This document provides the ordering process for the Technology Applications Development and Sustainment (TADS) indefinite-delivery, indefinite-quantity contract. The Air Force's 55th Contracting Squadron will award a single-award IDIQ contract with a potential period of performance of 5 years plus a 6-month extension to provide Air Force weather capability deployment and sustainment services. The contract will allow for various contract types including cost-plus-fixed-fee, firm-fixed-price, cost-plus-incentive-fee, cost-reimbursement, and fixed-price incentive firm line items. The ordering process outlines requirements packages, task order requests, contractor proposals, negotiations, and award procedures. It establishes timelines for proposal submissions, evaluations, negotiations and provides standard templates for independent government cost estimates, performance work statements, and other documents.

Attachment 03 - TADS Ordering Process; 28 May 2019

View the file

Other files for this federal contract opportunity

Other files attached to Technology Applications Development and Sustainment (TADS), newest first.
File Type Posted
Attachment_09c_-_Task_Order_01-Transition_and_Sustainment_Performance_Requirements_Summary.docx DOCX document
FA460019RA0010002_-_Amendment_SF_30.pdf PDF
Attachment_06_-_Section_L-Instructions_to_Offerors.docx DOCX document
Attachment_09a_-_Task_Order_01-Transition_and_Sustainment_Sections_B_thru_J.docx DOCX document
Attachment_09c_-_Task_Order_01-Transition_and_Sustainment_Performance_Requirements_Summary.docx DOCX document
FA460019RA0010001_-_Amendment_SF_30.pdf PDF
Attachment_10a_-_Task_Order_02-CAF_Development_and_Integration_Sections_B_thru_J.docx DOCX document
Questions_and_Answers_20190724.pdf PDF
Solicitation_-_FA460019RA001.pdf PDF
Attachment_10a_-_Task_Order_02-CAF_Development_and_Integration_Sections_B_thru_J.docx DOCX document
Attachment_10b_-_Task_Order_02-CAF_Development_and_Integration_Statement_of_Objectives.docx DOCX document
Attachment_04_-_Rights_in_Data.docx DOCX document
Attachment_12_-_Solicitation_Acronym_List.docx DOCX document
Attachment_09e_-_Task_Order_01-Transition_and_Sustainment_Rights_in_Data.docx DOCX document
Attachment_11_-_Line_Item_Units_of_Measure.pdf PDF
QASP_TADS_Order01.doc DOC document
Attachment_05_-_DoL_Wage_Determination_Number_2015-5005_(Revision_7).pdf PDF
Attachment_09f_-_Task_Order_01-Transition_and_Sustainment_Workload_Estimate.docx DOCX document
Attachment_09d_-_Task_Order_01-Transition_and_Sustainment_Contract_Data_Requirements_List.pdf PDF
Attachment_02_-_Contract_Security_Classification_Specification_-_DD_Form_254.pdf PDF
Attachment_10d_-_Task_Order_02-CAF_Development_and_Integration_Rights_in_Data.docx DOCX document
Exhibit_A_-_Contract_Data_Requirements_List.docx DOCX document
Attachment_09c_-_Task_Order_01-Transition_and_Sustainment_Performance_Requirements_Summary.docx DOCX document
Attachment_09b_-_Task_Order_01-Transition_and_Sustainment_Performance_Work_Statement.docx DOCX document
Attachment_08_-_Solicitation_Cross_Reference_Matrix.docx DOCX document
Attachment_06_-_Section_L-Instructions_to_Offerors.docx DOCX document
Attachment_10c_-_Task_Order_02-CAF_Development_and_Integration_Contract_Data_Requirements_List.pdf PDF
Attachment_07_-_Section_M-Evaluation_Factors_for_Award.docx DOCX document
Attachment_09a_-_Task_Order_01-Transition_and_Sustainment_Sections_B_thru_J.docx DOCX document
Attachment_01_-_TADS_Overarching_Performance_Work_Statement.docx DOCX document
Show all 30

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4600-19-R-A001

Attachment 03 -- TADS Ordering Process

TECHNOLOGY APPLICATION DEVELOPMENT AND SUSTAINMENT (TADS)

ORDERING PROCESS

FA4600-19-R-A001

Attachment 03 28 May 2019

1.0 Objective

1.1 This process is intended to establish the overall process and expectations applicable for awarding orders under the TADS contract. This is not a comprehensive document that covers every individual scenario that may be encountered during the ordering period and does not supersede the contracting officer’s discretion.

1.2 The process outlined herein is based on the essential concept of achieving a win-win outcome in the acquisition process. All parties must be forthright, professional, and consistent in their dealings with each other.

1.3 As with all contracts, success is contingent upon all parties employing professional judgment and continuous cooperation.

2.0 Prior to Task Order Request

2.1 Requiring activity and Contractor establish mutual understanding of the requirements.

2.1.1 Although the Government is wholly responsible for establishing the requirements, it is critical that the Government and Contractor have a common understanding of the technical requirements and intended outcomes.

2.1.2 The 55th Contracting Squadron (55 CONS) will provide business advice, but the requiring activity is responsible for determining the need for pre-coordination activities and determining when pre-coordination activities are complete.

2.1.3 Mutual understanding may be accomplished by any method appropriate to the circumstances. The requiring activity is responsible for leading all pre-coordination activities; however, 55 CONS shall be included with all communication. Potential methods of pre-coordination may include, but are not limited to:

1) Providing draft documents for Contractor feedback
2) Technical Meetings
3) Requests for information

2.2 The Government’s requiring activity shall submit all of the following documents 55 CONS before a proposal will be requested from the Contractor:

2.2.1 Complete Performance Work Statement (PWS) or Statement of Objectives (SOO)

2.2.1.1 Per FAR 37.602(b), a task order’s PWS shall:

1) Describe the work in terms of the required results rather than either “how” the work is to be accomplished or the number of hours to be provided

2) Enable assessment of work performance against measurable performance standards (e.g. Services Summary)

2.2.1.2 Per FAR 37.602(c), a task order’s SOO shall contain all of the following data:
1) Purpose;
2) Scope or mission;
3) Period and place of performance;
4) Background;
5) Performance objectives, i.e., required results; and
6) Any operating constraints

2.2.2 Independent Government Cost Estimate (IGCE)

The IGCE shall be break out the estimated costs to match the order’s intended CLIN and fee structure. Example IGCE tools and formats include:

· The DoD IGCE Handbook for Services Acquisition, Appendix A-3 (https://www.acq.osd.mil/dpap/sa/Policies/SA-Guides-and-Handbooks.html)

· TechFar Hub’s Agile Team Estimator (https://techfarhub.cio.gov/custom-tools/ate/)

· GSA’s IGCE Tool (https://hallways.cap.gsa.gov/app/#/igce)

2.2.3 High-Dollar Material List

The list shall consist of the individual end items for which the Government’s estimated unit acquisition cost is $10,000 or more.

“End item” is defined as the final product when assembled, or completed, and ready for issue or deployment.

2.2.4 Statement of Scope

The information is necessary for the contracting officer to determine how the request is within technical scope of the TADS IDIQ.

2.2.5 Completed Contract Data Requirements List (CDRL)

All CDRL requirements shall be submitted using the DD Form 1423, DD Form 1423-1, or DD Form 1423-2. Reference TADS Exhibit A for the list of CDRLs and corresponding Data Item Descriptions applicable for TADS.

2.2.6 Contracting Officer Representative (COR) Nomination

Every task order shall have one primary COR; alternate CORs may be appointed, as appropriate. All COR nomination(s) shall be submitted using the COR Tracking Tool which is accessible online within the Procurement Integrated Enterprise Environment (https://wawf.eb.mil).

2.2.7 Certification of Non-Personal Services

The primary COR shall submit a signed certification that conforms to the requirements DFARS 237.503 as implemented by DFARS PGI 237.503.

2.2.8 DD 254 specific to the task order, if required
This is needed only if the specific task order has unique security requirements.

2.2.9 Funding for Order

Certified Funding is required. The contracting officer may accept a draft (uncertified) funding document on a case-by-case basis.

2.2.10 Any special requirements to be incorporated into the Contractor’s proposal This is needed only if the specific task order includes unique attachments, directs specific formats, or any order-specific directions.

3.0 Task Order Request (TOR)

3.1 After receiving the complete requirements package, the contract administrator will send the Task Order Request (TOR) via email to the Contractor’s authorized contract representative. The Government’s and Contractor’s Program Mangers will be copied on the request.

3.2 At a minimum, the TOR will include:

1) TOR Letter, signed by the contracting officer
2) Identification of the planned COR
3) Proposal Due Date,
4) Affordability cap, when applicable (this is not the IGCE)
5) The complete PWS or SOO
6) High-Dollar Material list, if applicable
7) CDRL Forms (DD 1423, DD 1423-1, or DD 1423-2)
8) Any other special proposal requirements, attachments, exhibits, or addendums

4.0 Contractor Proposal

The Contractor shall provide an adequate proposal within 20 business days after TOR receipt.

“Business Day” is defined as Monday through Friday, excluding all Federal holidays.

4.1 Technical Narrative

The Technical Narrative describes how the Contractor plans to execute the Performance Work Statement or Statement of Objectives. The proposal shall include sufficient information necessary to substantiate the Contractor’s approach for completing the task order and for the Government to evaluate the soundness of the Contractor’s approach.

4.2 Pricing Proposal Format and Content

4.2.1 The formats and data at FAR 15, Table 15-2 applies for all TOR pricing proposals and order modifications.

4.2.2 The provision at 252.215-7010, Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data, applies to all task order proposals.

4.2.3 Proposal Adequacy Checklist

All proposals that exceed the threshold for certified cost or pricing data shall include the completed Proposal Adequacy Checklist, DFARS 252.215-7009, to facilitate submission of a thorough, accurate, and complete proposal.

4.3 Performance Work Statement

If the Government provided a SOO as the means of describing the Government’s needs, the Contractor shall provide a complete PWS with the task order proposal.

4.3.1 The PWS shall be incorporated into the resultant task order award.

4.3.2 The PWS shall be unclassified, contain no proprietary information or markings, and be releasable in its entirety under the Freedom of Information Act.

4.3.3 The PWS shall be organized according to the CWBS, describe the work in terms of the required results rather than either “how” the work is to be accomplished or the number of hours to be provided, and provide performance standards and a method of assessing contractor performance against those standards.

4.4 Quality Control Plan

Per AFI 63-138 – Acquisition of Services, this document addresses the “detection” function that defines the type, number, Acceptable Quality Levels (AQLs), and frequency of quality assurance/control inspections planned by the Contractor to meet the quality requirements of the Air Force as identified by the requiring activity.

4.5 TADS Rights in Data.

The Contractor shall provide a completed “Rights in Data” attachment, specific to each order, to identify and track the Government’s rights in data to all technical data, computer software, and computer software documentation delivered or otherwise provided during performance of the order. After task order award, a bilateral modification is required to update this document.

4.6 Any other special proposal requirements, attachments, exhibits, or addendums as directed by the TOR Letter.

5.0 After Proposal Receipt

5.1 Fact Finding

Fact-finding may be required for the Government to understand different elements of the proposal and complete an appropriate evaluation.

5.1.1 Fact finding provides an opportunity for the Government to identify issues or concerns about the proposal, but this is not a forum for debate.

Note: Identifying issues/evaluation results to the Contractor is not the same thing as negotiating prior to obtaining Business Clearance approval to enter negotiations

5.1.2 55 CONS shall initiate and participate in all fact-finding communication.

5.1.3 The Contractor may provide supplemental information; however, no proposal updates/changes will be accepted unless the contracting officer provides a written request for revised proposal.

5.2 The COR is responsible for conducting technical evaluation and providing a single consolidated technical evaluation to 55 CONS; multiple technical evaluation documents will be rejected. The technical evaluation is essential for development of the Government’s negotiation objectives or documenting the rationale for accepting the proposal.

5.2.1 At a minimum, the technical evaluation examines the types and quantities of material proposed and the need for the types and quantities of labor hours and the labor mix. The analysis should include any other data that may be pertinent to assessment of the offeror’s ability to accomplish the technical requirements or to the cost or price analysis.

(Reference FAR 15.404-1(e))

5.2.2 If the COR accepts the proposal, the evaluation shall clearly explain the evaluation findings and rationale for accepting the proposal.

5.2.3 If the COR requests to negotiate, the evaluation shall clearly explain the evaluation findings, which proposal aspects the Government intends to accept and rationale for acceptance. For each individual aspect to be negotiated, the evaluation shall clearly explain:

1) The evaluation findings
2) Detailed rationale explaining the basis for negotiation
3) Government negotiation objective (target)
4) Government maximum

5.2.4 The COR’s technical evaluation shall not be considered “complete” until 55 CONS confirms that the content is acceptable for supporting the Price Negotiation Memorandum. 55 CONS shall accept or reject the CORs technical evaluation within 2 business days after receipt.

6.0 Negotiation

6.1 The Government contracting officer shall open negotiation by providing a TOR Negotiation Letter that states:

1) Aspects that the Government intends to negotiate
2) The rationale supporting the Government position
3) Any deficiencies in the proposal’s cost or pricing data

6.2 After the Contractor has received the TOR Negotiation Letter, negotiation between 55 CONS and the Contractor may employ any method(s) appropriate to the circumstances to achieve a win-win agreement. Methods may include email, telephone calls, or face-to-face meetings.

6.3 Upon conclusion of negotiations, the Government contracting officer shall close negotiation by providing written notice that negotiation is complete. The Contractor shall submit a final proposal revision within 5 business days after receipt of the contracting officer’s written request.

6.4 The Contractor’s final proposal revision shall include:

1) The updated Technical Proposal
2) The updated Cost Proposal
3) The updated Performance Work Statement
4) The signed Certificate of Current Cost or Pricing Data

7.0 Award

7.1 Before 55 CONS begins final documentation to award the order, the following documents are required from the COR:

1) The final version of any documents submitted as “draft” from Section 2

2) The final written technical evaluation explaining why the proposal is determined acceptable

3) Signature on the Quality Assurance Surveillance Plan (QASP)
4) Written confirmation that certified funds are still available to award the order

7.2 Although all applicable clauses from the overarching IDIQ contract remain in full force and affect for each order and do not need to be specifically restated; including these clauses serves as emphasis for particular concerns and to highlight order-specific information.

7.2.1 All orders shall contain the following clauses:
232.232-7006 – Wide Area Workflow Payment Instructions
252.227-7013 – Rights in Technical Data – Noncommercial Items
252.227-7030 – Technical Data – Withholding of Payment
252.227-7037 – Validation of Restrictive Markings on Technical Data
252.239-7018 – Supply Chain Risk
252.246-7001 – Warranty of Data

7.2.2 Individual orders may contain other clauses, as appropriate. Examples include:

52.232-20 – Limitation of Cost
52.232-22 – Limitation of Funds
52.217-9 – Option to Extend the Term of the Contract

252.227-7014 – Rights in Noncommercial Computer Software and Noncommercial Computer Software Documentation 252.232-7007 – Limitation of Government’s Obligation

8.0 Procurement Acquisition Lead Time (PALT) – Consolidated Summary This is the standard PALT, including time for negotiation. The timeline below assumes the total value of the action (including all options) is less than $5M and negotiation is not required.

Event
Lead

Time Cumulative Business Days

55 CONS receives complete requirements package (TADS Ordering Process, Section 2)

0 Days
T +0
55 CONS reviews the requirements package
2 Days
T +2

55 CONS emails the TOR package to the Contractor (TADS Ordering Process, Section 3)

1 Day
T +3

Contractor sends proposal to 55 CONS (TADS Ordering Process, Section 4)

20 Days
T +23

COR submits technical evaluation (TADS Ordering Process, Section 5)

10 Days
T +33
55 CONS reviews technical evaluation
2 Day
T +35
55 CONS prepares clearance package
6 Days
T +41

55 CONS receives clearance to award (TADS Ordering Process, Section 7)

5 Days
T +46
Contractor and 55 CONS sign the DD Form 1155 to award the order
2 Days
T +48

9.0 Proposal Adequacy Checklist

252.215-7009 -- PROPOSAL ADEQUACY CHECKLIST (JAN 2014)

The offeror shall complete the following checklist, providing location of requested information, or an explanation of why the requested information is not provided. In preparation of the offeror’s checklist, offerors may elect to have their prospective subcontractors use the same or similar checklist as appropriate.

PROPOSAL ADEQUACY CHECKLIST

REFERENCES

SUBMISSION

ITEM

PROPOSAL PAGE No.
If not provided EXPLAIN (may use continuation pages)

GENERAL INSTRUCTIONS

1.
FAR 15.408, Table 15-2, Section I Paragraph A
Is there a properly completed first page of the proposal per FAR 15.408 Table 15-2 I.A or as specified in the solicitation?
2.
FAR 15.408, Table 15-2, Section I Paragraph A(7)

Does the proposal identify the need for Government-furnished material/tooling/test equipment? Include the accountable contract number and contracting officer contact information if known.

3.
FAR 15.408, Table 15-2, Section I Paragraph A(8)
Does the proposal identify and explain notifications of noncompliance with Cost Accounting Standards Board or Cost Accounting Standards (CAS); any proposal inconsistencies with your disclosed practices or applicable CAS; and inconsistencies with your established estimating and accounting principles and procedures?
4.
FAR 15.408, Table 15-2, Section I,

Paragraph C(1)

FAR 2.101, “Cost or pricing data” Does the proposal disclose any other known activity that could materially impact the costs?

This may include, but is not limited to, such factors as—

(1) Vendor quotations;

(2) Nonrecurring costs;

(3) Information on changes in production methods and in production or purchasing volume;

(4) Data supporting projections of business prospects and objectives and related operations costs;

(5) Unit-cost trends such as those associated with labor efficiency;

(6) Make-or-buy decisions;

(7) Estimated resources to attain business goals; and

(8) Information on management decisions that could have a significant bearing on costs.

5.
FAR 15.408, Table 15-2, Section I Paragraph B

Is an Index of all certified cost or pricing data and information accompanying or identified in the proposal provided and appropriately referenced?

6.
FAR 15.403-1(b)
Are there any exceptions to submission of certified cost or pricing data pursuant to FAR 15.403-1(b)? If so, is supporting documentation included in the proposal? (Note questions 18-20.)
7.
FAR 15.408, Table 15-2, Section I Paragraph C(2)(i)

Does the proposal disclose the judgmental factors applied and the mathematical or other methods used in the estimate, including those used in projecting from known data?

8.
FAR 15.408, Table 15-2, Section I Paragraph C(2)(ii)
Does the proposal disclose the nature and amount of any contingencies included in the proposed price?
9.
FAR 15.408 Table 15-2, Section II, Paragraph A or B
Does the proposal explain the basis of all cost estimating relationships (labor hours or material) proposed on other than a discrete basis?
10.
FAR 15.408, Table 15-2, Section I Paragraphs D and E
Is there a summary of total cost by element of cost and are the elements of cost cross-referenced to the supporting cost or pricing data? (Breakdowns for each cost element must be consistent with your cost accounting system, including breakdown by year.)
11.
FAR 15.408, Table 15-2, Section I Paragraphs D and E
If more than one Contract Line Item Number (CLIN) or sub Contract Line Item Number (sub-CLIN) is proposed as required by the RFP, are there summary total amounts covering all line items for each element of cost and is it cross-referenced to the supporting cost or pricing data?
12.
FAR 15.408, Table 15-2, Section I Paragraph F
Does the proposal identify any incurred costs for work performed before the submission of the proposal?
13.
FAR 15.408, Table 15-2, Section I Paragraph G
Is there a Government forward pricing rate agreement (FPRA)? If so, the offeror shall identify the official submittal of such rate and factor data. If not, does the proposal include all rates and factors by year that are utilized in the development of the proposal and the basis for those rates and factors?

COST ELEMENTS

MATERIALS AND SERVICES

14.
FAR 15.408, Table 15-2, Section II Paragraph A
Does the proposal include a consolidated summary of individual material and services, frequently referred to as a Consolidated Bill of Material (CBOM), to include the basis for pricing? The offeror’s consolidated summary shall include raw materials, parts, components, assemblies, subcontracts and services to be produced or performed by others, identifying as a minimum the item, source, quantity, and price.

SUBCONTRACTS (Purchased materials or services)

15.
DFARS 215.404-3
Has the offeror identified in the proposal those subcontractor proposals, for which the contracting officer has initiated or may need to request field pricing analysis?
16.
FAR 15.404-3(c)

FAR 52.244-2

Per the thresholds of FAR 15.404-3(c), Subcontract Pricing Considerations, does the proposal include a copy of the applicable subcontractor’s certified cost or pricing data?

17.
FAR 15.408, Table 15-2,

Note 1;

Section II Paragraph A Is there a price/cost analysis establishing the reasonableness of each of the proposed subcontracts included with the proposal?

If the offeror’s price/cost analyses are not provided with the proposal, does the proposal include a matrix identifying dates for receipt of subcontractor proposal, completion of fact finding for purposes of price/cost analysis, and submission of the price/cost analysis?

EXCEPTIONS TO CERTIFIED COST OR PRICING DATA

18.
FAR 52.215-20

FAR 2.101,

“commercial item” Has the offeror submitted an exception to the submission of certified cost or pricing data for commercial items proposed either at the prime or subcontractor level, in accordance with provision 52.215-20?

a. Has the offeror specifically identified the type of commercial item claim (FAR 2.101 commercial item definition, paragraphs (1) through (8)), and the basis on which the item meets the definition?

b. For modified commercial items (FAR 2.101 commercial item definition paragraph (3)); did the offeror classify the modification(s) as either—

i. A modification of a type customarily available in the commercial marketplace (paragraph (3)(i)); or

ii. A minor modification (paragraph (3)(ii)) of a type not customarily available in the commercial marketplace made to meet Federal Government requirements not exceeding the thresholds in FAR 15.403-1(c)(3)(iii)(B)?

c. For proposed commercial items “of a type”, or “evolved” or modified (FAR 2.101 commercial item definition paragraphs (1) through (3)), did the contractor provide a technical description of the differences between the proposed item and the comparison item(s)?

19.

[Reserved]

20.
FAR 15.408, Table 15-2, Section II Paragraph A(1)
Does the proposal support the degree of competition and the basis for establishing the source and reasonableness of price for each subcontract or purchase order priced on a competitive basis exceeding the threshold for certified cost or pricing data?

INTERORGANIZATIONAL TRANSFERS

21.
FAR 15.408, Table 15-2, Section II Paragraph A.(2)
For inter-organizational transfers proposed at cost, does the proposal include a complete cost proposal in compliance with Table 15-2?
22.
FAR 15.408, Table 15-2, Section II Paragraph A(1)
For inter-organizational transfers proposed at price in accordance with FAR 31.205-26(e), does the proposal provide an analysis by the prime that supports the exception from certified cost or pricing data in accordance with FAR 15.403-1?

DIRECT LABOR

23.
FAR 15.408, Table 15-2, Section II Paragraph B
Does the proposal include a time phased (i.e.; monthly, quarterly) breakdown of labor hours, rates and costs by category or skill level? If labor is the allocation base for indirect costs, the labor cost must be summarized in order that the applicable overhead rate can be applied.
24.
FAR 15.408, Table 15-2, Section II Paragraph B
For labor Basis of Estimates (BOEs), does the proposal include labor categories, labor hours, and task descriptions, (e.g.; Statement of Work reference, applicable CLIN, Work Breakdown Structure, rationale for estimate, applicable history, and time-phasing)?
25.
FAR subpart 22.10
If covered by the Service Contract Labor Standards statute (41 U.S.C. chapter 67), are the rates in the proposal in compliance with the minimum rates specified in the statute?

INDIRECT COSTS

26.
FAR 15.408, Table 15-2, Section II Paragraph C
Does the proposal indicate the basis of estimate for proposed indirect costs and how they are applied? (Support for the indirect rates could consist of cost breakdowns, trends, and budgetary data.)

OTHER COSTS

27.
FAR 15.408, Table 15-2, Section II Paragraph D
Does the proposal include other direct costs and the basis for pricing? If travel is included does the proposal include number of trips, number of people, number of days per trip, locations, and rates (e.g. airfare, per diem, hotel, car rental, etc)?
28.
FAR 15.408, Table 15-2, Section II Paragraph E
If royalties exceed $1,500 does the proposal provide the information/data identified by Table 15-2?

29.

FAR 15.408, Table 15-2, Section II Paragraph F
When facilities capital cost of money is proposed, does the proposal include submission of Form CASB-CMF or reference to an FPRA/FPRP and show the calculation of the proposed amount?

FORMATS FOR SUBMISSION OF LINE ITEM SUMMARIES

30.
FAR 15.408, Table 15-2, Section III
Are all cost element breakdowns provided using the applicable format prescribed in FAR 15.408, Table 15-2 III? (or alternative format if specified in the request for proposal)
31.
FAR 15.408, Table 15-2, Section III Paragraph B
If the proposal is for a modification or change order, have cost of work deleted (credits) and cost of work added (debits) been provided in the format described in FAR 15.408, Table 15-2.III.B?
32.
FAR 15.408, Table 15-2, Section III Paragraph C
For price revisions/redeterminations, does the proposal follow the format in FAR 15.408, Table 15-2.III.C?

OTHER

33.
FAR 16.4
If an incentive contract type, does the proposal include offeror proposed target cost, target profit or fee, share ratio, and, when applicable, minimum/maximum fee, ceiling price?
34.
FAR 16.203-4 and FAR

15.408 Table 15-2, Section II, Paragraphs A, B, C, and D

If Economic Price Adjustments are being proposed, does the proposal show the rationale and application for the economic price adjustment?

35.

FAR 52.232-28
If the offeror is proposing Performance-Based Payments did the offeror comply with FAR 52.232-28?
36.
FAR 15.408(n)

FAR 52.215-22

FAR 52.215-23

Excessive Pass-through Charges– Identification of Subcontract Effort: If the offeror intends to subcontract more than 70% of the total cost of work to be performed, does the proposal identify: (i) the amount of the offeror’s indirect costs and profit applicable to the work to be performed by the proposed subcontractor(s); and (ii) a description of the added value provided by the offeror as related to the work to be performed by the proposed subcontractor(s)?

(End of Provision)