Attachment 1 - Bldg 975 Specifications.pdf
PDF 10 MB Posted
- Attached to
- Repair CRL Bldg 975 Federal contract opportunity
- Solicitation number
- FA4528-20-R-0003
About this file
This solicitation is for repair work on Building 975 at Minot Air Force Base. The goal of the project is to complete a total renovation of the interior and exterior site work, including 15% general work, 35% architectural, 25% mechanical, and 25% electrical. The work includes repairing common rotary launchers and providing storage for new equipment. The response deadline is not specified. The solicitation involves the Department of the Air Force Global Strike Command for the project work.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA4528-20-R-0003 Amendment 3.pdf | ||
| Attachment 9 - Revised Drawing Amendment Item List #1.pdf | ||
| Attachment 9 - Drawing Amendment Item List #1.pdf | ||
| FA4528-20-R-0003 Amendment 2.pdf | ||
| Attachment 8 - Questions and Answers.pdf | ||
| FA4528-20-R-0003 Amendment 1.pdf | ||
| Attachment 2 - Bldg 975 Drawings.pdf | ||
| Attachment 4 - Past Performance Information (PPIF).docx | DOCX document | |
| Attachment 6 - Section L - Instructions to Offerors_CRL.docx | DOCX document | |
| Solicitation - FA452820R0003.pdf | ||
| Attachment 5 - Financial Reference.docx | DOCX document | |
| Attachment 3 - DBA Wage Determination - 4 Oct 19.pdf | ||
| Synopsis Notice FY20.doc | DOC document | |
| Attachment 7 - Section M - Evaluations_CRL.docx | DOCX document |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
S P E C I F I C A T I O N
FOR PROJECT
QJVF14-0026
REPAIR CRL Mx & STORAGE B975
AT
MINOT AIR FORCE BASE, NORTH DAKOTA
PREPARED BY:
5 CES, ENGINEERING FLIGHT
MINOT AIR FORCE BASE, NORTH DAKOTA
100% SUBMITTAL
18 MARCH 2016
FA452820R0003
Attachment 1
I HEREBY CERTIFY THAT THIS ENGINEERING
DOCUMENT WAS PREPARED BY ME OR UNDER MY
DIRECT PERSONAL SUPERVISION AND THAT I AM A
DULY LICENSED PROFESSIONAL ENGINEER UNDER
THE LAWS OF THE STATE OF NORTH DAKOTA
0, 1, 2, 6, 7, 8, 9, 10, 12
SPECIFICATION DIVISIONS COVERED BY THIS SEAL:
STEPHEN R. SMITH, AIA
ARCHITECT DATE
I HEREBY CERTIFY THAT THIS ENGINEERING
DOCUMENT WAS PREPARED BY ME OR UNDER MY
DIRECT PERSONAL SUPERVISION AND THAT I AM A
DULY LICENSED PROFESSIONAL ENGINEER UNDER
THE LAWS OF THE STATE OF NEBRASKA
31, 32, 33
SPECIFICATION DIVISIONS COVERED BY THIS SEAL:
CHRISTOPHER J. LANGAN, PE
CIVIL ENGINEER DATE
I HEREBY CERTIFY THAT THIS ENGINEERING
DOCUMENT WAS PREPARED BY ME OR UNDER MY
DIRECT PERSONAL SUPERVISION AND THAT I AM A
DULY LICENSED PROFESSIONAL ENGINEER UNDER
THE LAWS OF THE STATE OF NEBRASKA
3, 4, 5
SPECIFICATION DIVISIONS COVERED BY THIS SEAL:
JEFFREY A. EHLER, PE
STRUCTURAL ENGINEER DATE
18 MARCH 2016
18 MARCH 2016
18 MARCH 2016
R
C
H
I
T
E
C
T
A
D
E
C
I
L
N
S
E
T
S
M
S
R
N
E
H
P
E
T
S
(2625)
T
I
H
A
T
E
O
F
N
RO
T
H
D
A
K
O
T
A
3/18/16
{Repair CRL Mx & Storage B975, Minot AFB, ND} {QJVF 14-0026}
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 15 LIST OF DRAWINGS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 33 29 SUSTAINABILITY REPORTING
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.10 20 QUALITY CONTROL FOR MINOR CONSTRUCTION
01 57 20.00 10 ENVIRONMENTAL PROTECTION
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
01 78 39 AS-BUILT DRAWINGS
01 91 00.00 40 COMMISSIONING
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
02 82 14.00 10 ASBESTOS HAZARD CONTROL ACTIVITIES
02 82 33.13 20 REMOVAL/CONTROL AND DISPOSAL OF PAINT WITH LEAD
DIVISION 03 - CONCRETE
03 20 00.00 10 CONCRETE REINFORCING
03 30 00 CAST-IN-PLACE CONCRETE
DIVISION 04 - MASONRY
04 20 00 MASONRY
DIVISION 05 - METALS
05 05 23.16 STRUCTURAL WELDING
05 12 00 STRUCTURAL STEEL
05 50 13 MISCELLANEOUS METAL FABRICATIONS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS
06 61 16 SOLID POLYMER (SOLID SURFACING) FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 13 BOARD AND BLOCK INSULATION
07 21 16 MINERAL FIBER BLANKET INSULATION
07 42 13 METAL WALL PANELS
07 53 23 ETHYLENE-PROPYLENE-DIENE-MONOMER ROOFING
07 57 13 SPRAYED POLYURETHANE FOAM (SPF)
07 60 00 FLASHING AND SHEET METAL
07 92 00 JOINT SEALANTS
PROJECT TABLE OF CONTENTS Page 1
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 33 13 COILING COUNTER DOORS
08 36 13 SECTIONAL OVERHEAD DOORS
08 51 13 ALUMINUM WINDOWS
08 60 45 TRANSLUCENT PANELS
08 62 50 TUBULAR DAYLIGHTING DEVICE
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
08 91 00 METAL WALL LOUVERS
DIVISION 09 - FINISHES
09 06 90 COLOR SCHEDULE
09 22 00 SUPPORTS FOR GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 30 13 CERAMIC TILING
09 51 00 ACOUSTICAL CEILINGS
09 65 00 RESILIENT FLOORING
09 67 23.15 FUEL RESISTIVE RESINOUS FLOORING, 3-COAT SYSTEM
09 90 00 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 14 00.20 INTERIOR SIGNAGE
10 21 13 TOILET COMPARTMENTS
10 26 00 WALL PROTECTION
10 28 13 TOILET ACCESSORIES
10 44 16 FIRE EXTINGUISHERS
10 51 13 METAL LOCKERS
DIVISION 12 - FURNISHINGS
12 21 00 WINDOW BLINDS
12 48 13 ENTRANCE FLOOR MATS AND FRAMES
DIVISION 21 - FIRE SUPPRESSION
21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 08 00.00 10 COMMISSIONING OF HVAC SYSTEMS
23 09 23.13 20 BACnet DIRECT DIGITAL CONTROL SYSTEMS FOR HVAC
23 11 25 FACILITY GAS PIPING
23 23 00 REFRIGERANT PIPING
23 54 16.00 10 HEATING SYSTEM; GAS-FIRED HEATERS
23 74 33.00 40 PACKAGED, OUTDOOR, HEATING AND COOLING MAKEUP
AIR-CONDITIONERS
23 82 02.00 10 UNITARY HEATING AND COOLING EQUIPMENT
PROJECT TABLE OF CONTENTS Page 2
23 82 46.00 40 ELECTRIC UNIT HEATERS
DIVISION 26 - ELECTRICAL
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 27 13.10 30 ELECTRIC METERS
26 42 14.00 10 CATHODIC PROTECTION SYSTEM (SACRIFICIAL ANODE)
26 51 00 INTERIOR LIGHTING
26 56 00 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 11 00 CLEARING AND GRUBBING
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID
PAVEMENTS
32 12 17 HOT MIX BITUMINOUS PAVEMENT
32 16 13 CONCRETE SIDEWALKS AND CURBS AND GUTTERS
32 17 23.00 20 PAVEMENT MARKINGS
32 92 19 SEEDING
DIVISION 33 - UTILITIES
33 11 00 WATER DISTRIBUTION
33 40 00 STORM DRAINAGE UTILITIES
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 3
Document 00 01 15 Page 1
DOCUMENT 00 01 15
LIST OF DRAWINGS
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
GENERAL
G-001 COVER SHEET
G-002 INDEX OF DRAWINGS, LEGENDS AND GENERAL NOTES
G-003 ABBREVIATIONS
G-004 FIRE PROTECTION PLAN AND CODE ANALYSIS
CIVIL
V-001 TOPOGRAPHIC SURVEY
CD101 REMOVAL PLAN
C-101 GRADING PLAN
C-102 UTILITY PLAN
C-103 PAVING PLAN
C-104 CIVIL DETAILS
ARCHITECTURAL
AD100 COMPOSITE REMOVAL PLAN
AD101 PARTIAL REMOVAL PLAN
AD102 PARTIAL REMOVAL PLAN
A-100 COMPOSITE FLOOR PLAN AND PHASING PLAN
A-101 PARTIAL FLOOR PLAN
A-102 PARTIAL FLOOR PLAN
A-103 PARTIAL REFLECTED CEILING PLAN
A-104 PARTIAL REFLECTED CEILING PLAN
A-105 ROOF PLAN AND DETAILS
A-201 BUILDING ELEVATIONS
A-202 BUILDING ELEVATIONS
A-301 BUILDING SECTIONS
A-302 WALL SECTIONS
A-401 LARGE SCALE PLANS, INTERIOR ELEVATIONS AND DETAILS
A-501 EXTERIOR DETAILS
A-601 ROOM FINISH SCHEDULE
A-602 DOOR AND FRAME SCHEDULE, AND DOOR, FRAME AND LOUVER TYPES
A-701 DOOR AND FRAME DETAILS
A-702 DOOR AND FRAME DETAILS
I-100 FURNITURE PLANS
STRUCTURAL
S-001 GENERAL NOTES
S-101 PARTIAL FOUNDATION PLAN
S-102 PARTIAL FRAMING PLAN
Document 00 01 15 Page 2
S-103 PARTIAL FRAMING PLAN
S-201 FOUNDATION DETAILS
S-301 FRAMING DETAILS
S-302 FRAMING DETAILS
FIRE PROTECTION
FG001 FIRE PROTECTION SYMBOLS LEGEND AND GENERAL NOTES
FD101 FIRE PROTECTION DEMOLITION PARTIAL FLOOR PLAN
FD102 FIRE PROTECTION DEMOLITION PARTIAL FLOOR PLAN
FX101 FIRE SUPPRESSION PARTIAL FLOOR PLAN
FX102 FIRE SUPPRESSION PARTIAL FLOOR PLAN
FX201 FIRE SUPPRESSION DETAILS AND SCHEDULES
FA101 FIRE ALARM FLOOR PLAN
FA102 FIRE ALARM PARTIAL FLOOR PLAN
FA201 FIRE ALARM DETAILS AND RISERS DIAGRAM
PLUMBING
PG101 PLUMBING SYMBOLS AND GENERAL NOTES
PD101 UNDERFLOOR PLUMBING DEMOLITION FLOOR PLAN
PD201 PLUMBING DEMOLITION PARTIAL FLOOR PLAN
PD202 PLUMBING DEMOLITION PARTIAL FLOOR PLAN
P-101 UNDERFLOOR PLUMBING PLAN
P-201 PLUMBING PARTIAL PLAN
P-202 PLUMBING PARTIAL PLAN
P-301 UNDERFLOOR PLUMBING ENLARGED FLOOR PLANS
P-302 PLUMBING ENLARGED FLOOR PLANS
P-401 PLUMBING RISERS
P-402 PLUMBING RISERS
P-403 PLUMBING RISERS
P-501 PLUMBING DETAILS
P-502 PLUMBING DETAILS
P-601 PLUMBING FIXTURE AND EQUIPMENT SCHEDULES
P-602 PLUMBING FIXTURE AND EQUIPMENT SCHEDULES
MECHANICAL
MG101 MECHANCIAL SYMBOLS LEGEND
MG102 MECHANCIAL GENERAL NOTES
MD101 HVAC DEMOLITION PARTIAL FLOOR PLAN
MD102 HVAC DEMOLITION PARTIAL FLOOR PLAN
MD201 HVAC PIPING DEMOLITION PARTIAL FLOOR PLAN
MD202 HVAC PIPING DEMOLITION PARTIAL FLOOR PLAN
MH101 PARTIAL HVAC FLOOR PLAN
MH102 PARTIAL HVAC FLOOR PLAN
MP101 HVAC PIPING PLAN
M-301 MECHANICAL ENLARGED FLOOR PLANS
M-401 MECHANICAL CONTROLS
M-402 MECHANICAL CONTROLS
M-403 MECHANICAL CONTROLS
M-501 MECHANICAL DETAILS
M-502 MECHANICAL DETAILS
M-601 MECHANICAL SCHEDULES
M-602 MECHANICAL SCHEDULES
M-603 MECHANICAL SCHEDULES
M-701 FLOW DIAGRAMS
ELECTRICAL
EG101 ELECTRICAL SYMBOLS AND GENERAL NOTES
Document 00 01 15 Page 3
ES101 ELECTRICAL SITE PLAN
ED101 ELECTRICAL DEMOLITION PARTIAL FLOOR PLAN
ED102 ELECTRICAL DEMOLITION PARTIAL FLOOR PLAN
EL101 LIGHTING PARTIAL FLOOR PLAN
EL102 LIGHTING PARTIAL FLOOR PLAN
EL103 LIGHT TUBE AVERAGE FOOT CANDLE PERFORMANCE FLOOR PLAN
EP101 POWER PARTIAL FLOOR PLAN
EP102 POWER PARTIAL FLOOR PLAN
EY101 SPECIAL SYSTEMS PARTIAL FLOOR PLAN
EY102 SPECIAL SYSTEMS PARTIAL FLOOR PLAN
EY201 SPECIAL SYSTEMS RISERS AND DETAILS
E-401 ELECTRICAL ENLARGED FLOOR PLANS
E-501 ELECTRICAL ONE-LINE DIAGRAM
E-601 ELECTRICAL DETAILS
E-602 ELECTRICAL DETAILS
E-701 ELECTRICAL SCHEDULES
E-702 ELECTRICAL SCHEDULES
E-703 ELECTRICAL SCHEDULES
-- End of Document --
Section 01 11 00 Page 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
The Munitions Maintenance building, Building No. 975, is a one story, 41,912 GSF facility located in the vicinity of the airfield. The building serves as the 5th Munitions Squadron's maintenance facility for B-52 bomber bomb-bay and under-wing conventional weapon systems. The facility supports approximately 30 personnel operating in two to three shifts per work day.
The original building was constructed around 1962 with an addition added approximately 1983.
The facility currently does not meet the needs of the 5th Munitions Squadron (user). The building will need space for 20 to 22 new common rotary launchers (CRLs) by Fiscal Year (FY) 2018. By FY 2016, 10 of those will need storage space, as they will be delivered by then. This new requirement is downward directed by Air Force Global Strike Command (AFGSC). The age and condition of the facility requires some modifications to the interior to make room for the new CRLs and to make a modern maintenance and storage facility. Furthermore, 10 additional personnel will be assigned to the facility.
Deficiencies identified by the users include: replace overhead door seals;
replace personnel doors; replace or repair windows (air and snow/rain comes in the windows); paint floors a white color to be reflective and increase reflectivity to increase light in the maintenance and storage areas; replace aged insulation; renovate and right-size restrooms for the amount of personnel in the building, and fix plumbing issues as well; add a water fountain near the restrooms; replace all interior finishes in office areas to include flooring, wall finishes (paint), ceilings, etc.; repair and/or replace electrical and communications systems as needed; and add awning and snow guards over the personnel doors facing the parking lot.
1.1.2 Location
The work is located northeast of the flightline, as shown on the cover sheet of the Contract Drawings.
1.2 WORK RESCHEDULING
Allow for a maximum of 15 calendar days in the construction schedule where construction activity is prohibited due to military operations. Government will provide 24 hour notification each time the restrictions are invoked.
Normal duty hours for work are from 7:30 a.m. to 4:00 p.m., Monday through Friday. Requests for additional work requires written approval from the Contracting Officer 7 days in advance of the proposed work period.
Section 01 11 00 Page 2
1.3 OCCUPANCY OF PREMISES
This project requires phased construction. Portions of this building will be occupied during performance of work under this contract. See Contract Drawings for proposed Phasing Plan.
Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
1.4 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.5 ON-SITE PERMITS
1.5.1 Utility Outage Requests and Utility Connection Requests
Schedule work to minimize outages. For utility outages and connections required during the execution of work that affect existing systems, schedule outside the regular working hours or on weekends, as approved by the Contracting Officer. Schedule utility outages and connections to minimize disruptions to the Government. No additional payment will be provided for utility outages and connections required to be performed outside the regular work hours.
Submit requests for utility outages and connections in writing to the Contracting Officer for approval at least 7 calendar days in advance of the time required. In each request, state the system involved, area involved, approximate duration of outage, and the nature of work involved.
1.6 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.
Contact local utility locating service a minimum of 48 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings within area of work.
Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered.
Verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by
Section 01 11 00 Page 3 piping, ducts, and other work to be constructed or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.6.1 Notification Prior to Excavation
Notify the Contracting Officer at least 48 hours prior to starting excavation work.
1.7 SALVAGE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area located within 3 miles of the construction site.
Provide a salvage plan, listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Use a system of property control that is approved by the Contracting Officer. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
Section 01 14 00 Page 1
SECTION 01 14 00
WORK RESTRICTIONS
1.1 SUBMITTALS
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel
Personnel List
Vehicle List
1.2 SPECIAL SCHEDULING REQUIREMENTS
a. Permission to interrupt any roads, railroads, and/or utility service must be requested in writing a minimum of 7 calendar days prior to the desired date of interruption.
b. The work under this contract requires special attention to the scheduling and conduct of the work in connection with existing operations. Identify on the construction schedule each factor which constitutes a potential interruption to operations.
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
Ensure that Contractor personnel become familiar with and obey regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. To minimize traffic congestion, delivery of materials must be outside of peak traffic hours (6:30 to 8:00 a.m. and 3:30 to 5:00 p.m.) unless otherwise approved by the Contracting Officer. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry.
Mark Contractor equipment for identification.
1.3.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.3.1.2 Identification Badges and Installation Access
Personnel must be able to meet REAL ID Act of 2005 requirements to obtain access to base. The contractor shall submit to the Contracting Officer a Personnel Listing in three copies with each employee's name as it appears on
Section 01 14 00 Page 2 the employee's primary form of picture identification (i.e., State Driver’s License), address and telephone number of the firm that will be working at the construction site. This listing must be provided no later than the date of the preconstruction conference. Changes to the list will take place prior to employees arriving at the job site. Each employee shall have two forms of identification to be permitted entry into the job site. One form of identification shall have a picture.
1.3.1.3 Employee List
The Contractor must provide to the Contracting officer, in writing, the names of two designated representatives authorized to request personnel and vehicle passes for employees and subcontractor's employees prior to commencement of work under this contract.
1.3.1.4 Personnel Entry Approval
Failure to obtain entry approval will not affect the contract price or time of completion.
1.3.1.5 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.3.2 Working Hours
Regular working hours must consist of an 8 1/2 hour period, between 7:30 a.m. and 4:00 p.m., Monday through Friday, excluding Government holidays.
1.3.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 7 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.
1.3.4 Occupied and Existing Building
The Contractor shall be working in an existing building which is occupied.
The existing buildings and their contents must be kept secure at all times.
Provide temporary closures as required to maintain security as directed by the Contracting Officer.
The Government will remove Government property in the areas of the building scheduled to receive work.
Section 01 14 00 Page 3
1.3.5 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours."
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, and compressed air are considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours."
1.4 SECURITY REQUIREMENTS
Contract Clause "FAR 52.204-2, Security Requirements and Alternate II," "FAC 5252.236-9301, Special Working Conditions and Entry to Work Area," and the Minot Air Force Base Integrated Defense Plan 31 apply.
1.4.1 Personnel List
Submit for approval, at least 15 days prior to the desired date of entry, an original alphabetical list of personnel who require entry into Government property to perform work on the project. Furnish for each person:
a. Name
b. Date and place of birth
c. Citizenship
d. Home address
e. Social security number
f. Current pass expiration date
g. Naturalization or Alien Registration number
h. Passport number, place of issue, and expiration date
The request for personnel passes must be accompanied with the following certification:
"I hereby certify that all personnel on this list are either born U.S.
citizens, naturalized U.S. citizens with the naturalization number shown, or legal aliens with the alien registration number indicated."
Signature/Firm Name
1.4.1.1 Citizenship Requirements
Aliens will not be admitted to the work site without approval. Clearance for aliens may require approximately 20 work days for approval.
Section 01 14 00 Page 4
1.4.1.2 Documents Acceptable for Proof of Citizenship
a. Birth registration card
b. Certificate of live birth, birth certificate
c. Certificate of Naturalization
d. Certificate of registration
e. DD-214 (Must Cite Birthplace)
f. DD Form 4 (Contract for Enlistment and Must Cite Birthplace)
g. DD 1966 (Application for Enlistment)
h. Military discharge papers (must cite birthplace)
i. Delayed birth certificate
j. Hawaii certificate of foreign birth
k. Hospital birth certificate
l. Marriage license certificate
m. Merchant marine certificate
n. Military officer ID card
o. Notification of birth registration
p. USA passport
1.4.2 Vehicle List
Submit an original list of vehicles to be utilized at the work site with the following information for each vehicle:
a. Make
b. Year
c. Model
d. License number
e. Registered owner
1.4.3 Passes
Submit request for personnel and vehicle passes together. Include the Certificate of Insurance for Contractor and Subcontractor(s) and the Statement of Acknowledgement Form SF 1413 with the submittal. Passes will normally be issued within 21 days.
Section 01 14 00 Page 5
1.4.3.1 Control
Maintain strict accountability over passes. Immediately report to the source of issue, passes missing or lost and the circumstances. If the Contractor has another active contract or one commencing immediately, employees' names may be transferred from one contract to the other. Final payment will not be effected until employees are transferred to another contract or the records are cleared. Furnish a signed letter, countersigned by the source of issue, stating that passes have been turned in.
Not Used
Not Used
Section 01 32 01.00 10 Page 1
SECTION 01 32 01.00 10
PROJECT SCHEDULE
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AACE INTERNATIONAL (AACE)
AACE 29R-03 (2011) Forensic Schedule Analysis
AACE 52R-06 (2006) Time Impact Analysis - As Applied in
Construction
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems
1.2 SUBMITTALS
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
Project Scheduler Qualifications Preliminary Project Schedule Initial Project Schedule Periodic Schedule Update
1.3 PROJECT SCHEDULER QUALIFICATIONS
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification.
Representative must have a comprehensive knowledge of CPM scheduling principles and application.
2.1 SOFTWARE
The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.
Section 01 32 01.00 10 Page 2
2.1.1 Contractor Software
Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required sdef file must be created and supported by the software manufacturer.
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction design and construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules.
Prepare each Project Schedule using the Precedence Diagram Method (PDM).
3.1.1 Construction Progress Schedule
The contractor shall prepare and submit to the Contracting Officer for approval prior to construction beginning a Construction Progress Schedule, AF IMT 3064, showing the order in which the contractor proposes to perform the work. The schedule shall separate the work into phases developed in cooperation with the Government. The schedule shall include the dates on which the contractor contemplates starting and completing the salient elements of the work. The contractor shall also specifically identify on each Contract Progress Report, AF IMT 3065, any apparent, anticipated or proposed deviation from the previously approved schedule.
3.2 BASIS FOR PAYMENT AND COST LOADING
The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract Cost Line Item Number (CLIN) must equal the value of the CLIN.
3.2.1 Activity Cost Loading
Activity cost loading must be reasonable and without front-end loading.
Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.
3.2.2 Withholdings / Payment Rejection
Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.
In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule
Section 01 32 01.00 10 Page 3 revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.2 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.
Less than 2 percent of all non-procurement activities may have Original Durations (OD) greater than 20 work days or 30 calendar days.
3.3.3 Procurement Activities
Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.
3.3.4 Mandatory Tasks
Include the following activities/tasks in the initial project schedule and all updates.
a. Submission, review and acceptance of SD-01 Preconstruction Submittals
(individual activity for each).
b. Submission of mechanical/electrical/information systems layout drawings.
c. Long procurement activities
d. Submission and approval of O & M manuals.
e. Submission and approval of as-built drawings.
f. Submission and approval of DD1354 data and installed equipment lists.
g. Submission and approval of testing and air balance (TAB).
h. Submission of TAB specialist design review report.
i. Submission and approval of Building Commissioning Plan, test data, and reports: Develop the schedule logic associated with testing and commissioning of mechanical systems to a level of detail consistent with the contract commissioning requirements. All tasks associated with
Section 01 32 01.00 10 Page 4 all building testing and commissioning will be completed prior to submission of building commissioning report and subsequent contract completion.
j. Air and water balancing.
k. Building commissioning - Functional Performance Testing.
l. Controls testing plan submission.
m. Controls testing.
n. Performance Verification testing.
o. Other systems testing, if required.
p. Contractor's pre-final inspection.
q. Correction of punch list from Contractor's pre-final inspection.
r. Government's pre-final inspection.
s. Correction of punch list from Government's pre-final inspection.
t. Final inspection.
3.3.5 Government Activities
Show Government and other agency activities that could impact progress.
These activities include, but are not limited to: approvals, acceptance, design reviews, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
3.3.6 Standard Activity Coding Dictionary
Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11. This exact structure is mandatory. Develop and assign all Activity Codes to activities as detailed herein. A template SDEF compatible schedule backup file is available on the QCS web site:
http://rms.usace.army.mil.
The SDEF format is as follows:
Field Activity Code Length Description
1 WRKP 3 Workers per day
2 RESP 4 Responsible party
3 AREA 4 Area of work
4 MODF 6 Modification Number
5 BIDI 6 Bid Item (CLIN) http://rms.usace.army.mil/
Section 01 32 01.00 10 Page 5
Field Activity Code Length Description
6 PHAS 2 Phase of work
7 CATW 1 Category of work
8 FOW 20 Feature of work*
*Some systems require that FEATURE OF WORK values be placed in several activity code fields. The notation shown is for Primavera P6. Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements.
3.3.6.1 Workers Per Day (WRKP)
Assign Workers per Day for all field construction or direct work activities, if directed by the Contracting Officer. Workers per day is based on the average number of workers expected each day to perform a task for the duration of that activity.
3.3.6.2 Responsible Party Coding (RESP)
Assign responsibility code for all activities to the Prime Contractor, Subcontractor(s) or Government agency(ies) responsible for performing the activity.
a. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government Furnished Property/Equipment (GFP) and Notice to Proceed (NTP) for phasing requirements.
b. Activities cannot have more than one Responsibility Code. Examples of acceptable activity code values are: ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for Minot AFB).
3.3.6.3 Area of Work Coding (AREA)
Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew, from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings. Activities cannot have more than one Work Area Code.
Not all activities are required to be Work Area coded. A lack of Work Area coding indicates the activity is not resource or space constrained.
3.3.6.4 Modification Number (MODF)
Assign a Modification Number Code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by Contracting Officer. Key all Code values to the Government's
Section 01 32 01.00 10 Page 6 modification numbering system. An activity can have only one Modification Number Code.
3.3.6.5 Bid Item Coding (BIDI)
Assign a Bid Item Code to all activities using the Contract Line Item Number (CLIN) to which the activity belongs, even when an activity is not cost loaded. An activity can have only one BIDI Code.
3.3.6.6 Phase of Work Coding (PHAS)
Assign Phase of Work Code to all activities. Examples of phase of work are design phase, procurement phase, and construction phase. Each activity can have only one Phase of Work code.
a. If the contract specifies phasing with separately defined performance periods, identify a Phase Code to allow filtering and organizing the schedule accordingly.
3.3.6.7 Category of Work Coding (CATW)
Assign a Category of Work Code to all activities. Category of Work Codes include, but are not limited to review conferences, permits, construction submittals, procurement, fabrication, weather sensitive installation, non-weather sensitive installation, start-up, and testing activities. Each activity can have no more than one Category of Work Code.
3.3.6.8 Feature of Work Coding (FOW)
Assign a Feature of Work Code to appropriate activities based on the Definable Feature of Work to which the activity belongs based on the approved QC plan.
Definable Feature of Work is defined in Section 01 45 00.10 20 QUALITY CONTROL FOR MINOT CONSTRUCTION. An activity can have only one Feature of Work Code.
3.3.7 Contract Milestones and Constraints
Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.
Mandatory constraints that ignore or effect network logic are prohibited.
No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for approval on a case by case basis.
3.3.7.1 Project Start Date Milestone and Constraint
The first activity in the project schedule must be a start milestone titled "NTP Acknowledged," which must have a "Start On" constraint date equal to the date that the NTP is acknowledged.
3.3.7.2 End Project Finish Milestone and Constraint
Section 01 32 01.00 10 Page 7
The last activity in the schedule must be a finish milestone titled "End Project."
Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the longest path.
The Government is under no obligation to accelerate Government activities to support a Contractor's early completion.
3.3.7.3 Interim Completion Dates and Constraints
Constrain contractually specified interim completion dates to show negative float when the calculated late finish date of the last activity in that phase is later than the specified interim completion date.
3.3.7.3.1 Start Phase
Use a start milestone as the first activity for a project phase. Call the start milestone "Start Phase X" where "X" refers to the phase of work.
3.3.7.3.2 End Phase
Use a finish milestone as the last activity for a project phase. Call the finish milestone "End Phase X" where "X" refers to the phase of work.
3.3.8 Calendars
Schedule activities on a Calendar to which the activity logically belongs.
Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government Acceptance activities, concrete cure times, etc. Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays. Develop Seasonal Calendar(s) and assign to seasonally affected activities as applicable.
If an activity is weather sensitive it should be assigned to a calendar showing non-work days on a monthly basis, with the non-work days selected at random across the weeks of the calendar, using the anticipated days provided in the contract clause TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER. Assign non-work days over a seven-day week as weather records are compiled on seven-day weeks, which may cause some of the weather related non-work days to fall on weekends.
3.3.8.1 Scheduled Project Completion and Activity Calendars
The schedule interval shall extend from the notice to proceed (NTP) date to the required contract completion date. The contract completion activity (End Project) shall finish based on the required contract duration in the accepted contract proposal, as adjusted for any approved contract time extensions. The first scheduled work period shall be the day after NTP is received by the Contractor. Schedule activities on a calendar to which the activity logically belongs. Activities may be assigned to a 7 day calendar when the contract assigns calendar day durations for the activity such as a Government Acceptance activity. If the Contractor intends to perform physical work less than seven days per week, schedule the associated activities on a calendar with non-work periods identified including weekends
Section 01 32 01.00 10 Page 8 and holidays. Assign the Category of Work Code - Weather Sensitive Installation to those activities that are weather sensitive.
Original durations must account for anticipated normal adverse weather.
The Government will interpret all work periods not identified as non-work periods on each calendar as meaning the Contractor intends to perform work during those periods.
3.3.9 Open Ended Logic
Only two open ended activities are allowed: the first activity "NTP Acknowledged" may have no predecessor logic, and the last activity -"End Project" may have no successor logic.
Predecessor open ended logic may be allowed in a time impact analyses upon the Contracting Officer's approval.
3.3.10 Default Progress Data Disallowed
Actual Start and Finish dates must not automatically update with default mechanisms included in the scheduling software. Updating of the percent complete and the remaining duration of any activity must be independent functions. Disable program features that calculate one of these parameters from the other. Activity Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process must match those dates provided in the Contractor Quality Control Reports. Failure to document the AS and AF dates in the Daily Quality Control report will result in disapproval of the Contractor's schedule.
3.3.11 Out-of-Sequence Progress
Activities that have progressed before all preceding logic has been satisfied (Out-of-Sequence Progress) will be allowed only on a case-by-case basis subject to approval by the Contracting Officer. Propose logic corrections to eliminate out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule.
Address out of sequence progress or logic changes in the Narrative Report and in the periodic schedule update meetings.
3.3.12 Added and Deleted Activities
Do not delete activities from the project schedule or add new activities to the schedule without approval from the Contracting Officer. Activity ID and description changes are considered new activities and cannot be changed without Contracting Officer approval.
3.3.13 Original Durations
Activity Original Durations (OD) must be reasonable to perform the work item. OD changes are prohibited unless justification is provided and approved by the Contracting Officer.
3.3.14 Leads, Lags, and Start to Finish Relationships
Section 01 32 01.00 10 Page 9
Lags must be reasonable as determined by the Government and not used in place of realistic original durations, must not be in place to artificially absorb float, or to replace proper schedule logic.
a. Leads (negative lags) are prohibited.
b. Start to Finish (SF) relationships are prohibited.
3.3.15 Retained Logic
Schedule calculations must retain the logic between predecessors and successors ("retained logic" mode) even when the successor activity(s) starts and the predecessor activity(s) has not finished (out-of-sequence progress). Software features that in effect sever the tie between predecessor and successor activities when the successor has started and the predecessor logic is not satisfied ("progress override") are not be allowed.
3.3.16 Percent Complete
Update the percent complete for each activity started, based on the realistic assessment of earned value. Activities which are complete but for remaining minor punch list work and which do not restrain the initiation of successor activities may be declared 100 percent complete to allow for proper schedule management.
3.3.17 Remaining Duration
Update the remaining duration for each activity based on the number of estimated work days it will take to complete the activity. Remaining duration may not mathematically correlate with percentage found under paragraph entitled Percent Complete.
3.3.18 Cost Loading of Closeout Activities
Cost load the "Correction of punch list from Government pre-final inspection" activity(ies) not less than 1 percent of the present contract value. Activity(ies) may be declared 100 percent complete upon the Government's verification of completion and correction of all punch list work identified during Government pre-final inspection(s).
3.3.18.1 As-Built Drawings
If there is no separate contract line item (CLIN) for as-built drawings, cost load the "Submission and approval of as-built drawings" activity not less than $35,000 or 1 percent of the present contract value, which ever is greater, up to $200,000. Activity will be declared 100 percent complete upon the Government's approval.
3.3.18.2 O & M Manuals
Cost load the "Submission and approval of O & M manuals" activity not less than $20,000. Activity will be declared 100 percent complete upon the Government's approval of all O & M manuals.
3.3.19 Anticipated Adverse Weather
Section 01 32 01.00 10 Page 10
Paragraph applicable to contracts with clause entitled TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER. Reflect the number of anticipated adverse weather delays allocated to a weather sensitive activity in the activity's calendar.
3.3.20 Early Completion Schedule and the Right to Finish Early
An Early Completion Schedule is an Initial Project Schedule (IPS) that indicates all scope of the required contract work will be completed before the contractually required completion date.
a. No IPS indicating an Early Completion will be accepted without being fully resource-loaded (including crew sizes and manhours) and the Government agreeing that the schedule is reasonable and achievable.
b. The Government is under no obligation to accelerate work items it is responsible for to ensure that the early completion is met nor is it responsible to modify incremental funding (if applicable) for the project to meet the contractor's accelerated work.
3.4 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
This clause specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the contract clause entitled Fixed-Price Construction. In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the contractor.
The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.
MONTHLY ANTICIPATED ADVERSE WEATHER
DELAY WORK DAYS BASED ON (5) DAY WORK WEEK
Jan 23 Feb 17 Mar 13 Apr 4 May 3 Jun 6 Jul 3 Aug 4 Sep 4 Oct 3 Nov 12 Dec 20
Section 01 32 01.00 10 Page 11
Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the contractor will record on the daily CQC report the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the contractor's scheduled work day.
The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph b. above, the contracting officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the contract clause entitled Fixed-Price Construction.
3.5 PROJECT SCHEDULE SUBMISSIONS
Provide the submissions as described below. The data CD/DVD, reports, and network diagrams required for each submission are contained in paragraph SUBMISSION REQUIREMENTS. If the Contractor fails or refuses to furnish the information and schedule updates as set forth herein, then the Contractor will be deemed not to have provided an estimate upon which a progress payment can be made.
Review comments made by the Government on the schedule(s) do not relieve the Contractor from compliance with requirements of the Contract Documents.
3.5.1 Preliminary Project Schedule Submission
Within 15 calendar days after the NTP is acknowledged submit the Preliminary Project Schedule defining the planned operations detailed for the first 90 calendar days for approval. The approved Preliminary Project Schedule will be used for payment purposes not to exceed 90 calendar days after NTP.
Completely cost load the Preliminary Project Schedule to balance the contract award CLINS shown on the Price Schedule. The Preliminary Project Schedule may be summary in nature for the remaining performance period. It must be early start and late finish constrained and logically tied as specified. The Preliminary Project Schedule forms the basis for the Initial Project Schedule specified herein and must include all of the required plan and program preparations, submissions and approvals identified in the contract (for example, Quality Control Plan, Safety Plan, and Environmental Protection Plan) as well as permitting activities and other non-construction activities intended to occur within the first 90 calendar days. Government acceptance of the associated design package(s) and all other specified Program and Plan approvals must occur prior to any planned construction activities. Activity code any activities that are summary in nature after the first 90 calendar days with Bid Item (CLIN) code (BIDI), Responsibility Code (RESP) and Feature of Work code (FOW).
3.5.2 Initial Project Schedule Submission
Submit the Initial Project Schedule for approval within 42 calendar days after notice to proceed is issued. The schedule must demonstrate a reasonable and realistic sequence of activities which represent all work through the entire contract performance period. Cover in the preliminary schedule the entire construction effort with as much detail as is known at
Section 01 32 01.00 10 Page 12 the time but, as a minimum, include all construction start and completion milestones, and detailed construction activities through the dry-in milestone, including all activity coding and cost loading. Include the remaining construction, including cost loading, but it may be scheduled summary in nature.
3.5.3 Periodic Schedule Updates
Update the Project Schedule on a regular basis, monthly at a minimum.
Provide a draft Periodic Schedule Update for review at the schedule update meetings as prescribed in the paragraph PERIODIC SCHEDULE UPDATE MEETINGS.
These updates will enable the Government to assess Contractor's progress.
a. Update information including Actual Start Dates (AS), Actual Finish
Dates (AF), Remaining Durations (RD), and Percent Complete is subject to the approval of the Government at the meeting.
b. AS and AF dates must match the date(s) reported on the Contractor's
Quality Control Report for an activity start or…