Answer -Attachment 1 Questions and Parts Specs AT.pdf
PDF 576 KB Posted
- Attached to
- OSP FY23 Federal contract opportunity
- Solicitation number
- FA2517-23-Q-0052
About this file
This document contains questions and answers regarding a request for quotation from the Department of the Air Force Space Command for outside plant fiber optic installation at Peterson Space Force Base in Colorado. The solicitation seeks a contractor to install fiber optic cable from Building 626 to Building 1038 using directional boring techniques. Acceptable part numbers and specifications are provided for fiber optic cable, maxcell material, and conduit. The contractor would be responsible for issue resolution during the construction period but not ongoing maintenance. Performance and payment bonds as well as a bid bond guarantee would be required to be submitted with responses. Spacers, warning tape, and concrete duct banks would be necessary elements of the installation. Only one conduit of a parallel run would require maxcell installation.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Answer-Questions from Site Visit 2 21 Jun 2023_Sb revised.pdf | ||
| Answer-Questions from Site Visit 2 21 Jun 2023_Sb revised.pdf | ||
| Attachment 2 PWS FOC from B626 to B1470 B1471 3 July 2023 Revision 1.pdf | ||
| OSP FY23 Amendment 1_CO signed.pdf | ||
| Attachment 5 OSP FY 23 Solicitation Site Visit.docx | DOCX document | |
| Attachment 3 PWS FOC from B122 to B1038_ 28 March 2023.docx | DOCX document | |
| Attachment 1 PWS FOC from B626 to B1038_ 28 March 2023.docx | DOCX document | |
| OSP FY23 Solicitation_CO Signed.pdf | ||
| Attachment 2 PWS FOC from B626 to B1470 and B1471_ 28 March 2023.docx | DOCX document | |
| Attachment 4 Wage Determination.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ for 21 CS OSP Fiber Optics – FA2517-23-Q-0052 Questions
1. Is the government expecting the contractor to perform service or maintenance after project completion, or is the below statement only in regards from the construction period. The reason for the question is on page.19/21 on the “Attachment 1 PWS FOC from B626 to B1038” there is a table showing “95% compliance; issues resolved within 24 hours; 5% of any remaining issues resolved within 12 hours”.
2. Confirm that 4” HDPE SDR 11.5 is acceptable for installation throughout the project. It appears that directional boring will be used on any new pathways for Attachment 1 PWS FOC from B626 to B1038.
3. Confirm that the following part number and specs are acceptable for this project; 036EU4-T4100D20.
4. Confirm that the part number (MXED64283) and specs below are acceptable for the maxcell. The trace wire will not be in any individual cell but sewn into the material.
a. Concurred.
5. Will a performance and payment bond be needed for this project. Also, would a bid bond guarantee be needed at time of submission?
6. Confirm that spacers will not be needed if boring is to be utilized.
7. Confirm that warning tape will not be applicable if boring is utilized.
8. Confirm that concrete duct bank would be needed if boring is utilized.
9. Confirm that only one conduit needs to have maxcell when another is run in parallel.