RFI 2

View the file

Other files for this federal contract opportunity

Other files attached to GRAVITY (ROLLER) SYSTEM, newest first.
File Type Posted
FBO_doc_-_Statement_of_Requirment _rev_1.pdf PDF
RFI_1.pdf PDF
Site_Visit_Minutes_-_Roller_System-signed.pdf PDF
FBO_doc_-_RFI_template.doc DOC document
FBO_doc_-_Statement_of_Requirment.pdf PDF
FBO_doc_-_provisions_ _clauses_attachment.pdf PDF
FBO_doc_-_conveyor_sketch.pdf PDF
FBO_doc_-_roller_system_pics.pptx PPTX presentation
FBO_doc_-_AT-OPSEC_REQUIREMENTS.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR INFORMATION

R E

Q U

E S

T O

R S

E C

T

IO

N

From:

Conveyor Handling

Date:

To: Contracting Officer

1. Solicitation Number:

F7R3116126AW01

2. Project title:

Roller System

3. Information Requested: (Include Specification Section and/or Drawing Number and Page if inquiring about a discrepancy)

1 - The existing supports appear to be in good condition. Can they be reused?

2 - Does the overall length of the conveyor (50’-10”) include the section outside the door?

3 - What is the length of that section?

4 - Do you want a fixed guide rail on the outside of both sides of each 4 lane set as shown below?

Attachments:

Date Response Required:

By:

Title:

Requestor's FAX Number:

Requestor's Telephone Number:

G O

V E

R N

M E

N T

R E

S P

O N

S E

To:

Date:

Response:

1. There is nothing that says they cannot be reused; however, any quality, performance, functionality, warranty impact, etc shall be the same as if providing new material supports.

2. The estimated measurement provided in solicitation statement of requirements does include; however, the exact measurement will be the responsibility of the contractor to verify (on-site); site visit provided opportunity for this.

3. 14’’ is estimated…however, on-site verification of field measurements will ultimately be the responsibility of the contractor

(part of reason for holding a site visit)

4. Only want one guide rail per set (which side can be determined/identified, once awardee has been determined).

This information is a clarification of the solicitation/contract and does not change the contract terms or conditions.

This information is a proposed change to the solicitation/contract. An amendment will be issued.