RFI_1.pdf

PDF 141 KB Posted

Attached to
GRAVITY (ROLLER) SYSTEM Federal contract opportunity
Solicitation number
F7R3116126AW01
Issued by
Department of the Army Ohio Army National Guard

About this file

RFI 1

View the file

Other files for this federal contract opportunity

Other files attached to GRAVITY (ROLLER) SYSTEM, newest first.
File Type Posted
FBO_doc_-_Statement_of_Requirment _rev_1.pdf PDF
RFI_2 _rev_1.pdf PDF
Site_Visit_Minutes_-_Roller_System-signed.pdf PDF
FBO_doc_-_Statement_of_Requirment.pdf PDF
FBO_doc_-_provisions_ _clauses_attachment.pdf PDF
FBO_doc_-_conveyor_sketch.pdf PDF
FBO_doc_-_RFI_template.doc DOC document
FBO_doc_-_roller_system_pics.pptx PPTX presentation
FBO_doc_-_AT-OPSEC_REQUIREMENTS.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR INFORMATION

R E

Q U

E S

T O

R S

E C

T

IO

N

From:

Date:

To: Contracting Officer

1. Solicitation Number:

F7R3116126AW01

2. Project title:

Roller System

3. Information Requested: (Include Specification Section and/or Drawing Number and Page if inquiring about a discrepancy)

Can you tell me the current roller centers? (spacing) It looks like they may be on 6" centers.

What is the axle hex size? 7/16", 11/16"

It appears that in lieu of the lift up gates you want fixed sections with a gap for the door. How thick is the door?

You ask for side guides but it appears that the loads often overhang the conveyor. What do you have in mind?

End stops. Can they be fixed on the inside of the building? Where the load enters or exits the truck do you want end stops as well?

Attachments:

Date Response Required:

By:

Title:

Requestor's FAX Number:

Requestor's Telephone Number:

G O

V E

R N

M E

N T

R E

S P

O N

S E

To:

Contracting office

Date:

Response:

-Rollers are on 6’’ centers

-Axle hex size is 11/16’’

-The sweep at the bottom of the door is 4’’

-Guides need to be attached to one side of frame sticking out approx. 6’’.

Guide needs to be a heavier gauge steel and connected in a manner that can withstand the weight of a 5000# pallet bumping into it. I would rather see the brackets attached with bolts as opposed to being welded on. Guides should be painted safety yellow as well.

-We will require two end stops. Both need to be located inside the building with the stop closest to the concrete wall being a fixed stop.

The stop at the other end closest to the door needs to be a mechanical stop that can be locked in the open and the closed position. The stop should be located approx. 1’ from the door.

This information is a clarification of the solicitation/contract and does not change the contract terms or conditions.

This information is a proposed change to the solicitation/contract. An amendment will be issued.

Contracting Officer:

File details come from the government source that posted it. Updated .