Attachment_03_-_SEED_Project__Renovate_90352_Common_Area_SOW.doc

DOC document 76 KB Posted

Attached to
Simplified Acquisition of Base Engineering Requirements (SABER), IDIQ Federal contract opportunity
Solicitation number
FA4417-14-R-0001
Issued by
Department of the Air Force Special Operations Command

About this file

FA4417-14-R-0001 Attachment 3 - SOW Seed Project FTEV 13-1125

View the file

Other files for this federal contract opportunity

Other files attached to Simplified Acquisition of Base Engineering Requirements (SABER), IDIQ, newest first.
File Type Posted
Attachment_01_-_SOW_Revision_dated_21_May_2014_Final.docx DOCX document
FA4417-14-R-0001 _Amendment_0002.doc DOC document
Questions_1-30 __22_May_14.doc DOC document
Questions_2_-_12_May_2014.doc DOC document
FA4417-14-R-0001-0001.doc DOC document
Attachment_01_-_SOW_Revision_dated_15_May_2014_(FINAL).docx DOCX document
SABER_Site_Visit_MFR_and_Sign-In_Sheet _14-R-0001.pdf PDF
Attachment_11_-_Wage_Rate_FL140119.docx DOCX document
Attachment_06_-_Past_Performance_Questionaire.docx DOCX document
Attachment_07_-_Financial_Reference_Sheet_-_SABER_-_14-R-0001.docx DOCX document
Attachment_02_-_HF_Base_Master_Specs_Combined_2014.pdf PDF
Attachment_09_-_Wage_Rate_FL140170.docx DOCX document
FA4417-14-R-0011 _SABER_Solicitation.doc DOC document
Attachment_10_-_Wage_Rate_FL140222.docx DOCX document
Attachment_05_-_SEED_Project_Drawings.pdf PDF
Attachment_08_-_Wage_Rate_FL140029.docx DOCX document
Attachment_04_-_As-Builts_First_Floor_Building_Plan.pdf PDF
Attachment_01_-_SOW_Revision_dated_29_Apr_2014_(FINAL).docx DOCX document
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

FA4417-14-R-0001, Attachment 3

FTEV: 13-1125

Title: Renovate Common Area, Bldg. 90352 Date: Jan 2014

1.

GENERAL

1.0 The following Statement of Work is for a SABER task order to be accomplished by the contractor in accordance with the requirements of the Hurlburt Field Base Master Specifications (HBMS), dated 1 Jun 12, and the SABER Contract.

1.1 The contractor shall provide all plant, labor, materials, equipment, design, and supervision necessary to Renovate Common Area, Bldg. 90352. All work shall be done in accordance with the requirements contained in the Hurlburt Field Base Master Specifications, dated 1 June 12, SABER Contract and the Statement of Work. Contractor shall provide a projected schedule of all submittals and a project construction schedule upon award of the contract.

1.2 Contractor and all subcontractors must fully comply with specification section 01 00 00, General Requirements. All forms referenced, notarized statements, construction data worksheets, contractor progress reports, contractor compliance statements, etc. must be provided to the contracting officer at the appropriate time as indicated within the specification.

1.3 Contractor should refer to Hurlburt Field Base Master Specifications, dated 1 June 12, for guidance on the documentation needed to fulfill the requirements of the SABER task order.

1.4 A Cost Estimate shall be accomplished using the 2014 Means Book. Non pre-priced items should be identified as such on the estimate.

1.5 Contractor shall obtain all necessary permits and work clearances, including underground utilities PRIOR to start of work.

1.6 Contractor shall coordinate work closely with Contracting Officer or, representative, as well as the CE project manager on all issues pertaining to work phasing, scheduling, planning, and execution.

1.7 The contractor will provide the names of all workers to the building manager and security officials of the building.

1.8 Contractor must provide a letter on company letterhead with the following:

1. Full name of each worker assigned to the project

2. Workers Social Security number

3. Workers date of birth

4. Workers driver’s license number, license must be valid.

5. Workers current home address.

6. Workers assigned to this project must be United States citizens

1.9 All workers from the contractor and sub contractors will be informed on the specific security issues and operating practices of the building and will comply.

1.10 Any work done after duty hours, weekends or holidays will be coordinated with requestor and building manager.

1.11 All close out documents (see section 01 70 00) must be submitted to contracting officer prior to final inspection. Government will withhold 3% of contract sum until project is complete and has been accepted by the Government.

2.

LOCATION

2.0 The project site is located at Building 90352, Hurlburt Field, Florida.

3.

MATERIALS

3.0 Contractor shall refer to the HBMS for guidance in selecting appropriate materials to accomplish the work.

3.1 Contractor to provide submittals for all materials.

3.2 If the Contractor suggests the use of a specific material not listed in the specifications, which the Government might consider to lessen the cost or increase the utility or appearance of the facility, the material should be listed under Alternatives as described in the SABER contract.

4. PROJECT ELEMENTS

4.0 The project will contain, but is not limited to, the following elements:

4.1 TV Room

4.1.1 Remove existing ceiling tile and grid.

4.1.2 Remove 4 existing 2’x2 light fixtures. Existing wire and flexible conduit can be reused in new ceiling layout.

4.1.3 Support existing security camera, HVAC grilles/registers and fire suppression heads, to be reinstalled in new ceiling layout.

4.1.4 Remove existing ceramic floor tile. Prep slab for new tile flooring.

4.1.5 Remove existing wood cove base and door stop.

4.1.6 Remove existing double compartment sink.

4.1.7 Remove existing base cabinets and countertops.

4.1.8 Cap existing sink drain line flush with finished floor elevation.

4.1.9 Remove hot and cold water piping to sink and ice machine (vending room). Cap at existing water fountain location.

4.1.10 Remove existing range hood and suppression system.

4.1.11 Remove existing flexible exhaust duct for range hood. Exterior wall penetration and damper can be reused at new location.

4.1.12 Remove existing gypsum board and metal framed wall/soffit separating tv room and vending room.

4.1.13 Remove existing power and lighting conduit, boxes, wire and face plates in this wall back to nearest panel. See drawings provided.

4.1.14 Remove existing door, frame and hardware.

4.1.15 Install 4 each recessed communications outlet boxes at locations shown on provided drawings. Run ¾” flex conduit from the outlet box extending above wall height at each location. Top with bushing. Install blank cover plates on boxes. No wire/cable to be installed.

4.1.16 Install thermostat and control wire back to mechanical room.

4.1.17 Paint entire room. Remove 9 outlet covers and 1 fire horn. Replace after painting.

4.1.18 Install new 2’ x 2’ ceiling grid with tegular ceiling tiles.

4.1.19 Reinstall existing security camera and HVAC grilles/registers.

4.1.20 Adjust 4 existing fire suppression sprinkler heads to match new ceiling height.

4.1.21 Install 4 each 2’ x 2’ fluorescent lights in this area. (See new reflected ceiling plan for layout of TV/Kitchen areas.)

4.1.22 Install new slip resistant 12” x 12” ceramic tile floor. Grout color to match tile

4.1.23 Install 6’ ceramic tile cove base matching floor tile. Grout to match floor tile grout color.

4.1.24 Patch/repair where wall was removed.

4.2 Vending Room

4.2.1 Remove existing ceiling tile and grid.

4.2.2 Remove existing 2’ x 4’ lighting fixture.

4.2.3 Support existing security camera, HVAC grilles/registers and fire suppression head, to be reinstalled in new ceiling layout.

4.2.4 Remove existing ceramic tile flooring. Prep slab for new tile flooring.

4.2.5 Remove existing tile cove base.

4.2.6 Remove header, stem wall and 15” of wall at water fountain. Remove single light switch at this location.

4.2.7 Construct new stem wall at this location.

4.2.8 Install 2 gang switch in the stem wall. One switch to control new lighting in kitchen area and the other switch to control new lighting in TV room.

4.2.9 Relocate ice machine to mechanical room wall. Hang filter system on mechanical room wall. Connect drain into drain for water fountain.

4.2.10 Install ½” cold water line to ice machine. Connection point is above ceiling by water fountain.

4.2.11 Seal wall for ice machine at current location.

4.2.12 Install new kitchen range hood system and associated suppression system. Exhaust through existing wall damper located on exterior wall. No flexible duct allowed on re-installation. Connect to existing fire alarm system.

4.2.13 Remove drywall from exterior wall and wall adjoining mechanical room to expose framing.

4.2.14 Saw cut and remove 8” wide x 5’ – 10” section of concrete slab from this wall to the drain line for the floor drain in the center of the vending room floor.

4.2.15 Install drain line for new sink location. Connect to drain line for floor drain.

4.2.16 Install ½” hot and cold water plumbing lines to new sink location. Install isolation ball valves on each of these lines. Connection point is above ceiling by water fountain.

4.2.17 Install new vent line and roof vent stack for sink.

4.2.18 Insulate plumbing lines as required.

4.2.19 Raise 3 existing power receptacles from standard installation height to standard height above new countertop. Convert to GFCI circuit. Connect 2 each outlets remaining at standard height to GFCI circuit.

4.2.20 Change 1 each 110V outlet to 220V outlet at new range location. Run new conduit and wire from the electrical panel to this location.

4.2.21 Install 5/8” Type X gypsum board on exterior wall and wall adjoining mechanical room. Install vertically.

4.2.22 Mud, tape and prep new drywall for type 4 light textured finish. Match texture of existing walls.

4.2.23 Install custom built base cabinets and bull-nosed laminate countertops at locations shown on provided drawings. Provide space for range and cutout for drop in double compartment sink. Provide access hatch in end cabinet to allow for change-out of filters on ice machine. Install wall cabinets on sink wall only. Install drawer and door hardware.

4.2.24 Install new stainless steel double compartment sink, garbage disposal and faucet. Connect to new hot and cold water lines. Connect drain and vent lines.

4.2.25 Patch/repair walls at demolition locations.

4.2.26 Paint entire room.

4.2.27 Install new 2’ x 2’ ceiling grid with tegular ceiling tiles.

4.2.28 Reinstall existing security camera and HVAC grilles/registers

4.2.29 Adjust fire suppression sprinkler head to match new ceiling height.

4.2.30 Install 4 each 2’ x 2’ fluorescent lights in this area. (See new reflected ceiling plan for layout of TV/Kitchen areas.)

4.2.31 Install slip resistant 12” x 12” ceramic tile floor. Grout color to match floor tile.

4.2.32 Install 6’ ceramic tile cove base matching floor tile. Grout to match floor tile grout color.

4.3 Game Room

4.3.1 Remove existing gypsum board and metal stud wall for phone booth area and recessed wall cabinets.

4.3.2 Remove existing recessed can light in wall cabinet assembly.

4.3.3 Remove existing ceiling tile and grid entire room.

4.3.4 Remove 9 existing 2’ x 2’ fluorescent lighting fixtures.

4.3.5 Support security camera, HVAC grilles/registers and fire suppression heads to be reinstalled in new ceiling layout.

4.3.6 Remove existing ceramic tile flooring entire room. Prep slab for new tile flooring

4.3.7 Remove existing wood/tile cove base.

4.3.8 Relocate switch in phone booth area to entry door in foyer.

4.3.9 Remove existing lighting fixture in phone booth area.

4.3.10 Patch damage in remaining walls.

4.3.11 Frame, install 5/8” Type X drywall, mud, tape and sand existing doorway to phone area.

4.3.12 Texture new wall surfaces to match existing where required.

4.3.13 Paint entire room. Remove 1 switch plate and 10 receptacle cover plates. Replace after painting.

4.3.14 Install new 2’ x 2’ ceiling grid with tegular ceiling tiles.

4.3.15 Install 9 new 2’ x 2’ fluorescent lighting fixtures.

4.3.16 Install slip resistant 12” x 12” ceramic tile floor. Grout color to match floor tile

4.3.17 Install 6’ ceramic tile cove base matching floor tile. Grout to match floor tile grout color.

4.4 Vestibule

4.4.1 Remove existing ceiling tile and grid.

4.4.2 Support existing security camera, HVAC grilles/registers, exit sign and fire suppression heads, to be reinstalled in new ceiling layout.

4.4.3 Remove 3 existing 2’ x 2’ fluorescent lighting fixtures.

4.4.4 Remove existing ceramic tile flooring. Prep slab for new tile flooring.

4.4.5 Remove existing tile cove base.

4.4.6 Remove drywall on wall supporting water fountain to expose piping and power supply.

4.4.7 Disconnect water fountain and utilities. Save fountain for re-installation.

4.4.8 Reroute and connect drain line, power supply and cold water line to new location.

4.4.9 Install new backing material to support water fountain in new location.

4.4.10 Remove existing semi-recessed fire extinguisher cabinet, replace with new semi-recessed cabinet.

4.4.11 Install 5/8” Type X drywall, mud, tape and sand wall at water fountain location. Texture to match existing.

4.4.12 Remove existing display board, replace after painting.

4.4.13 Paint entire vestibule. Remove 2 power receptacles and 1 pull station. Replace after painting.

4.4.14 Install new 2’ x 2’ ceiling grid with angular tegular ceiling tiles

4.4.15 Adjust 2 fire suppression sprinkler heads to match new ceiling height.

4.4.16 Reinstall existing security camera, HVAC grilles/registers, exit light and fire suppression heads in new ceiling location.

4.4.17 Install 3 new 2’ x 2’ fluorescent lighting fixtures.

4.4.18 Re-install water fountain.

4.5 Dorm Manager’s Office

4.5.1 Remove existing carpet.

4.5.2 Remove existing vinyl cove base.

4.5.3 Remove existing ceiling tile and grid.

4.5.4 Support existing security camera, HVAC grilles/registers, and fire suppression head, to be reinstalled in new ceiling layout.

4.5.5 Paint entire office. Remove 6 power/data receptacles. Replace after painting.

4.5.6 Install new 2’ x 2’ ceiling grid with angular tegular ceiling tiles.

4.5.7 Adjust fire suppression sprinkler head to match new ceiling height.

4.5.8 Reinstall existing security camera, HVAC grilles/registers, and fire suppression head to match new ceiling height.

4.5.9 Install 4 new 2’ x 2’ fluorescent lighting fixtures.

4.5.10 Install new 24” x 24” carpet tiles.

4.5.11 Install new 6” vinyl cove base.

4.6 Mechanical Room

4.6.1 Remove insulation, piping, valves, sensors and gauges from isolation valves to AHU.

4.6.2 Remove existing AHU.

4.6.3 Remove duct work from AHU to duct expansion joint on both sides of AHU.

4.6.4 Remove existing pneumatic controls and disconnect unit from fire alarm monitor module.

4.6.5 Install new piping, valves, sensors, gauges and insulation.

4.6.6 Install new AHU. See provided drawings for sizing details.

4.6.7 Install and connect new controls.

4.6.8 Reconnect unit to fire alarm monitoring module

END OF TASK ORDER