Attachment_C_-_SOW_02Nov2018.pdf
PDF 89 KB Posted
- Attached to
- Replace Halon & Electrical at GWEF Federal contract opportunity
- Solicitation number
- FA2823-19-R-A005
About this file
Attachment C: Statement of Work
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| GWEF_BLDG_374_CEILING_HEIGHTS.PDF | ||
| Q_and_A_03_May.pdf | ||
| Q_and_A_02_May.pdf | ||
| Q_and_A_26_Apr.pdf | ||
| Amendment_FA282319RA0050002.pdf | ||
| Conformed_FA282319RA0050002.pdf | ||
| Q_and_A__2_25_Apr.pdf | ||
| Attachment_QA_1_pictures.pdf | ||
| Attachment_QA_1_Carcom_filter.pdf | ||
| Conformed_FA282319RA0050001.pdf | ||
| FA282319RA0050001_SF_30.pdf | ||
| Q_and_A_1_19_Apr.pdf | ||
| Attachment_A_-_Specs_02Nov2018.pdf | ||
| FA282319RA005_GWEF_FINAL.pdf | ||
| Attachment_B_-_Drawings_02Nov2018.pdf | ||
| 50_Div_Cost.xls | XLS spreadsheet | |
| Wage_Determination_FL190217.pdf | ||
| Attachment_F_-_Base_Access_Memo.docx | DOCX document | |
| Attachment_D_-_PPQ.pdf | ||
| Attachment_E_-_FRQ.pdf |
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
FOR CONSTRUCTION
FTFA 18-1013
Replace Halon/Upgrade Electrical, GWEF Bldg 374
02 Nov 2018
1. STATEMENT OF WORK: The Contractor shall perform all construction services for the subject project, according with the associated drawings and specifications, located at Eglin Air Force Base, Florida. It is declared and acknowledged intention and meaning of this work includes:
A. Removing the existing Halon Fire suppression system and replacing with the approved
FM-200 clean agent suppression in areas outlined in the attached drawings and specifications for project FTFA 18-1013. All work shall be accomplished in accordance with the latest UFC
3-600-01 Fire Protection.
B. Upgrading the electrical service to both main test chambers in building 374 per the drawings and specifications. The new 2000 KVA transformer shall be provided and installed by Chelco. Special Clarification Note: This upgrade requires very large electrical equipment with maximum allowable dimensions pertaining to the width, depth, and height shown on sheet
E-100, Note 1, 8, 9, 10, 11. This equipment is expected to have a long lead time. The contractor shall make special efforts to expedite the submittal process as will the government review. The contractor shall overlap as much work as they can as we wait on the arrival of the electrical equipment.
C. Provide architectural modifications at room 308 and 109 suite to support the associated user mission per the drawings and specifications.
2. LOCATION: The work is located at Building 374 Eglin Air Force Base, FL as indicated on the drawings. The exact location of the facility will be indicated by the Contracting Officer.
3. SITE INSPECTION: Prospective bidders are expected to visit the areas of work and verify all conditions of dimensions.
4. SUBMITTALS: To be discussed at the preconstruction meeting include, but may not be limited to: Project Schedule, Shop Drawings, Material Submittals, Work permits, Utility Outage Requests, Utility Connection Requests, Welding Permits, and Burning Permits.
-The contractor is responsible for marking and verifying all utilities not marked.
5. CONFLICTS: In case of conflict between different Air Force standards or other any information herein this document, the more stringent requirement criteria and/or work-effort shall apply and take precedence.
6. COMPLETION DATE: 194 Calendar days from Notice to Proceed (NTP).