Date: August 4, 2020
ADDENDUM #1
PROJECT NAME: REPAIR EXTERIOR LARCHER CHAPEL
PROJECT NUMBER: MAHG11-116152; WO: 70742
LOCATION: Building 3709 – Keesler AFB, Mississippi
ADDENDUM ITEMS:
1. Revised Statement of Work:
a. Reference 3.2.5 Scope of Work, heading REMOVE EXISTING, subheading Exterior Walls & Panels, Windows and Doors, item # 2: Omitted removal of storefront on west elevation.
b. Reference 3.2.5 Scope of Work, heading REMOVE EXISTING, subheading Exterior Walls & Panels, Windows and Doors, item # 3: Omitted removal of hollow metal doors and frames from north elevation.
c. Reference 3.2.5 Scope of Work, heading REMOVE EXISTING, subheading Exterior Walls & Panels, Windows and Doors, item # 4: Omitted the notes to remove light fixtures above mechanical room doors (quadrant E-7, west elevation behind chapel), and on the ceilings at both East entrances.
d. Reference 3.2.5 Scope of Work, heading PROVIDE AND INSTALL NEW, subheading Exterior Storefront System, item # 1: Omitted removal of storefront on west elevation.
e. Reference 3.2.5 Scope of Work, heading PROVIDE AND INSTALL NEW, subheading Exterior Walls, Item #3: Add to the following sentence: “Also, prior to pressure washing, seal the opening in the exterior wall around the electrical conduit on the west elevation near the exterior mechanical units.”
2. Revised drawings:
a. Sheet D1.0, Sheet 2 of 7:
1. Omitted note “8”, in quadrant D-4, from existing hollow metal storefront door/window on west elevation.
2. Omitted note “9”, in quadrant B & C/D-8, from north elevation doors into the chapel.
3. Omitted note “10” in quadrant E-7 to remove light fixture over double doors.
b. Sheet A1.0, Sheet 3 of 7:
1. Omitted note “G” in quadrant D-4 from existing hollow metal storefront door/window on west elevation.
2. Omitted note “H” in quadrant B & D-8 from north elevation doors into the chapel.
Date: August 4, 2020
3. Revised Note “H” to state “Remove existing Hollow Metal Door, Frame and Hardware and replace with Hollow Metal Door, Frame and Hardware.
c. Sheet A2.0, Sheet 4 of 7
1. Omitted note “C” in quadrant C-5 from the west hollow metal storefront door and window.
2. Omitted note “D” in quadrant A-8 from north elevation doors into chapel.
d. Sheet A2.1, Sheet 5 of 7
1. Omitted note “3” in quadrants A-2 and A-3 from north elevation doors into chapel.
2. Omitted note “D” in quadrants A-1 and A-4 from north elevation doors into chapel.
END OF ADDENDUM #1