Questions and Answers # 1
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Q_and_A_03_May.pdf | ||
| GWEF_BLDG_374_CEILING_HEIGHTS.PDF | ||
| Q_and_A_02_May.pdf | ||
| Q_and_A_26_Apr.pdf | ||
| Amendment_FA282319RA0050002.pdf | ||
| Conformed_FA282319RA0050002.pdf | ||
| Q_and_A__2_25_Apr.pdf | ||
| Attachment_QA_1_pictures.pdf | ||
| Attachment_QA_1_Carcom_filter.pdf | ||
| Conformed_FA282319RA0050001.pdf | ||
| FA282319RA0050001_SF_30.pdf | ||
| Attachment_C_-_SOW_02Nov2018.pdf | ||
| Attachment_A_-_Specs_02Nov2018.pdf | ||
| Wage_Determination_FL190217.pdf | ||
| Attachment_F_-_Base_Access_Memo.docx | DOCX document | |
| Attachment_D_-_PPQ.pdf | ||
| Attachment_E_-_FRQ.pdf | ||
| FA282319RA005_GWEF_FINAL.pdf | ||
| Attachment_B_-_Drawings_02Nov2018.pdf | ||
| 50_Div_Cost.xls | XLS spreadsheet |
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION FA282319RA005
Replace Halon and Electrical Questions and Answers # 1
19 April 2019
THESE QUESTIONS AND ANSWERS SUPERCEDE ALL PREVIOUS ANSWERS
Question 1:
1- 1a) The RF Testing Note found on sheet E-100 states "The Allowable Threshold of db Leakage Across a Wire Frequency Range Shall be Determined by the User". Please provide the allowable db leakage range in order that an accurate bid may be tabulated. That information will allow us to determine how much time is involved in testing.
1- 1b) Also is there a preferred test method/specification (Example: MIL-STD-188-125-1 – Shielding Effectiveness)?
1- 2) Refer to the Riser Diagram Sheet E-002. Note 1 describes the "New 1200 Amp, Four Phase Filter Basis of Design Corcom". No specifications were provided for the Four Phase Filter. Will specifications for the Filters be provided? What Federal Specs are we required to meet? Will on-site factory start-up services or testing be required?
1- 3) Refer to the Riser Diagram Sheet E-002. Note 3 describes the "500 KVA Power Conditioner...Basis of Design Eaton Power-Sure 700". No specifications were provided for the Power Conditioner. Will specifications for the Power Conditioners be issued? Will testing be required? What Federal Specs are we required to meet? Will on-site factory start-up services or testing be required?
1- 4) In the pre-bid jobsite visit held on 9 Apr 2019, it was mentioned that a recent core drill was made and a photo and information of the core drill sample of the floors was available for review. Please provide the photo and information for accurate pricing.
1- 5) Refer to Specification 26 20 00 Para. 1.3 Submittals (Page 4) and Para. 2.18 (Page 15). Specification 26 20 00 Para. 1.3 states to submit Metering and Specification 2.18 is the specification for the Metering. However, no metering is indicated on the design drawings. Is metering required?
1- 6) Drawing Sheet E-002 indicates to install 4 Parallel Runs of 4 #600 MCM, 1 #3/0 Ground for the feeders from the Power Conditioners to the 1200-Amp Enclosed Breakers and from the 1200-Amp Enclosed Breakers to the Filters. At 75 Degree Celsius it should only require 3 Parallel runs of 4 #600 MCM instead of 4 runs. Please confirm the requirement.
1- 7) Drawing Sheet E-002 Key Note 1 states to provide a "New 1200 Amp Four Phase Filter, Basis of Design Corcom. Provide with Surge-Protective Device." Corcom does not make a Four Phase Filter. They do make 3-Phase 4-Wire Filters. There are no specifications provided for the power line filters. Please clarify the requirements and provide specifications for the power line filters.
1- 8) Refer to Plan Sheet E-602. Panelboard RP51 contains a 225/3 breaker designated to power a Panel RP-41. There is not a Panel RP-41 indicated on the plans. Is Panel RP-41 an existing panel that will be re-fed from the new panel RP51? Please provide the location of the existing Panel RP-41 (if it exists).
1- 9) Refer to Power Riser Sheet E-003 and Sheet E-601. The Power Riser on Sheet E-003 indicates that Panels L1-224, L2-224, L3-224, L4-224, and L5-224 are powered from Panel PDP13, and the Panel schedule for PDP13 found on Sheet E-602 indicates branch breakers for these same panels. Note that Panel L1-224 is indicated to be a 100A MLO Panel on the Power Riser Diagram on Sheet E-003 and is powered with 1-1/2" Conduit with 4 #1 CU . However, Sheet E-601 indicates Panel L1-224 to be a 400A Main Breaker Panel with 100/3 branch breakers powering Panels L2-224, L3-224, L4-224, and L5-
224. Which is correct and what needs to be adjusted?
1- 10) Refer to Power Riser Sheet E-003 and Sheet E-600. The Power Riser on Sheet E-003 indicates that Panels L1-210, L2-210, L3-210, L4-210, and L5-210 are powered from Panel PDP12, and the Panel schedule for PDP12 found on Sheet E-602 indicates breakers for these same panels. Note that Panel L1- 210 is indicated to be a 800A MB Panel on the Power Riser Diagram on Sheet E-003 but is powered with 1-1/2" conduit and 4 #1 CU which does not yield the required amperage indicated. The panel scheduled for Panel L1-210 on Sheet E-600 also indicates Panel L1-210 to be a 800A Main Breaker Panel, but also with 100/3 branch breakers powering Panels L2-210, L3-210, L4-210, and L5-210. What is correct and what needs to be adjusted?
Answer 1:
1- 1a) Acceptance Testing:
Magnetic: 1.0 kHz, 10.0 kHz, 14.0 kHz, 100.0 kHz 1.0 MHz: 50 dB Electric: 5.0 kHz, 100.0 kHz: 100 dB Planewave: 100.0 MHz, 400.0 MHz, 1.0 GHz: 100 dB Microwave: 10.0 GHz, 18.0 GHz, 35.0 GHz: 100 dB Millimeterwave: 94.5 GHz: 80 dB
1- 1b) Yes, utilize MIL-STD-188-125-1 and also comply with Radio Frequency (RF) Shielding Testing per IEEE Std-299 (2006): Baseline testing: 1.0 GHz, 10.0 GHz, 18.0 GHz, 35 GHz, & 94.5 GHz/or info only.
1- 2) Basis of design is a Corcom TECUL4 inductive filter. Install per manufacturers requirements. There are no federal specs for this type of equipment. No factory startup required
1- 3) Install per manufacturers requirements. There are no federal specs for this type of equipment. No factory startup required. Conditioner shall be factory tested prior to delivery.
1- 4) See attached pics of current GEN room floor holes.
1- 5) Yes, metering is required by the contractor. 2500:5 CT’s to be furnished and installed by the contractor. The meter shall be a combination KW-HR and KW demand meter that includes wireless transceiver hardware. The meter and transceiver hardware shall be compatible with Flexnet system currently being utilized by Eglin AFB. The metering (by contractor) and CTs (by contractor) shall be furnished and installed on the new 2,000 KVA transformer that shall be furnished and installed by Chelco. Contractor shall subcontract with Chelco to furnish and install the new 2,000 KVA transformer.
1- 6) Yes, 4 parallel runs is correct due to voltage drop concerns.
1- 7) Basis of design is a Corcom TECUL4 inductive filter. The manufacturer cut sheet shows that the filter has 4 filtered phases. This would be for A, B, C, and N conductors.
1- 8) There is no Panel RP-41 in project. The reference and associated breaker may be deleted from panel schedule.
1- 9) Panel L1-224 will be 100 amp Main Lug Only. Remove four 100 amp/3 pole breakers and install with twenty-two 20 amp/1 pole breakers. All “224” panels are served by PDP13 as shown on riser.
1- 10) Panel L1-210 will be 100 amp Main Lug Only. Remove four 100 amp/3 pole breakers and install with twenty-two 20 amp/1 pole breakers. All “210” panels are served by PDP12 as shown on riser.
Question 2:
There appears to be numerous conduits that will require penetrations at the RF shielded walls. There is a detail shown on page E-100, but it does not show dielectric unions in the detail or listed anywhere in writing that I can find. If dielectric unions are require can you provide a detail on what the requirement is?
Answer 2:
The SECTION detail on E-100 shows the plate (welded to the wall) which will require a pass through chase (welded to the plate) that the conduit (welded to the chase) will pass through. Dielectric unions are not required. Pics of existing GWEF examples attached.
Question 3:
Due to the amount of rigid conduits that is called to be installed in the corridors on page E-100 note 2.
We feel that the existing ceilings need to be removed and re-installed. The areas above the ceiling are already very congested and it is going to be very difficult to install conduit that weights approximately 100 lbs per a 10’ section without damage to the existing ceiling.
Answer 3:
Understood, contractor can remove and replace ceiling grid and ceiling tiles at their discretion to accommodate the work of this project.
Question 4:
There is not enough information to provide pricing on the 1200 amp 4 phase filters. All is says is a( Basis of design corcom) listed on page E-100 note 10. They have requested a model #, part #'s, etc. If the Government can provide more information that will be a great help.
Answer 4:
Reference the attached cut sheet regarding the electrical, enclosure type, and dimensional parameters that must be complied with.
Question 5:
On page E-002 and W-003 it does not show a routing for conduits that leave panel PDP12 and PDP13 that feeds the panels on the 210 side and 224 side. My question is are we allowed to core drill the holes in the floor to go up to feed the associated panels listed in the riser on E-002 and E-003. If this is not acceptable please provide a detail on the routing of conduits.
Answer 5:
Contractor will be allowed to core-drill through floors in Government-approved locations.
Question 6:
Also on Page E-001 note 10 item D if calls for RGS conduit 2” and larger. Can EMT be used in lieu of rigid galvanized steel? If emt can be used it will be a cost saving on material with steel prices going up daily, it also is less labor cost to install. Also it will be less weight for the overhead structure to support. Please advise.
Answer 6:
The request to use EMT instead of RGS for conduits that are 2" and larger is disapproved."
Question 7:
On page E-002 and W-003 it does not show a routing for conduits that leave panel PDP12 and PDP13 that feeds the panels on the 210 side and 224 side. My question is are we allowed to core drill the holes in the floor to go up to feed the associated panels listed in the riser on E-002 and E-003. If this is not acceptable please provide a detail on the routing of conduits.
Answer 7:
Any new welds for penetrations of RF shielding will have to be RF tested.
Conduit shall be installed from generator room floors running from Rm 401 to 301, Rm 301 to 219, and Rm 219-124; and from Rm 400 to 300, Rm 300 to 211, and Rm 211 to 116. Core drilling will be required in order to install conduit between floors. Existing generator room flooring consists of approximately 2" concrete protection slab, class RFA shielding, concrete slab and metal decking and another class RFA shield (verify with as-builts). Conduits shall be secured with continuous welded bead around both class RFA shield penetrations and repair all concrete disturbed as required.
Also, the RF welds need to be tested before concrete repairs are done so any weld leaks can be repaired. Contr4actor will need a welder on site when testing is being done to make any repairs.