Date: August 31, 2021

ADDENDUM #1

PROJECT NAME: REPLACE COVERED ENTRY TRIANGLE CHAPEL

LOCATION: Building #7402

PROJECT NUMBER: MAHG201151; WO #83400

Addendum #1 consists of the following:

· Addendum #1:

· Revised Statement of Work rev1 (8-31-21)

· Issue new set of drawings

ADDENDUM ITEMS:

1. ISSUE revised Statement of Work rev 1 (8-31-21). OMIT all previous SOW’s.

a.Reference 3.2.4 SCOPE, REMOVE EXISTING, ADD items:
i.“G. Existing ceiling tile in tower vestibule (Approx. 70 SF).”
ii.“H. Existing metal screens at tower both outside and inside (Approx. 60SF).”
c.Reference 3.2.4 Scope of Work, INSTALL NEW, ADD items:
i.(Under A.) “Moisture barrier equal to Tyvek ‘Stucco Wrap’.
ii.“L. Provide and install new ceiling grid and tile in tower vestibule tomatch existing (Approximately 70 SF).
iii.“M. Provide and install new metal stud/EIFS infill at tower(Approximately 60 SF).”
2.ISSUE revised drawings labeled “ADDEDNUM #1:

a. Replace ceiling grid and tile in the tower vestibule.

b. Remove East and West facing metal screens/louvers, and REPLACE with EIFS/metal stud infill.

END OF ADDENDUM #1