A009 - CDRL Metrics.docx
DOCX document 15 KB Posted
- Attached to
- Air Vehicle Planning System V
- Solicitation number
- FA4600-11-R-0028
About this file
CDRL A009
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Metrics The following table enumerates the set of metrics that shall be delivered as part of the CDRL A009. Contractor format may be used so long as all information required is provided.
| Measure |
| Purpose |
| Sample Questions Addressed |
| CDRL |
| Effort |
| The Effort measure counts the number of hours of effort applied to software tasks. This measure should include both estimated and actual hours for every SCR included in a given release. This measure usually correlates directly with software cost, but can also be used to address other common information categories including Schedule and Progress. |
| - Is/Was effort expended according to plan? |
- Do/Did certain tasks or activities taking more/less effort than expected?
- Is/Was the effort profile realistic?
- Software Version Description (SVD)
File details come from the government source that posted it. Updated .