-O0010)

Apr 2023 Deviation 2022-O0010 Apr 2023

252.232-7004 DoD Progress Payment Rates (DEVIATION 2020-O0010) Oct 2014 Deviation 2020-O0010 Mar 2020

Section K - Representations, Certification, & Other Statements

Additional Regulation or Supplemental Clauses Incorporated by Full Text

The following Clause(s) were deleted:

DFARS Clauses Incorporated by Reference

Number Title Effective Date Alternate/ Deviation

Variation Effective Date

252.223-7997 Prohibition on Procurement of Certain Items Containing Perfluorooctane Sulfonate or Perfluorooctanoic Acid -- Representation. (Deviation 2022-O0010)

Sep 2022 Deviation 2022-O0010 Sep 2022

252.225-7055 Representation Regarding Business Operations with the Maduro Regime. May 2022

252.225-7059 Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region- Representation.

Jun 2023

SUMMARY OF CHANGES
Solicitation/Contract Form
Contract Clauses
Representations, Certification, & Other Statements
IDCode: J
Page: 1
Pages: 8
AmendNo: 0002
EffDate: 03 Sep 2025
ReqNo:
ProjNo: SGBP 22-0097
IssCode: FA4600
AdmCode:
IssuedBy: FA4600 55 CONS PKP

BLDG 323C CP 402 232 6459, 106 PEACEKEEPER DR STE 2N3

OFFUTT AFB, NE 68113

UNITED STATES

Victor Medina Jr, Email: victor.medina.6@us.af.mil Telephone: 4022328661 AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: FA460025B0003
SolDate: 23 Aug 2025
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: Off
OffrNoEx: 1
NoCopies: 1
ApprData: See Section G - Contract Administration Data
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: See Schedule
ContNameTitle:
CoNameTitle: Blaine Terry
ContDate:
CODate: 02 Sep 2025

File details come from the government source that posted it. Updated .