Attachment__1_-_Area_Lighting_SOW_-_18_APR_13.pdf

PDF 43 KB Posted

Attached to
Upgrade Area Lighting (Induction)
Solicitation number
FA4418-13-R-0014
Issued by

About this file

Attachment 1 - Statement of Work - w/Installation Layout Map C-1 for Solicitation FA4418-13-R-0014 Upgrade Area Lighting (Induction).

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4418-13-R-0014 Attachment 1

Statement of Work

DKFX 11-1059 Upgrade Area Lighting (Induction)

Charleston Air Force Base

South Carolina

18 April 2013

Statement of Work:

The project consists of providing all plant, labor, material parts, and equipment necessary to replace existing 400 watt high pressure sodium (HPS) street pole lighting fixtures along Hill Blvd and adjacent streets to include parking lots. Existing fixtures will be replaced with shadow box type induction lighting fixtures located on Joint Base Charleston (Air Base), South Carolina. The performance period for this project shall be 180 days. The project requirements include, but are not limited to the following major items of work:

General Requirements:

• Contractor shall submit lighting fixture and surge protector cut sheets along with the AF Form 3000 (Material Submittal) to the Government Contract Officer for review and approval. The Cut sheets shall be from the manufacture showing details of the fixture and will include items such as the fixture color, size, voltage and mounting brackets.

• Parking Lot Fixtures: Disconnect and remove existing High Pressure Sodium (HPS) fixtures located at parking lot areas identified on the attached map. Provide and install advanced 100W and/or 80W Induction fixtures with photocells which meet or exceed existing lighting specifications as determined by the IES recommended lighting requirements. Specifications for the Induction lighting replacements are listed in the Technical Data below. Contractor shall verify voltage requirements prior to ordering fixtures and surge protection.

• Utilize existing lighting poles and ensure weight specifications are maintained with new Induction fixtures.

• Provide all electrical power connections and grounding as necessary to complete the lighting fixture installation and ensure that it is operational at each location.

• Lighting fixtures shall be equipped with a dusk to dawn photocell sensor. Photocells will be installed on the each lighting fixture. If a pole mounted photocell exists install a shorting cap and install photocell on each light.

• Install a surge protector on each pole (inside the hand-hole). Specifications for the surge protectors are listed in the Technical Data below.

• Disposal and/or recycling of the existing lighting fixtures will be in accordance with Federal, State and Local regulations.

• All fixtures will meet the Charleston AFB color specifications, (Sherwin-Williams Nightscape/SW 2007 Dark Bronze).

FA4418-13-R-0014 Attachment 1

Locations: (See Attached Map for Locations and Wattages) B – 214/215 (Bowling Alley/Library) – 6ea/100W shoe box w/ PE cell (2 double Pole & 2 Single Pole) B – 254 (Security Forces) – 8ea/100W shoe box w/ PE cell (4 Double Pole) B – 256 (Security Forces Warehouse) - 6ea/100W shoe box w/ PE cell (1 double Pole & 4 Single Poles) B – 113 (C-17 Trainer) - 6ea/100W shoe box w/ PE cell (2 double Pole & 2 Single Pole) B – 108 (Flight Sim.) – 9ea/100W shoe box w/PE cell (2 double Pole & 5 Single Pole) B – 164 (Passenger Terminal) – 8ea/100W shoe box w/PE cell (4 Double Pole) B – 51 (Reserve Bldg) – 15ea/100W shoe box w/PE cell (6 double Pole & 3 Single Pole) B – 58 (Avionics Shop) – 33ea/100W shoe box w/PE cell and 2ea/80W shoe box w/twist lock PE cell (15 double Pole & 5 Single Pole) B – 16000/129 (Wing HQ) - 8ea/100W shoe box w/PE cell and 2ea/80W shoe box w/twist lock PE cell (1 double Pole & 8 Single Pole) B – 503 (Contracting) – 11ea/100W shoe box w/PE cell (5 double Pole & 1 Single Pole) B – 581/506 (Life Support) – 9ea/100W shoe box w/PE cell (9 Single Pole) B – 224 (Pool) – 3ea/100W shoe box w/PE cell (3 Single Pole)

• Street Lighting Fixtures: Disconnect and remove existing 400W HPS fixtures located along Hill

Blvd from the East Jackson to Bates Ave. and along Graves Ave. See Attached map for light fixture locations. Provide and install 200W Induction fixtures with photocells which meet or exceed existing lighting specifications as determined by the IES recommended lighting requirements. Specifications for the Induction lighting replacements are listed in the Technical Data below. Contractor shall verify voltage requirements prior to ordering fixtures and surge protectors.

• Utilize existing lighting poles and ensure weight specifications are maintained with new Induction fixtures.

• Provide all electrical power connections and grounding as necessary to complete the lighting fixture installation and ensure that it is operational at each location.

• Lighting fixtures shall be equipped with a dusk to dawn photocell sensor. Lighting fixtures shall be equipped with a dusk to dawn photocell sensor. Photocells will be installed on the each lighting fixture. If a pole mounted photocell exists install a shorting cap and install photocell on each light.

• Install a surge protector on each pole (inside the hand-hole). Specifications for the surge protectors are listed in the Technical Data below.

• Light poles (15) on Hill Blvd will require a round pole adapter for mounting the fixtures.

• Disposal and/or recycling of the existing lighting fixtures will be in accordance with Federal, State and Local regulations.

• Paint all fixtures to Charleston AFB color specifications, (Sherwin-Williams Nightscape/SW 2007

Dark Bronze)

Locations: (See Attached Map for Locations and Wattages) Hill Blvd – 56ea/200W shoe box w/PE cell (24 Single pole & 16 Double pole) Graves Ave. – 6ea/200W shoe box w/PE cell (6 Single Pole) Hill Blvd – (Dorchester Gate) 20ea/200W shoe box w/PE cell (5 Double pole & 10 Single Pole)

FA4418-13-R-0014 Attachment 1

Project Work Site Locations:

• See attached area maps for fixture locations.

Light Plan.pdf

Technical Descriptions

• Technical Specifications: All Induction lighting fixtures shall meet and/or exceed the IES recommended lighting requirements/specifications and will have a minimum warranty of 5 years.

If using suitable substitute, submittals are required for review and approval.

Surge Protector:

Model: SYCOM Surge Inc, SYC-LP series or suitable substitute General Description: Lifetime warranty, Hard- wire parallel installation, thermal fusing and enclosure measures 2-7/8” x 3-3/4” x 2”, UL 94V0 flame retardant and NEMA 4 weatherproof.

Max Load Current: Unlimited Life Cycle: > 3000 10,000A pulses Insulation: > 600V Protected Modes: L-N, L-G, N-G, and L-L Current Drain: < 100uA Operating Frequency: 0-400Hz Response Time: < 5 Nanoseconds Voltage: Varies depending on pole location

Parking Lot Lighting Fixtures:

Model: Industrial Lighting Products (ILP) F16A-100-120/277-FLEM6-PC (100W) or F16A-80-120/277- FLEM6-PC (80W) or suitable substitute General Description: Ideal for parking lot and general area applications. Housing is made of heavy gauge die cast aluminum with textured bronze powercoat finish. Standard Mounting is 6” side arm (pole). Instant on, flicker free, cold start and hot restart. 16” Large Window Flood Induction fixture.

Safety: UL listed for wet locations, ETL/UL Standard 1598.

Finish: Finish color shall be Sherwin-Williams Nightscape/SW 2007 Dark Bronze or suitable substitute.

System Watts: Varies depending on pole location

Street Lighting Fixtures:

Model: Industrial Lighting Products (ILP) F23-200-120/277-FLEM6-PC (200W) or suitable substitute General Description: Ideal for parking lot and street applications. Housing is made of heavy gauge die cast aluminum with textured bronze powercoat finish. Standard Mounting is 6” side arm (pole). Instant on, flicker free, cold start and hot restart, 23” Large Window Flood Induction fixture.

Safety: UL listed for wet locations, ETL/UL Standard 1598.

Finish: Finish color shall be Sherwin-Williams Nightscape/SW 2007 Dark Bronze or suitable substitute.

System Watts: Varies depending on pole location

FA4418-13-R-0014 Attachment 1

Products:

• All project components shall be installed in accordance with the manufacturer’s technical instructions.

• All electrical installations shall comply with National Electrical Code (current edition) and contract specifications.

Applicable Instructions:

• Work areas around and within project site will be occupied by the using activity during the course of work. Caution must be taken to insure all safety work practices are adhered to while construction work requirements are performed.

• Caution must be taken in all work areas to avoid physical or cosmetic damage to existing government and private property. Any damage to government or private property resulting from construction procedures shall be the responsibility of the contractor.

• Power shut-off request must be coordinated in order to minimize the impact to onsite facility activities and advanced request shall be scheduled with the base civil engineering representative.

• All permits, as required, shall be obtained prior to lighting fixture implementation.

Special Instructions:

• Project site shall be kept clean and orderly daily.

• Work methods and practices shall be accomplished in a safe manner abiding by work safety and base safety standards. Work site is subject to OSHA inspections.

• Work site areas shall be returned to existing conditions at completion of work requirements.

Environmental: The Contractor shall comply with all applicable requirements stated in the Toxic Substances Control Act of 1976. All materials used in the performance of this contract shall be applied in strict accordance with manufacturer’s printed label instructions and all applicable standards. The use of Class I ozone-depleting substances, asbestos containing materials, and lead paints are strictly prohibited.

Waste Disposal/Recycling: The contractor shall recycle all recyclable materials as a result of demolition. All waste materials generated by all work under this contract shall be handled, transported, stored and disposed of off base at no additional cost to the government, by the contractor and or sub-contractors, in accordance with all applicable federal, state or local laws, ordinances, regulations.

END OF STATEMENT OF WORK