FA4427-17-R-0008 1 June 2017

SCOPE OF WORK

Project Name: Renovate Office Space for Bldg. 836

Revision 01

XDAT # 07-1052

1. GENERAL DESCRIPTION

1.1 The contractor (Ktr) shall provide all design, labor, materials, and supervision to renovate the

1st floor hallways and office space for Bldg. 836. All work shall comply with specifications.

Any work not specifically covered by the specifications shall comply with current governing

UFC, IBC codes and industry standards. Contractor shall verify field conditions, dimensions, and material quantities prior to fact finding with planner and award of the contract.

Contractor shall have approved drawings and submittals for all materials prior to any new work or installation of equipment, including accessory items. Contractor shall review existing as-built drawings and make corrections to apply with proposed new scope designs with final review by government for approval. All work must comply with environmental laws and regulations, including abatement of any hazardous materials.

2. TESTING

2.1 No testing required.

3. DEMOLITION

3.1 Remove wallpaper, paint and wall texture from all hallway walls on the 1st floor.

3.2 Demolish roll up windows at entrance of room 130.

3.3 Demolish lighting over roll up windows in room 130.

3.4 Demolish window on wall that is adjacent to the entrance of room 130.

3.5 Remove door at entrance of room 145.

3.6 Demolish water fountain.

3.7 Remove sink and countertop in the women’s restroom.

3.8 Remove pump sink in men’s restroom.

3.9 Remove exit door of room 1.

3.10Remove exit door of 114A.

3.11 Remove sink and cabinets in Kitchen/Breakroom 135.

3.12 Remove flood lights in atrium above trophy cases.

3.13 Remove Core Value embroidery in atrium above trophy cases.

4. CONSTRUCTION

4.1 Re-paint and re-texture all hallway walls on the 1st floor.

4.1.1 Contractor will ensure to apply paint and smooth texture that is semi-gloss and can be easily cleaned.

4.2 Construct new solid wall at entrance of room 130.

4.2.1 Install 10-12 8’x3’ lockable cabinets on inside of new wall.

4.3 Construct new solid wall that is adjacent to the entrance of room 130.

4.4 Install glass door at entrance of command support section (Room 145).

4.4.1 Glass door will be storefront type 3’x7’ with 1’x7’ glass sidelight panels on each side of the door.

4.5 Replace sink in men’s restroom with 4 deep well sinks and supporting countertop.

4.5.1 Countertops will be solid surface, nonporous Corian type or equivalent.

4.6 Install new 2 new sinks and supporting countertop in women’s restroom.

4.6.1 Countertops will be solid surface, nonporous Corian type or equivalent.

4.7 Restructure shower in women’s restroom to eliminate water runoff.

4.8 Repair/replace stalls in women’s restroom.

4.9 Replace exhaust fans with new in both restrooms.

4.10 Construct wall/partition in locker room establishing separate areas for men and women.

4.10.1 Relocate fire alarm horn strobe in locker room that is located where new wall/partition will be established.

4.10.2 Install new fire alarm horn strobe in each locker room once new wall/partition is established.

4.10.3 Ensure fire alarm horn strobes are compatible with existing Edwards EST fire alarm system in the facility.

4.11 Replace exit door with new in room 114.

4.12 Renovate Existing Kitchen/Breakroom (room 135).

4.12.1 Retexture and repaint all walls.

4.12.2 Replace sink, countertop and cabinets with with new.

4.13 Install automatic filtered water fountain in place of old.

4.14 Replace all ceiling tiles in the hallway with new.

4.14.1 Ceiling tiles will be 2’x2’

4.15 Install 4 outlet receptacles on south wall of room 123, behind the bar area.

NOTES: All room numbers are in reference to the attached floor plan.

5. Additional Requirements:

5.1 All work areas shall be kept as clean as possible during working hours. Debris will not be allowed to accumulate on work site. All debris will be deposited in an authorized container supplied by the contractor.

5.2 Working drawings shall provide sufficient detail to provide a clear and complete understanding of the work.

5.3 Special precautions must be made, as needed, to prevent any potential fire hazard. The fire reporting number is 424-4911 from a base phone or 911 from any commercial phone.

5.4 All work shall be IAW all Contract Specifications, UFC’s, UBC, UMC, UPC and NEC requirements. The contractor shall challenge any requirements in the scope of work (SOW) or items during Fact Finding/Negotiations which are specifically in violation of the governing code. It is the contractor’s responsibility to comply with the governing code unless the construction representative provides specific documentation to the contrary.

5.5 The contractor shall ensure installation of all items included in the contract. The contractor shall be accountable for all related costs of items not installed per negotiations.

5.6 All work shall be in full compliance with the requirements, spirit, and intent of the base compatibility plan (discussed at the Basic Content Pre-construction meeting and a copy provided by the Contracting Officer) and contract specifications.

5.7 All exposed and visible surfaces shall be finished and provide an aesthetically pleasing appearance.

5.8 Any existing items encountered during construction shall be identified and included in the finished as-builts.

5.9 The contractor shall field verify all drawing measurements and any other supplied information given at the site visit before negotiations. Any item that should have been verified prior to negotiation will not be considered a differing site condition.

5.10 Contractor hours will be Monday-Friday 08:00 to 16:00. Work conducted outside these hours will need to be approved by Contracting Squadron and Civil Engineering Squadron.

5.11 Materials storage and clean up: The contractor’s materials and equipment shall be stored and protected after end of each day. Storage facilities area to be provided by contractor at an approved Government location. Clean up and removal of all debris, spoil and waste shall be accomplished at the end of each day’s work. Disposal shall be off base upon completion.

5.12 Working conditions: Contractor shall perform work in such a manner as to cause minimum interference to facility and surrounding areas utilities: Reasonable qualities of water and electricity will be provided to the contractor without charge. Needed temporary connections shall be installed maintained and removed at the contractors expense.