Sustain/Replace Auto Hobby Roof Bldg 656
NKAK 13‐1038
Questions
8‐7‐15
1. Will Fire Detection be required in the new attic space?
ANSWER: Please review SOW, there is no portion where we create new attic space.
2. Will lighting be required in the new attic space?
ANSWER: Please review SOW, there is no portion where we create new attic space.
3. Compliance with UFGS 075200, Modified Bituminous Membrane Roofing is required in paragraph 2.01.F of Section 011001, State of Work for Design‐Build (SOW). Will this section be issued during the pre‐bid period?
ANSWER: UFGS requirements can be found on the internet.
4. Paragraph 2.03.A.15 of the SOW requires R‐38 insulation at the roof areas to receive the modified bitumen membrane installation. The insulation requires a flexible vapor retarder that is an ice/water guard membrane underlayment. This is a confusing requirement. Could a more specific type product be described?
ANSWERS: Determined during design phase of project.
5. Paragraph 2.03.B.2.f of the SOW requires a 4’ overhang on the metal roof portion. Does this apply to this project?
ANSWER: No, 2’ overhang applies
6. Paragraph 2.03.B.2.j requires the slope of the new metal roof replacement to be no less than a 4/12 slope. Is the actual intent to match the existing slope?
ANSWER: 4/12 slope is not required. Match existing slope.
7. Does the installation of R38 thermal insulation under the new metal roofing apply?
ANSWER: For bidding purpose we will require the R38 insulation.
8. Is an economic analysis as described in paragraph 5.04.B of the SOW required?
ANSWER: no.
9. Will the 4' overhang be required for the metal roofs?
ANSWER: No, 2’ overhang applies.
10. Does the small canopy on the North side of the building over the door requirement repalcement?
ANSWER: yes
11. The brick wall leading up to the high parapet roof does not appear to have weeps, or they have been covered. There are also signs of water intrusion into the wall. Will we need to design to add brick weeps to these walls?
ANSWER: yes