Questions and Answers 18-86 (Answered) CAC Locks.pdf
PDF 507 KB Posted
- Attached to
- CAC Door Lock Access Control System & Install Bldg 127 JBSA Lackland Federal contract opportunity
- Solicitation number
- FA301621Q0034
About this file
This document contains questions and answers regarding a solicitation for a CAC door lock access control system and installation at Building 127 at Joint Base San Antonio Lackland. The solicitation seeks proposals to install CAC-enabled door locks and an access control system across three floors of the building, involving approximately 234 interior doors and 5 exterior doors. The project includes providing card readers, request to exit devices, new door hardware, and connecting all components to a wireless network to integrate with a server located in an on-base command center. The document provides additional details on the types of doors, construction of the building, and configuration of the existing system, to help inform vendor responses prior to the February 18th cutoff date for questions.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation -Amendment 3 FA301621Q0034 Final.pdf | ||
| Attachment 1 Addendum 3-SOW CAC Locks.pdf | ||
| Solicitation -Amendment 2 FA301621Q0034 Final.pdf | ||
| Attachment 1 Addendum 2-SOW CAC Locks.pdf | ||
| Questions and Answers 87-97 (Answered) CAC Locks.pdf | ||
| Questions and Answers 3-17 (Answered) CAC Locks.pdf | ||
| CAC replacement images.pdf | ||
| B127 Door Lock layout.pdf | ||
| Attachment 1 Addendum 1-SOW CAC Locks.pdf | ||
| Questions and Answers 18-86 (Unanswered) CAC Locks.pdf | ||
| Questions and Answers 3-17 (Unanswered) CAC Locks.pdf | ||
| Solicitation -Amendment 1 FA301621Q0034 Final.pdf | ||
| Questions and Answers-CAC Locks Question 1-2.pdf | ||
| Questions and Answers-CAC Locks Question 1 .pdf | ||
| Solicitation - FA301621Q0034 Final.pdf | ||
| Attachment 1-SOW CAC Locks.pdf | ||
| Questions and Answers-CAC Locks.docx | DOCX document |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
502 CONS/JBKAE FA301621Q0034
JBSA Lackland, TX CAC Enabled Door Locks
QUESTIONS & ANSWERS: Cut-off date for contractor questions is 2:00 PM CST, 18 February
2021.
Question 18: Item 1 of the SOW, please let us know if the new PACS Server will be connected to the Air
Force Network?
Government Response: No, it will not.
Question 19: Ref Section 2 of the SOW: Please let us more about the types of doors where the new card readers will be installed, we are specifically requesting information about the 5 exterior doors. We need to know if the door frames are concrete filled or are metal and/or wooden frames. You can send us pictured of the typical exterior doors, that will help us a lot to bid on this project.
Government Response: See attached PowerPoint (CAC replacement images). Exterior doors are metal hollow core.
Question 20: Ref Section 2 of SOW regarding “Lock replacement must not compromise the integrity of the door fire rating and all holes as result of removal of existing locks shall be covered by the new Access
Control System.” Do you mean that all those 234 interior doors will require card readers to be connected to the main PACS system via Wi-Fi provided by the Air Force?
Government Response: Please see addendum 1 to the statement of work.
Question 21: In ref: 3. “Specifications and Applicable Characteristics of the Access Control System.
Mortise lock and Panic Hardware shall meet or exceed the American National Standards ANSI A156.13, Series 1000, Grade 1 Operational and Grade 2 Security”.
Does the Air Force is looking to add Panic Hardware? if the answer is yes please specify how many panic door hardware is needed for the entire project? and specify if the panic hardware will be installed in a single door only?.
Government Response: All existing panic hardware is in place already.
Question 22: In ref to section 3.3 of the SOW: “All new Wi-Q readers shall have a minimum 130,000 cycle / 2-to-5-year battery life”, will the Air Force accept alternative with equal or better functionality than these specified locks?
Government Response: Yes.
Question 23: In ref to section 3.5 Software: Will the software needs to pass RMF and DISA Standards?
Government Response: Please see addendum 1 to the statement of work.
Question 24: Attachment 1 Building 127 floor plan: Please confirm that only the 5 exterior door and 2 exterior doors will be directly hardwired to the control panels of the PACS system?
Government Response: Only front entrance (double door) will have card reader. Interior vestibule doors will not have readers. All other exterior entrances will not have readers.
Question 25: Please confirm that the other doors (66 Student rooms, 2 briefing rooms, Laundry and Day
Rooms, SCA C113 room, Computer Room and 9 offices) will use wireless lockset readers, are we correct in this assumption?
Government Response: See attached PowerPoint (Door Lock Layout)
1st floor requires 70 CAC/PIV readers (66 student rooms; 2 exterior entrance; 2 admin spaces) and 15
PIN readers (Offices; classroom, dayroom & laundry). All should be connected to Wi-Fi to record door access.
Question 26: We also need to know if the second floor and 3rd floor card readers will use wireless locksets only, please specify if assumption is correct or incorrect.
Government Response: See attached PowerPoint (Door Lock Layout)
2nd floor requires 66 CAC/PIV readers (student rooms) and 6 PIN (Office; storage, dayroom & laundry) readers. All should be connected to Wi-Fi to record door access.
3rd floor requires 68 CAC/PIV readers (student rooms) and 4 PIN(storage rooms, dayroom & laundry) readers. All should be connected to Wi-Fi to record door access.
Question 27: We also need to know if the new readers will require the use of door strikes or not, since that will be a major difference in cost.
Government Response: None were used in previous installation. Should not need now.
Question 28: And once again the question for the Wi-Fi is if the contractor will be required to provide the infrastructure or the Air Force will provide the wireless infrastructure, please specify?
Government Response: Should be able to use most/all of existing infrastructure.
Question 29: If you expect the contractor to install hardwired readers to all rooms other than the 66 each
(per floor) Student rooms, we will need to know more specifics about the types of existing door frames, and if the cables can be installed with out conduit?
Government Response: See attached PowerPoint (Door Lock Layout). Images show typical door construction within the bldg. All readers should connect to Wi-Fi system – not hard wired.
Question 30: If conduit is needed, please give us more information about the ceiling, if there are ceiling tiles that can be removed for cable installation; or if the ceiling is closed in all areas, or you can even send us few pictures.
Government Response: Ceilings and floors are generally concrete between floors. Ceilings in ‘connecting center areas’ are drop ceilings - cables and piping run thru that area. Existing Wi-Fi repeaters are installed on the sheetrock walls and use cable channels on the wall (See PowerPoint)
Question 31: How old is the facility?
Government Response: Approximately 15 years old.
Question 32: How much square footage is the facility?
Government Response: Approximately 122,000 Sqft.
Question 33: How stable is the power?
Government Response: Stable.
Question 34: How many employees does the facility support?
Government Response: 350-550 students; 10 staff.
Question 35: Is the ceiling a dropped ceiling?
Government Response: Only in central connecting area, day rooms, laundry rooms, storage and offices.
Question 36: How high is the ceiling?
Government Response: In general - 8 foot in common areas; 10 foot in student rooms, and 14-16 foot in hallways.
Question 37: What type of walls are in the perimeter areas?
Government Response: Masonry.
Question 38: What type of walls is inside the offices?
Government Response: Sheetrock.
Question 39: Are the door frames metal and concrete filled?
Government Response: Exterior door are metal and hollow core. Student rooms and offices are wood solid core. Dayrooms, laundry and storage are metal clad solid core.
Question 40: Are we to assume based on the SOW that there is a need for access control server, if yes can you tell us if there is a preference with a brand for the server?
Question 41: How many of those readers are to be installed in double exit doors?
Government Response: : Front entrance only – 2 readers.
Question 42: How many of those readers are to be installed in double doors?
Government Response: Front entrance only – 2 readers.
Question 43: What type of locksets is there in your doors?
Government Response: See attached Power Point.
Question 44: Of the 5 exterior doors and 234 interior doors, how many have a RIM exit device (Crash
Bar) and how many only require the mortise type lock?
Government Response: All exterior doors have RIM device. All other doors do not have a RIM device.
Question 45: Is this requirement for 12 servers or 12 client workstations or at a minimum 12 WI-Q portal gateways?
Question 46: How many building managers are there?
Government Response: One facility manager has their office in building 127 while 11 additional facility managers are housed in other locations.
Question 47: What is the existing access control system and make/model of the existing locks installed?
Government Response: Schlage, Model # - COM400.
Question 48: Can the government provide that latest copy of the approved/evaluated products list for approved software?
Question 49: What type of token cards are required?
Government Response: Approximately a 1 ½ x 3 ½ card that can be programed to be issued as temporary access for residents.
Question 50: What are the locations of the 12 server/software system head ends?
Question 51: If the existing panels themselves are still manufactured and available, can we just upgrade and replace the door handset-CAC reader and upgrade the server+software?
Question 52: Scope says the server is to be located in a command ops center and we are to establish a stand-alone network (dark = no internet) between the building and the server. Is there existing fiber between these points for us to use? If so what type (single mode or multi mode)? How many strands?
1 or 2?
Question 53: If there are no existing fibers, how can we do this without distance and drawing details between the 2 points? What is the approximate distance?
Government Response: Cannot answer this question at this time.
Question 54: Are there any photos available of the existing control panels on the various floors of the building?
Government Response: See attached Power Point.
Question 55: As I understand it the existing access doors are connected to the Vanderbilt access controllers, can you provide an existing inventory of controllers that are at the site?
Government Response: At this time, I cannot provide that information.
Question 56: From feedback from the manufacturer the existing locks are AD series locks that are talking to existing PIM modules, do you have a current inventory list of PIM modules at the site?
Question 57: Does the site have a preferred method with respect to locking hardware on the door, is there a specific model number that the site would like to use on each opening.
Question 58: Is there space to mount new network switches to create the independent security network?
Question 59: Does the site have a network switch part number they would prefer to use? i.e. Cisco /
Juniper? Model of network switch?
Government Response: No.
Question 60: Does the site have a preference to network media (fiber or ethernet) between the switches?
Question 61: Is the ceilings made up of hard drywall ceilings or drop tile ceilings? Accessibility for cabling to each door opening?
Government Response: Ceilings and floors are generally concrete between floors. Ceilings in ‘connecting center areas’ are drop ceilings - cables and piping run thru that area. Existing Wi-Fi repeaters are installed on the sheetrock walls and use cable channels on the wall (See PowerPoint)
Question 62: Is there a preferred model number of card reader that the site would like to use?
Question 63: What is the format of the existing credential to be used for card access?
Question 64: Does the RFQ require additional credentials, if so how many?
Question 65: How many of the 239 doors are on the existing system?
Government Response: 201.
Question 66: Is there a riser room with conduits between the floors?
Government Response: Yes, communication room on each floor.
Question 67: What is the primary interior construction? Poured walls? Cinder Block? Drywall?
Government Response: Drywall.
Question 68: Are the door frames filled with concrete?
Government Response: No.
Question 69: Can we mount panels in the computer rooms on the 1st and 2nd floors? If not, where can they be mounted? Yes.
Government Response:
Question 70: Where can we mount panels on the 3rd floor?
Question 72: Where are the existing access control panels located?
Government Response: Communication rooms on all three floors.
Question 73: The SOW mentions wireless; is it required to e a wireless system or would a fully wired system be accepted?
Question 74: How many enrollment clients are required?
Question 75: What is the manufacturer and model of the current lockset on the rooms?
Government Response: Schlage, Model # - COM400.
Question 76: Do the exterior doors have store room handles or crash bars to exit from the interior?
Government Response: All exterior doors have RIM device. All other doors do not have a RIM device.
Question 77: Should the lock cores be Primus High Security?
Question 78: (3.1.5) Is there adequate rack space for installing the new head end servers at all 12 locations? If not, does the government require the vendor to quote mounting system with the servers?
Question 79: (Section 3.1.6) Would the government allow for the vendor to utilize the existing conduit system to run cabling?
Question 80: Due to the "independent" network (signal and infrastructure) specified, the government requires the vendor to run all cabling independently from the "infrastructure" conduit already in place?
Question 81: (Section 3.2.1) Understanding a server is required for minimum of 12 locations, does the government require each server location to have a monitor, keyboard, mouse, etc. to allow for the administrator to perform admin tasks associated with that server for the controlled location?
Question 82: Is there a central location that the admin functions will be performed that can control each server point. Does the government require 12 sets of servers, monitors, keyboards, mouse or just the server at each location with a central station being offered with a monitor, keyboard, and mouse. This is to ensure we are submitting the proper QTY of hardware for the written requirement.
Question 83: (Sections 9 &10) Will the government provide conduit paths between floors for network and equipment cabling if necessary?
Government Response: Ceilings and floors are generally concrete between floors. Ceilings in ‘connecting center areas’ are drop ceilings - cables and piping run thru that area. Existing Wi-Fi repeaters are installed on the sheetrock walls and use cable channels on the wall (See PowerPoint).
Question 84: How long ago was it installed? (Existing Locks)
Government Response: Best guess is more than 5 years ago.
Question 85: Are all locks currently functioning?
Government Response: Electronic lock system – no. Keys/cores – yes.
Question 86: Does this connect to an outside network or is it local to this building only?
Government Response: Local to this building only.