Attachment_6_-_Additional_Clarifications.pdf

PDF 174 KB Posted

Attached to
Replace Approach - Threshold- End Light Fixtures Federal contract opportunity
Solicitation number
FA448619RA014
Issued by
Department of the Air Force United States Air Forces in Europe - Air Forces Africa

About this file

Attachment 6 - Additional Clarifications

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Additional Clarifications:

- Perform all work at overrun areas during nighttime.

- Due to airfield operations, never close both overruns at the same time. Complete all work on one side of the runway before starting work on the other side.

- Due to airfield operations constraints (summer operation) no work shall be occurring from mid-

April to October at the overrun areas. Clear all equipment and markings related to temporary displaced threshold during this timeframe. Both overruns shall be operational (without temporary displaced threshold) during this timeframe.