STATEMENT OF OBJECTIVES
1. GENERAL
Project Title: Replace Wind Screens at Chevron Park Pavilions and Beach House North Deck
Work Order No: 19017 and 19018
Date Written: 2 May 2017
Location: Chevron Park Pavilions, building 1636 and 1637; Beach House, building 236 North Deck
2. DESCRIPTION
A requirement exists to provide all material, labor, equipment and management necessary to install new windscreens at both picnic pavilions at Chevron Park and the lower north deck of the Beach House. Work includes complete removal and disposal of the existing windscreens, attachment structures and winch systems at Chevron Park.
3. DESIGN CRITERIA
The following items are required in the design criteria. Contractor shall submit in writing suggested design criteria not mentioned in this paragraph for review and approval by the requestor.
3.1. Windscreens at Chevron Park Pavilions.
a. Install pressure treated wood as attachment points for new windscreens to the pavilion.
b. Install windscreens made with Sunbrella bordering and 30 gauge window glass with a kidder welt in top edge, twist and turns on vertical edges and 1.25” pipe in turned over hem along bottom. All screens will have Sunbrella straps for holding them in place when rolled up.
3.2. Windscreens at Beach House North Deck
a. Install 10 windscreens ranging in size from 11.5’ to 9.4’ to 8.4’ x 8.5’ with Sunbrella bordering, 30 gauge window glass, trailor molding on top edge, twist and turns on vertical edges and 1.25” pipe in turned over hem along bottom.
All screens will have Sunbrella straps for holding them in place when rolled up.
4. SUBMITTAL APPROVAL OF MATERIAL AND EQUIPMENT
Contractor will submit a complete list of materials and equipment to be incorporated in this work, together with names and addresses of manufacturers and their catalog numbers and trade names. This submittal will also provide maintenance manuals, warranties and guarantees. Contractor will submit a visual sample of Sunbrella material colors for the requestor to choose from.
5. ADDITIONAL NOTES
a. All work shall be done in accordance with safety, electrical, and fire protection codes as well as current industry standards, publications and regulations.
b. Contractor shall be responsible for protecting existing surroundings.
c. Contractor shall verify all existing dimensions and conditions before proceeding with the project.
d. Contractor shall cleanup work area and remove trash and debris on a daily basis.
6. GOVERNMENT FURNISHED EQUIPMENT
7. PERFORMANCE PERIOD
Recommended performance period is 30 days upon award of the contract or as negotiated.