REVISED SECTION B – DATED 8/5/2015
FA4418-15-R-0011
PAGE of 44
Section B - Supplies or Services and Prices
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1 |
| Each |
Repair Electrical Distribution, Area J
FFP
All work as required by drawings and specifications for Project DKFX 07-0003J Repair Electrical Distribution System Area J. The work to be performed consists of providing the labor, equipment, and materials to replace substandard equipment and replace base overhead primary (12.47kV) distribution systems (poles, conductors, equipment), and overhead secondary supply conductors with a new underground utility systems. All work will be coordinated with the phone and CATV utility providers. Work includes all electrical, painting, concrete trenching, directional drilling, and site work.
FOB: Destination
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1 |
| Each |
Estimated Quantities (Repair) - Area J
Disposal of one Transformer with lead based paint and no PCB's.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1 |
| Each |
Estimated Quantities (Repair) - Area J
Disposal of one Transformer with PCB's and no lead based paint.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1 |
| Each |
Estimated Quantities (Repair) - Area J
Disposal of one Transformer with PCB's and lead based paint.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 2 |
| Each |
Estimated Quantities (Repair) - Area J
Work associated with installing new cable a manhole that is not shown on the plans.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1,200 |
| Linear Foot |
Estimated Quantities (Repair) - Arera J
Replacement of existing cable that fails electrical tests when new equipment is installed. (including re-test and terminate)
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 6 |
| Each |
Estimated Quantities (Repair) - Area J
Replacement of existing 15 kV cable termination including retest.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 6 |
| Each |
Estimated Quantities (Repair) - Area J
Installation of additional 10 foot copper clad steel ground rod and 25 foot of 4/0 bare copper connecting wire with exothermic connections.
NET AMT
ESTIMATED QUANTITIES
SCHEDULE B
NOTE: (Applicable to CLINS 0002-0009). If actual quantities should be less than 85% or more than 115% of the estimated quantities, the unit prices of those items falling outside the parameters of 85% / 115% will be subject to negotiation. However, if the actual quantities installed/removed fall within the 85% / 115% range of estimated quantities, the unit prices will be used for payment purposes. In either event, the contractor shall only be paid for the actual quantities installed/removed (as applicable to price schedule). In no case shall the contractor exceed the amount of the contract without consent of the Contracting Officer.