Solicitation - FA282325R0020.pdf

PDF 2 MB Posted

Attached to
Eglin Demo IDIQ Federal contract opportunity
Solicitation number
FA282325R0020
Issued by
Department of the Air Force Materiel Command Test Center

About this file

This document is a Request for Proposal (RFP) for an Indefinite Delivery/Indefinite Quantity (IDIQ) demolition contract at Eglin Air Force Base. The solicitation (FA282325R0020) is specifically for demolition services on Eglin AFB and surrounding reservations, with task orders ranging between $1,000 and $750,000. The contract is set aside exclusively for 8(a) certified small businesses, with an estimated overall construction magnitude between $5,000,000 and $10,000,000.

Key procurement details include a contract performance period of 10 calendar days to begin work and 1,827 calendar days to complete work after receiving notice to proceed. Proposals are due by 12:00 PM local time on 10 July 2025, with performance bonds required. The contract will be administered by the Air Force Test Center (AFTC) Contracting Division at Eglin AFB, Florida, with funding to be cited on individual task orders. Contractors must be prepared to perform self-performed demolition work, including removal, transportation, and disposal of demolished items, without subcontracting.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR

INFORMATION CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

CODE

6. PROJECT NUMBER

8. ADDRESS OFFER TO

4. CONTRACT NUMBER

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 12/2022)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

SEALED BID (IFB)

INVITATION FOR BID

NEGOTIATED (RFP)

REQUEST FOR PROPOSAL

3. DATE ISSUED PAGE OF PAGES

AWARD (To be completed by Government)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 12/2022) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES

CODE AT

27. PAYMENT WILL BE MADE BY

10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

Section A - Solicitation/Contract Form EGLIN AFB Demolition Indefinite Delivery Indefinite Quantity (IDIQ) Contract

Product Service Code: P400

North American Industry Classification System (NAICS): 238910 Date: 03 Jun 2025

Annual Receipts: USD 19,000,000.00

FA282325R0020

Section B - Supplies or Services & Prices or Costs

Section C - Description/Specifications/Statement of Work This acquisition will be conducted using competitive 8(a) procedures IAW FAR 19.805 1(a). For this procurement, it has been determined that competition will be limited to 8(a) certified firms.

Specifications - See Statement of Work, dated 20 May 2025

SEE SCHEDULE, offeror is required to complete and return SF 1442, Section B through Section K

Faxed or emailed proposals will NOT be accepted.

A post award conference will be held and will be at a date and time specified after contract award, see Section L. Site visits will be conducted on individual task orders after award.

Funds are currently available for this project. Funding will be cited on each individual task order as stated in Section G.

The Magnitude of Construction is between $5,000,000 and $10,000,000.

The Magnitude of Construction of individual task orders issued hereunder are between $1,000 and $750,000.

Requirements EGLIN AFB Demo Indefinite Delivery Indefinite Quantity (IDIQ) Contract

Section D - Packaging and Marking

Section E - Inspection and Acceptance

FAR Clauses Incorporated by Reference

Number Title Effective Date

Alternate/ Deviation

Variation Effective Date

52.246-4 Inspection of Services-Fixed-Price. Aug 1996 52.246-13 Inspection-Dismantling, Demolition, or Removal of Improvements. Aug 1996

Section F - Deliveries or Performance Overall Contract Delivery Period

FAR Clauses Incorporated by Reference

Number Title Effective Date

Alternate/ Deviation

Variation Effective Date

52.242-15 Stop-Work Order. Aug 1989

Section G - Contract Administration Data

DFARS Clauses Incorporated by Reference

Number Title Effective Date

Alternate/ Deviation

Variation Effective Date

252.232-7003 Electronic Submission of Payment Requests and Receiving Reports. Dec 2018

DFARS Clauses Incorporated by Full Text

252.232-7006 Wide Area WorkFlow Payment Instructions. (Jan 2023)

WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (JAN 2023)

(a) As used in this clause- Definitions.

"Department of Defense Activity Address Code (DoDAAC)" is a six position code that uniquely identifies a unit, activity, or organization.

"Document type" means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

"Local processing office (LPO)" is the office responsible for payment certification when payment certification is done external to the entitlement system.

"Payment request" and "receiving report" are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(b) The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Electronic invoicing.

Defense Federal Acquisition Regulation Supplement (DFARS) 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(c) To access WAWF, the Contractor shall- WAWF access.

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.

(d) The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before WAWF training.

submitting payment requests through WAWF. Both can be accessed by selecting the "Web Based Training" link on the WAWF home page at https://wawf.eb.mil/

(e) Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol. WAWF methods of document submission.

(f) The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this WAWF payment instructions.

contract or task or delivery order:

(1) The Contractor shall submit payment requests using the following document type(s): Document type.

(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.

(ii) For fixed price line items-

(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.

Approved Progress Report (AF IMT 3065)

(Contracting Officer: Insert applicable invoice and receiving report document type(s) for fixed price line items that require shipment of a deliverable.)

(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.

Construction Invoice

(Contracting Officer: Insert either "Invoice 2in1" or the applicable invoice and receiving report document type(s) for fixed price line items for services.)

(iii) For customary progress payments based on costs incurred, submit a progress payment request.

(iv) For performance based payments, submit a performance based payment request.

(v) For commercial financing, submit a commercial financing request.

(2) ) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.

[Note: The Contractor may use a WAWF "combo" document type to create some combinations of invoice and receiving report in one step.]

(3) The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating Document routing.

payment requests and receiving reports in the system.

Routing Data Table*

Field Name in WAWF Data to be entered in WAWF

Pay Official DoDAAC TBD on Individual Task Orders

Issue By DoDAAC FA2823

Admin DoDAAC FA2823

Inspect By DoDAAC F1T2BR

Ship To Code ____

Ship From Code ____

Mark For Code ____

Service Approver (DoDAAC) ____

Service Acceptor (DoDAAC) ____

Accept at Other DoDAAC ____

LPO DoDAAC ____

DCAA Auditor DoDAAC ____

Other DoDAAC(s) ____

(*Contracting Officer: Insert applicable DoDAAC information. If multiple ship to/acceptance locations apply, insert "See Schedule" or "Not applicable.")

(**Contracting Officer: If the contract provides for progress payments or performance-based payments, insert the DoDAAC for the contract administration office assigned the functions under FAR 42.302(a)(13).)

(4) The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance Payment request.

with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.

(5) The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F. Receiving report.

(g) WAWF point of contact.

(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.

Kristine.wright.2@us.af.mil

(Contracting Officer: Insert applicable information or "Not applicable.")

(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.

(End of clause)

Section H - Special Contract Requirements

SECTION H-SPECIAL CONTRACT REQUIREMENTS

H-1 PERFORMANCE AND PAYMENT BONDS (INDEFINITE DELIVERY INDEFINITE QUANTITY (IDIQ) CONTRACTS) Pursuant to FAR clause 52.228-15, Performance and Payment Bonds, the contractor shall submit its performance and payment bonds no later than 10- days after award of the contract. The Contractor shall furnish two bonds each with surety or sureties acceptable to the Government in the form of a Performance Bond (Standard Form 25) and a Payment Bond (Standard Form 25A). The penal sums of such bonds shall be as follows:

(a) Performance Bond. The penal sum of the Performance Bond shall equal one hundred percent (100%) of the annual value (excluding option years not exercised) of the IDIQ contract. If the cumulative value of all active Task Orders exceeds the annual value, at any one given time, the Contractor shall furnish additional performance bonding to reflect increased value of cumulative active Task Orders. This requirement also applies to any options exercised by the Government. Any bonds will be furnished by the Contractor to the Government prior to commencement of contract performance.

(b) Payment Bonds. The penal sum of the Payment Bond shall equal one hundred percent (100%) of the annual value (excluding option years not exercised) of the Indefinitely Delivery, Indefinite Quantity contract. If the cumulative value of all active Task Orders exceeds the annual value, at any one given time, the Contractor shall furnish additional performance bonding to reflect increased value of cumulative active Task Orders. This requirement also applies to any options exercised by the Government. Any bonds will be furnished by the Contractor to the Government prior to commencement of contract performance.

H-2 PERFORMANCE AND PAYMENT BONDS (CONSTRUCTION)

Pursuant to FAR clause 52.228-15, Performance and Payment Bonds, the contractor shall submit its performance and payment bonds no later than 10-days after award of the contract. The Contractor shall furnish two bonds each with surety or sureties acceptable to the Government in the form of a Performance Bond (Standard Form 25) and a Payment Bond (Standard Form 25A). The penal sums of such bonds shall be as follows:

(a) Performance Bond. The penal sum of the Performance Bond shall equal one hundred percent (100%) of the value of the contract. Any bonds will be furnished by the Contractor to the Government prior to commencement of contract performance.

(b) Payment Bonds. The penal sum of the Payment Bond shall equal one hundred percent (100%) of the value of the contract. Any bonds will be furnished by the Contractor to the Government prior to commencement of contract performance.

H-3 CONFORMANCE WITH ENVIRONMENTAL MANAGEMENT SYSTEMS (POLLUTION PREVENTION AND RIGHT- TO KNOW INFORMATION)

(a) In addition to the requirements in FAR 52.223-5, contractors shall provide a list of toxic and hazardous chemicals to the Facility Hazardous Materials Cell, 96 CEG/CEIEC, 850-882-5929, before bringing any material onto the facility. This list shall consist of the material name, manufacturer name and address, quantity, and size of the materials. This list may be in Microsoft Word or Excel. Updates of this list shall be submitted quarterly to the above office.

(b) The Contractor shall perform work under this contract consistent with the relevant policy and objectives identified in the agency, organizational, or facility environmental management system (EMS) applicable for your contract. The Contractor shall perform work in a manner that conforms to all appropriate Environmental Management Programs and Operational Controls identified by the agency, organizational, or facility EMS, and provide monitoring and measurement information as necessary for the organization to address environmental performance relative to the environmental, energy, and transportation management goals.

In the event an environmental nonconformance or no Pre-testing of Fire Alarm and suppression noncompliance associated with the contracted services is identified, the contractor shall take corrective and/or preventative actions. In the case of a noncompliance, the Contractor shall respond and take corrective action immediately. In the case of a nonconformance, the Contractor shall respond and take corrective action based on the time schedule established by the EMS Site Coordinator, 96 CEG/CEIEC, 850-882-5929. In addition, the Contractor shall ensure that their employees are aware of the roles and responsibilities identified by the environmental management system and how these requirements affect their work performed under this contract.

(c) All on-site contractor personnel shall complete facility sponsored environmental training specific to the facility. The facility training will take approximately thirty minutes to accomplish. The training must be completed within 90 days of the contractor employee being work on the installation. The method of training can be video or my seminar presentations. Documentation of the training will be provided to EMS Coordinator, 96 CEG/CEIEC, 850-882-5929. Upon contract award, the Contracting Officer's Representative will notify the facility-level Environmental Management Systems Coordinator, 96 CEG/CEIEC, 850-882-5929, to arrange EMS training for appropriate staff.

H-4 CONSTRUCTION PERMITS

In accordance with (IAW) FAR 52.236-7, the Contractor shall obtain a construction permit for any construction work on Eglin Air Force Base. An AF Form 103 "Base Civil Engineering Work Clearance Request" must be submitted with all required signatures, to the Contract Inspector prior to beginning of performance on the job site. No work shall begin until approval of the AF Form 103 has been granted.

H-5 DAILY REPORT TO INSPECTOR

(a) The Contractor shall submit a Daily Report to 96 CEG/CEOM inspectors on 96 TW Form 3. The report shall include weather conditions, work accomplished, test accomplished, test reports, delays, and discrepancies. Reports should also include photographs of the site as necessary to document progress and any differing site conditions as necessary. Documentation of any differing site condition in a daily report does not relieve the Contractor of its responsibility to report any differing site condition to the Contracting Officer pursuant to FAR clause 52.236-2, Differing Site Conditions.

(b) The report to the inspector shall be the original signed by the contractor or his superintendent and turned into 96 CEG/CEOM inspectors by 12:00 noon the following workday.

H-6 HAZARDOUS WASTE REMOVAL

The Contractor shall dispose of all hazardous waste in accordance with all applicable local, federal, and state environmental laws and regulations, including but not limited to 40 CFR 260-268, Hazardous Waste Management, and Rule 17-30 Florida Administrative Code. The Contractor shall assume the responsibility of determining what constitutes "hazardous waste" and complying with all environmental laws and regulations governing its removal.

H-7 HURRICANE SEASON

Hurricane season for the state of Florida is normally the period from 01 June through 30 November. During an actual hurricane, tropical storm, or tropical depression condition, you may be contacted by the contracting office and requested to secure equipment, clean up your work area and properly protect stored materials. In accordance with the contract clause FAR 52.236-9, "Protection of Existing Vegetation, Structures, Equipment, Utilities and Improvements" and FAR 52.236-12 "Cleaning Up," you should keep this in mind and maintain your work area free from debris and in a safe and secure condition at the completion of each workday. A duty is imposed on the Contractor to monitor local weather conditions, weather bulletins and base closure information in the local media. The Contractor must contact the Contract Administrator with a report of conditions adversely affecting the construction site.

H-8 IMPLEMENTATION OF WARRANTY OF CONSTRUCTION

(a) Any manufacturer's guarantees which extend beyond or in addition to the normal one-year guaranty required by contract clause FAR 52.246-21 shall be furnished to the Government in their entirety, including names of vendors responsible for servicing said warranties.

(b) The following paragraph is applicable if this contract requires any painting whatsoever: If painted surfaces blister, peel, scale, become loose, effloresce, chalk, mildew, or otherwise show defective paint surfaces, the Government shall notify the Contractor in writing within a reasonable time after discovery. The Contractor shall prepare, prime, and repaint those surfaces in accordance with applicable paragraphs of the contract. Repainting shall be carried to natural stopping points such as corners, offsets, points of change of masonry to wood trim, and upward to eaves or ceilings, and downward to ground or floor level, in order that the entire wall will have an even texture. Where the surface to be repainted is a wood surface, the repainting shall be applied to the entire wood surface up to the edge of trim or to eaves, as applicable, in order that the repainted surface shall have an even texture. The contractor shall save harmless the Government against all liability and compensate private individuals for damage to their personal property caused directly or indirectly by negligent conduct including over spraying but not limited thereto. Furthermore, the Contractor shall post warning signs within the area where paint is being applied which gives notice that no party should park within the danger area. The location, size and lettering of the signs shall be as approved by the Contracting Officer.

(c) The above stated painting requirement and its effective period will be subject to the provisions of the Warranty of Construction as set forth in FAR 52.246-21.

(d) Prior to final acceptance of the work covered by this contract, the Contractor shall furnish in writing to the Contracting Officer a list of all items of equipment furnished. This list will include:

(1) Nomenclature of each item, type or serial number, and the name and address of the manufacturer;

(2) Cost;

(3) Period of guarantee; name, telephone number and address of the subcontractor or supplier; and name, telephone number and address of the service agency that will be responsible for service in event of failure or malfunction. This list will be accompanied by applicable guaranteed documents.

(e) To prevent delays and inconveniences to the Government and to ensure that equipment will be promptly serviced, the contractor shall make service arrangements with agencies located in the vicinity of the contract work.

(f) The Contracting Officer will furnish the prime Contractor the name of the office that will represent the Government regarding guaranteed conditions hereunder.

(g) The Contractor, at its expense, shall furnish and affix a decal or tag, as may be directed, to each piece of equipment covered by guarantee. The decal or tag will indicate the serial number of the equipment, guarantee period, contract number and name of Contractor. Such decal or tag shall be affixed where directed by the Contracting Officer.

H-9 INSPECTION AND SURVEILLANCE

The Director, Civil Engineering, Eglin Air Force Base, Florida, is designated as the representative of the Contracting Officer for the purpose of surveillance and inspection of performance of work under this contract. This designation does not include authority to direct or authorize the Contractor to make changes in the scope or terms of the contract without the written authority of the Contracting Officer. The contractor shall notify the Construction Management Branch, 96 CEG/ CEOM (telephone 882-2864) at least 24 hours in advance of the date work will commence under this contract; contractor shall also notify that office at earliest possible time of anticipated absence(s) from the job site.

H-10 INSURANCE CLAUSE IMPLEMENTATION

The Contractor shall obtain and maintain the minimum kinds and amounts of insurance during performance of this contract as specified in FAR Sub Part 28.3.

H-11 MEDICAL INFORMATION

The name of the Contractor's physician(s) and preferred hospital (for use in the event of industrial injury of employees) shall be posted by the Contractor at the site of the work in a prominent place where it can easily be seen by the workers. This information shall also be furnished to the Director of Base Medical Services, 96 MDG/SG, and Eglin AFB FL 32542-5300.

H-12 ON-BASE PERFORMANCE

(a) Work on this project shall be accomplished during normal hours, which are 7:00 AM to 3:30 PM, Monday through Friday, except legal holidays. Any work desired to be accomplished during other than the normal hours will require prior approval of the Contracting Officer. The Contractor must submit a written request to the Contracting Officer.

(b) The Contractor's performance may be interrupted from time to time because of high priority mission schedules. For each calendar day and/or portion of a calendar day that the contractor is removed from the job site, the contract schedule will be adjusted by one (1) calendar day.

(c) If a building remains occupied throughout construction, special provisions apply as follows: To be disclosed at pre-solicitation site-visit or as directed by CE representative.

H-13 SALVAGE MATERIALS

a) All items of Government property indicated on the drawings or in the specifications to be removed and disposed of by the contractor shall become the property of the contractor and shall be removed promptly from the Eglin AFB Reservation and legally disposed of.

(b) Contractors are encouraged to recycle salvage materials when possible. Contact the Eglin Recycling Center, 850-882-7744, for assistance.

H-14 SUPERINTENDENT

Upon notification of award, the Prime Contractor shall identify a superintendent and alternate for this contract and job site. The full name, home address, SSN#, date of birth, state driver's license number, days/hours of access required, and consent to a background check for security purposes of each such employee shall be required. The Prime Contractor's superintendent and/or alternate shall be accountable for all individuals allowed onto the installation. The likelihood of a potential employee meeting all security requirements and being granted authorization to access the base should be considered in all hiring and subcontracting decisions. The U.S. Air Force will not be responsible or liable for any costs or delays that a contractor incurs due to a contractor's employee being denied access to Eglin AFB. The Superintendent and/or alternate shall be responsible for collecting badges/PVC cards from all employees upon completion of the project/contract or termination of service. Prior to final payment approval, the Superintendent shall provide a company letter stating that all Eglin AFB access badges issued in the performance of this contract have been properly turned into the 96 Security Forces Squadron (SFS). This letter must have some type of validation from the 96 SFS badging office employee either by stamp or signature.

H-15 UTILITIES

The Contracting Officer shall specify whether electric and water utilities will be available for contractor use.

H-16 UTILITY OUTAGES

Contractor shall notify the Contracting Officer's Representative (COR) in writing two weeks prior to any utility outage Anticipated during the performance of this contract.

H-17 VERIFICATION OF UTILITY LINES

Once utility lines are flagged or spotted by the proper approving utilities authority, it is the Contractor's responsibility to verify the utility location and depth. The Contractor will be responsible for repairing any broken lines that might occur during the digging process. See clause H-22 for special procedures and requirements for communications cyber infrastructure repair procedures.

H-18 WARNING - HAZARDOUS CONDITIONS AT SITE

Please consult Statement of Work to see if the following applies.

(a) Notice to Contractor. The site, entrance routes, or adjacent areas to the site at which you and your employees and your subcontractors will be working have been used by the Air Force as an ammunition test range. There exists a possible danger to person and property from unexploded weapons in and on the ground.

Live bombs, missiles, and other explodable ordnance material may be embedded or partially embedded in the trees or soil. In no event should you or your employees, or your subcontractors or their employees, attempt to remove or otherwise tamper with such material or objects. Removal of such items from the site by unauthorized personnel is considered misappropriation of Government property and may be subject to penalties under law. However, of more importance is the potentially serious or fatal injury to the individual.

(b) Agreement. The Contractor agrees that if, during the performance of work under this contract, its employees, or subcontractors or their employees should encounter any of these munitions, or other unidentifiable objects which resemble ordnance material they will stop work in the immediate area, report such encounter to the Range Operations Control Center (ROCC) at phone number (850) 882-5800 which is manned 24 hours daily and then to the Government Inspector by the most expeditious method, and proceed as directed. The Contractor further agrees to cause warning to be brought to the attention of each of its employees, and to each subcontractor and its employees who will be working at the site.

(c) Procedures for Assuring Safety

(1) A poster describing the various items discussed above will be furnished to the Contractor at the preconstruction briefing. The Contractor shall display this poster in a prominent place at the construction site, readily available for inspection by all personnel.

(2) At the conclusion of the preconstruction briefing the Contractor will be required to signify on an appropriate form that the existence of hazardous munitions items has been discussed. The form will also indicate that the contractor agrees to brief all employees and subcontractors and will require all subcontractors to brief their employees on the content of this clause.

(3) The Contractor agrees to include the warning and briefing requirements of this clause in all subcontracts.

H-19 WEATHER DELAYS

The Anticipated Normal Weather Delay Schedule shown below is developed by month for this geographic location using National Oceanic and Atmospheric Administration (NOAA) and similar Weather Averaging System data for the project's general location. The Government has included additional time in the allowed performance period using this data. (The basic performance period allows seven calendar days for every five-day working day assuming work is performed Monday through Friday). The contractor's progress schedule must take these anticipated adverse weather delays into account in all Weather dependent activities to ensure timely completion of the job.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY WORKDAYS BASED ON A 5-DAY WORK WEEK

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

5 5 5 3 3 5 8 6 5 3 4 5

Upon acknowledgement of Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on his Daily Report (96 TW Form 3), the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for fifty percent or more of the Contractor's scheduled workday and must cause a delay in the work activities critical to contract completion. To obtain relief from contract schedule requirements, the Contractor will have to demonstrate not only that the anticipated amount of weather delay was exceeded by actual weather interruption, but also that reasonable efforts were made to compensate for such excess interruptions through changes in work hours, changes in the planned sequence of work, increased concurrent activities, or other available measures. Contemporaneous documentation of such efforts and prompt coordination thereof with government inspectors is encouraged (see below). If all reasonable effort to complete the required performance on schedule fail and it is determined that excessive inclement weather was the cause of that failure, the Contractor may request extension of the project performance period for any weather delays suffered because of adverse weather beyond the number day indicated on the chart. The number of workdays of delay added to the schedule shall be converted to calendar days by adding the appropriate number of weekend days associated with that number of workdays.

(a) Adverse weather days will not be granted for other than normal workdays that the Contractor requested to work solely for the Contractor's convenience to meet the contract performance period.

(b) Any extensions to the contract because of change orders will have the normal adverse weather days figured into the extension period.

(c) If the contract dictates an alternate performance period other than a normal Monday through Friday five-day workweek, an extension will be considered based on the contract requirement for a workday.

Upon the request of the Contractor made within one workweek after the relevant events, the government inspector will review the Contractor's documentation of weather delays and circumstances relevant to the availability of work around and promptly confirm or dispute the Contractor's conclusions in writing to the Contractor and the Contracting Officer. If the Contractor requests an adjustment to the contract schedule based on the government inspector's review, the contractor shall notify the Contracting Officer in writing and provide relevant information and recommendations regarding the request. The Contracting Officer shall determine whether the request should be promptly granted, deferred pending determination of cumulative weather effects during the contract performance period, denied, or some combination thereof. The reason for any deferral or denial will be simultaneously communicated to the Contractor in writing. The findings of the Contracting Officer shall be final and conclusive subject to appeal under the Disputes clause. Upon any extension, the Contractor shall immediately submit to the Contracting Officer a revised progress schedule to meet the revised performance period.

H-20 ACCESS TO EGLIN AIR FORCE BASE

(a) The contractor shall obtain base identification and vehicle passes, if required, for all contractor personnel who make frequent visits to or perform work on the Air Force installation(s) cited in the contract. Contractor personnel are required to wear or prominently display installation identification badges or contractor-furnished, contractor identification badges while visiting or performing work on the installation.

(b) The contractor must submit in writing to the designated Contract Specialist or Contracting Officer a request for all personnel needing access to Eglin AFB and associated sites. The Government will provide a memorandum template to the Contractor for the submission of all badges/passes. The memorandum is required regardless of the length of visit. The Contractor shall input the following information into the template:

FROM: Input Company Name, Address, and Point of Contact Paragraph 1: The following individuals require access to (Eglin AFB) to perform official duties at: Indicate what area you will need access (A) Eglin Main Base; (B) Duke Field; (C) Ranger Camp; (D) Range Road and (E) 7th SFG. Their duties will include (Input Project Title). All work will begin on (Input work start date) and will be accomplished by (Input work end date). The contract number (Input contract number). Paragraph 4: Complete the table providing the names/Days/Hrs. of Access/Full SSN/Date of Birth /Driver's License #/State of employees and subcontractor employees needing access to the base. ***NOTE: DO NOT USE NICKNAMES WHEN LISTING PERSONNEL. FOR EXAMPLE, DO NOT USE "BILL" IF THE INDIVIDUAL'S LEGAL NAME IS "WILLIAM"*** The Contracting Officer or Contracting Specialist will endorse the request and then send it to Security Forces via email for processing into the Security Forces database. Anticipate a three to five business day lead time for Security Forces to process the documents and conduct the required background check. Contractors should submit its requests for badge/passes in a timely manner so as not to delay or impede project progress. Once the background check is complete, a copy will be returned to the POC listed on the envelope. The prime contractor can provide paperwork for their subcontractor(s) and submit as many documents per envelope as necessary.

(c) When reporting to the registration office, the authorized contractor individual(s) should provide a valid driver's license, current vehicle registration, valid vehicle insurance certificate and social security card to obtain a vehicle pass. All deliveries to contractor work sites on Eglin AFB main base must go through the North Gate, located off SR-85 South. Trucks trying to enter the East, West or the Northwest (old ACC) gate will be turned around and told to use the North Gate.

Contractors' work trucks carrying equipment and tools are also required to use the North Gate. For work at Duke Field AFB, both deliveries and contractor work trucks will use the main Duke Field AFB gate. Pick up of badging for contractors once granted will only be done at Eglin AFB registration office.

(d) During performance of the contract, the contractor shall be responsible for obtaining required identification for newly assigned personnel and for prompt return of credentials and vehicle passes for any employee who no longer requires access to the work site. A new access badge will not be issued when the old/expired badge is not returned to Security Forces. Any lost badges have to be explained in writing using a company letter head and signed by an authorized company representative. The lost badge letter must be sent to the Contract Specialist and then signed by the Contract Specialist or Contracting Officer, and then the letter will be sent to Security Forces for their review. After Security Forces has the letter, a new badge may be issued.

(e) When work under this contract requires unescorted entry to controlled or restricted areas, the contractor shall comply with AFI 31-101, Volume 1, The Air Force Installation Security Program, and AFI 31-501, Personnel Security Program Management citing the appropriate paragraphs as applicable.

(f) Upon completion or termination of the contract or expiration of the identification passes, the prime contractor shall ensure that all base identification passes issued to employees and subcontractor employees are returned to the issuing office.

(g) Failure to comply with these requirements may result in withholding of final payment.

H-21 COMMUNICATIONS CYBER INFRASTRUCTURE REPAIR PROCEDURES NOTE:

***All temporary and/or permanent repairs made shall be accomplished by the repairing agency at no further cost to the government. Repairs shall be IAW all applicable industry and local standards, whichever is more stringent. ***

1.1 Temporary Repair Actions - Temporary repairs shall be initiated within 12 hours of reported/identified damage. All circuits (pairs, strands, etc...) must be restored to full mission capability within 24 hours. Temporary repairs shall not be considered a permanent repair fix action.

a. The repairing agency shall provide 24 hour/7 day a week on-call maintenance service for temporary repairs until all permanent repairs have been completed and accepted by the 96 CS/SCOW Branch Chief or 96 CS designated representative.

1.2 Permanent Repair Actions - All fiber optic and copper communications cyber infrastructure shall be restored to its original state prior to damage for all permanent repairs. At a minimum, all damaged communications cyber infrastructure shall be replaced regardless of distance and/or cost incurred, to the closest pre-existing, splice/terminal locations. New or additional splices shall not be allowed for permanent repairs without written approval from the 96 CS/SCOW Branch Chief or 96 CS designated representative.

a. The repairing agency shall provide a Statement of Work (SOW), Test Plan and Product Submittals for all proposed permanent repair solutions within 5-business days from date of reported damage to 96 CS/SCOW for written approval prior to beginning any permanent repairs.

NOTES:

***Maximum known distances between existing fiber optic cable splice points are up to 17,000 feet*** ***Maximum known distances between existing copper cable splice points is up to 5,000 feet*** ***Polymer type maintenance holes and/or hand holes shall not be used for supporting communication cyber infrastructure on EAFB***

H-22 - PAYMENT INFORMATION

(a) Payment terms are Net 14. There are no payment discount terms for this award.

(b) For customary progress payments based on work completed, contractor is to submit a progress report (AF 3065) to the Contracting Officer for review / approval.

(c) Following receipt of approved / signed progress report (AF 3065), contractor is submitting an invoice via electronic means utilizing the WAWF system subject to DFARS 252.232-7006 Wide Area Work Flow Payment Instructions.

H-23 SECURITY REQUIREMENTS - PERSONNEL

1. Work under this contract is restricted to U.S. citizens.

2. The request for personnel passes shall be accompanied with the following certification:

"I hereby certify that all personnel on this list are either born U.S. citizens, naturalized U.S. citizens with the naturalization number shown."

Signature/Firm Name

3. Documents Acceptable for Proof of Citizenship:

a. Birth registration card

b. Certificate of live birth, birth certificate

c. Certificate of Naturalization

d. Certificate of registration

e. DD-214 (Must Cite Birthplace)

f. DD Form 4 (Contract for Enlistment and Must Cite Birthplace)

g. DD 1966 (Application for Enlistment)

h. Military discharge papers (must cite birthplace)

i. Delayed birth certificate

j. Hawaii certificate of foreign birth

k. Hospital birth certificate

l. Marriage license certificate

m. Merchant marine certificate

n. Military officer ID card

o. Notification of birth registration

p. State of Hawaii ID card

q. USA passport

r. Verbal inquiry with State of Hawaii Vital Statistics Office

Section I - Contract Clauses

FAR Clauses Incorporated by Reference

Number Title Effective Date

Alternate/ Deviation

Variation Effective Date

52.202-1 Definitions. Jun 2020 52.203-3 Gratuities. Apr 1984 52.203-5 Covenant Against Contingent Fees. May 2014 52.203-6 Restrictions on Subcontractor Sales to the Government. Jun 2020 52.203-7 Anti-Kickback Procedures. Jun 2020 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity. May 2014 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity. May 2014 52.203-12 Limitation on Payments to Influence Certain Federal Transactions. Jun 2020 52.203-13 Contractor Code of Business Ethics and Conduct. Nov 2021 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements. Jan 2017 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards. Jun 2020 52.204-13 System for Award Management Maintenance. Oct 2018 52.204-18 Commercial and Government Entity Code Maintenance. Aug 2020 52.204-19 Incorporation by Reference of Representations and Certifications. Dec 2014

52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities.

Dec 2023

52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.

Nov 2021

52.204-27 Prohibition on a ByteDance Covered Application. Jun 2023

52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded

Jan 2025

52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters. Oct 2018 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations. Nov 2015 52.210-1 Market Research. Nov 2021 52.215-2 Audit and Records-Negotiation. Jun 2020 52.215-8 Order of Precedence-Uniform Contract Format. Oct 1997 52.215-10 Price Reduction for Defective Certified Cost or Pricing Data. Aug 2011 52.215-11 Price Reduction for Defective Certified Cost or Pricing Data-Modifications. Jun 2020 52.215-12 Subcontractor Certified Cost or Pricing Data. Jun 2020 52.215-12 Subcontractor Certified Cost or Pricing Data. (Alternate I) Jun 2020 Alternate I Aug 2020 52.215-13 Subcontractor Certified Cost or Pricing Data -- Modifications (Deviation 2022-O0001) Jun 2020 Deviation 2022-O0001 Oct 2021 52.215-15 Pension Adjustments and Asset Reversions. Oct 2010 52.215-18 Reversion or Adjustment of Plans for Postretirement Benefits (PRB) Other Than Pensions. Jul 2005 52.215-19 Notification of Ownership Changes. Oct 1997

52.215-21 Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data-Modifications.

Nov 2021

52.219-8 Utilization of Small Business Concerns. Jan 2025 52.222-3 Convict Labor. Jun 2003 52.222-35 Equal Opportunity for Veterans. Jun 2020 52.222-36 Equal Opportunity for Workers with Disabilities. Jun 2020 52.222-37 Employment Reports on Veterans. Jun 2020 52.222-50 Combating Trafficking in Persons. Nov 2021 52.222-54 Employment Eligibility Verification. Jan 2025 52.223-5 Pollution Prevention and Right-to-Know Information. May 2024 52.223-12 Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners. May 2024 52.223-20 Aerosols. May 2024 52.223-23 Sustainable Products and Services. May 2024 52.225-13 Restrictions on Certain Foreign Purchases. Feb 2021 52.226-7 Drug-Free Workplace. May 2024 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving. May 2024 52.228-5 Insurance-Work on a Government Installation. Jan 1997 52.229-3 Federal, State, and Local Taxes. Feb 2013 52.229-12 Tax on Certain Foreign Procurements. Feb 2021 52.232-11 Extras. Apr 1984 52.232-17 Interest. May 2014 52.232-18 Availability of Funds. Apr 1984 52.232-23 Assignment of Claims. May 2014 52.232-33 Payment by Electronic Funds Transfer-System for Award Management. Oct 2018 52.232-39 Unenforceability of Unauthorized Obligations. Jun 2013 52.232-40 Providing Accelerated Payments to Small Business Subcontractors. Mar 2023 52.233-1 Disputes. May 2014 52.233-3 Protest after Award. Aug 1996 52.233-4 Applicable Law for Breach of Contract Claim. Oct 2004 52.236-2 Differing Site Conditions. Apr 1984 52.236-3 Site Investigation and Conditions Affecting the Work. Apr 1984 52.236-6 Superintendence by the Contractor. Apr 1984 52.236-7 Permits and Responsibilities. Nov 1991 52.236-8 Other Contracts. Apr 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. Apr 1984 52.236-10 Operations and Storage Areas. Apr 1984 52.236-12 Cleaning Up. Apr 1984 52.236-13 Accident Prevention. Nov 1991 52.236-21 Specifications and Drawings for Construction. Feb 1997

52.237-2 Protection of Government Buildings, Equipment, and Vegetation. Apr 1984 52.242-13 Bankruptcy. Jul 1995 52.243-4 Changes. Jun 2007 52.244-6 Subcontracts for Commercial Products and Commercial Services. Jan 2025 52.246-25 Limitation of Liability-Services. Feb 1997

52.249-3 Termination for Convenience of the Government (Dismantling, Demolition, or Removal of Improvements).

Apr 2012

52.249-10 Default (Fixed-Price Construction). Apr 1984 52.249-10 Default (Fixed-Price Construction). (Alternate I) Apr 1984 Alternate I Apr 1984

DFARS Clauses Incorporated by Reference

Number Title Effective Date

Alternate/ Deviation

Variation Effective Date

252.203-7000 Requirements Relating to Compensation of Former DoD Officials. Sep 2011 252.203-7001 Prohibition on Persons Convicted of Fraud or Other Defense-Contract-Related Felonies. Jan 2023 252.203-7002 Requirement to Inform Employees of Whistleblower Rights. Dec 2022 252.203-7003 Agency Office of the Inspector General. Aug 2019 252.203-7004 Display of Hotline Posters. Jan 2023 252.204-7003 Control of Government Personnel Work Product. Apr 1992 252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting. May 2024 252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services. Jan 2023 252.204-7020 NIST SP 800-171 DoD Assessment Requirements. Nov 2023 252.205-7000 Provision of Information to Cooperative Agreement Holders. Oct 2024

252.209-7004 Subcontracting with Firms that are Owned or Controlled by the Government of a Country that is a State Sponsor of Terrorism.

May 2019

252.215-7002 Cost Estimating System Requirements. Jan 2025 252.222-7006 Restrictions on the Use of Mandatory Arbitration Agreements. Jan 2023 252.223-7006 Prohibition on Storage, Treatment, and Disposal of Toxic or Hazardous Materials. Sep 2014 252.223-7008 Prohibition of Hexavalent Chromium. Jan 2023 252.225-7012 Preference for Certain Domestic Commodities. Apr 2022 252.225-7048 Export-Controlled Items. Jun 2013 252.225-7056 Prohibition Regarding Business Operations with the Maduro Regime. Jan 2023 252.225-7058 Postaward Disclosure of Employment of Individuals Who Work in the People's Republic of China. Jan 2023 252.225-7060 Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region. Jun 2023

252.226-7001 Utilization of Indian Organizations, Indian-Owned Economic Enterprises, and Native Hawaiian Small Business Concerns.

Jan 2023

252.226-7003 Drug-Free Work Force. Aug 2024 252.232-7010 Levies on Contract Payments. Dec 2006 252.236-7005 Airfield Safety Precautions. Dec 1991 252.237-7010 Prohibition on Interrogation of Detainees by Contractor Personnel. Jan 2023 252.243-7001 Pricing of Contract Modifications. Dec 1991 252.243-7002 Requests for Equitable Adjustment. Dec 2022 252.244-7000 Subcontracts for Commercial Products or Commercial Services. Nov 2023

FAR Clauses Incorporated by Full Text

52.204-1 Approval of Contract. (Dec 1989)

Approval of Contract (Dec 1989)

This contract is subject to the written approval of Contracting Officer[identify title of designated agency official here] and shall not be binding until so approved.

(End of clause)

52.211-11 Liquidated Damages-Supplies, Services, or Research and Development. (Sep 2000)

Liquidated…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .