Attachment 10 - Questions_Answers_2 Aug 2021.pdf
PDF 83 KB Posted
- Attached to
- Maintain Exterior Coatings of Multiple Facilities Federal contract opportunity
- Solicitation number
- FA301021R0018
About this file
This document contains a solicitation for a federal contract to maintain exterior coatings of multiple facilities at Keesler Air Force Base. The proposed construction value is between $250,000 and $500,000, and the acquisition is being issued as a 100% HUBZone set-aside. The work includes repairs to exterior insulated finish systems and coatings on buildings 4106, 6950, and 7320. Gutters, downspouts and a large hole around a pipe are also included in the scope of work. An organized site visit was held on July 22, 2021 for offerors to gain access to the base. The period of performance will be between 60 to 120 days depending on the number of contract line items funded at time of award. Offerors are directed to review sections L and M of the solicitation for proposal preparation and evaluation factors. The contracting agency is the Department of the Air Force Air Education and Training Command.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 002 - SF 30.pdf | ||
| Amendment 001 - SF 30.pdf | ||
| Attachment 3 - Exteriors Phase 3 DWG_2 Aug 2021.pdf | ||
| Attachment 1 - Exteriors Phase 3 SOW_2 Aug 2021.pdf | ||
| Site Visit Sign-In_22 July.pdf | ||
| Attachment 5 - Wage Det MS20210050_2 Apr 2021.pdf | ||
| Attachment 1 - Exteriors Phase 3 SOW_6 July 2021.pdf | ||
| Attachment 9 - Notice of Compliance.pdf | ||
| Attachment 4 - Exteriors Phase 3 MSS_6 July 2021.xls | XLS spreadsheet | |
| Solicitation - FA301021R0018.pdf | ||
| Attachment 7 - Past Performance Questionnaire.pdf | ||
| Attachment 3 - Exteriors Phase 3 DWG_13 May 2021.pdf | ||
| Attachment 6 - Past Performance Reference List.pdf | ||
| Attachment 2 - Exteriors Phase 3 SPECS_6 July 2021.pdf | ||
| Attachment 8 - SF 1444.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Maintain Exterior Coatings of Various Facilities, Phase 3
FA301021R0018
Questions and Answers
Q1: Are the Gutters and Downspouts to be included on buildings 6950 and 7320?
A1: Yes; SOW and Drawings have been updated to include gutters and downspouts for buildings 6950 and 7320.
Q2: Are the large louver panels set back above the main entrance on buildings 6950 and 7320 to be included?
A2: No; small vents and louvers around the buildings are included but the large, referenced louver panels are not included.
Q3: Are metal vents located on the roofs of buildings 6950 and 7320 to be included?
A3: No; rooftop mounted equipment, vents, or other items on these two building are not included with the exception of the gutters and downspouts.
Q4: Is the large hole around a pipe on the South-east corner of building 4106 to be included in the EIFS repairs?
A4: Yes; the referenced hole should be included in the EIFS repairs.