Statement of Work
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Clarifications to Solicitation Partitions.docx | DOCX document | |
| Solicitation partition walls.docx | DOCX document | |
| Executive Summary Sheet Partition Walls.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
FOR
BUILDING 2216 ACCORDION STYLE PARTITION
MCGUIRE AIR FORCE BASE, NEW JERSEY
DESCRIPTION OF SERVICES: Work shall include the delivery, assembly and installation of operable partition wall in building 2216, room 136, Joint Base McGuire-Dix-Lakehurst, NJ. All carton materials and additional debris will be required to be removed from the facility and property disposed of at the end of each work day, and completely removed from the base at the completion of the project at contractor's expense.
Some installation requires finish trim after the items are in place and this shall be the responsibility of the contractor. All tools required to perform the work entailed in this contract shall be provided by the contractor.
Provide and install operable partition wall in same location as the original accordion style partition. The dimensions for the new partition are approx. 15’ high by 36’ wide. Must have moderate to high sound control (yelling barely audible, normal conversation on either side inaudible), one passage door without threshold, center division, manual operation, heavy vinyl or equivalent wall covering.
The wall panels/track/roller system must be of sturdy construction (steel) to provide many years of maintenance free use.
The contractor shall be responsible for the repair or replacement of any items that were damaged during the shipment or items or facilities damaged by anyone in the contractor’s employ. The contractor shall be required to work Monday through Friday from 0730-1630 hours, excluding Federal holidays.
A site visit of the facility will be on 1000 hrs EST 1 Sept 2011. Vendor attendance is highly recommended.
SPECIAL REQUIREMENTS: The work site shall remain clean and clutter free since this area is an active employment site. All dumpsters or other containers for trash and debris shall be located in areas designated by the building manager and shall be subject to removal and / or relocation at the building manager’s request. These requirements shall not impact the performance period.
POINTS OF CONTACT: The Government will have a Point of Contact (POC) available during the performance of work to coordinate the placement of all items. In addition, the Government may provide lists and drawings indicating the items to be installed and the placement of those items. At the time the work begins, the Contractor shall designate a responsible employee to supervise work and to coordinate with the POC. The Contractor's supervisor shall be on site during the time any work is being performed by the Contractor's employees.
BASE ENTRY: The contractor shall obtain the necessary passes and /or identification for entry into McGuire Air Force Base and Fort Dix for all employees prior to commencement of work. The Government reserves the right to refuse to issue an entrance pass to any employee for any reason deemed valid by the Government. The contractor shall be required to provide the Security Forces with vehicle registration(s), proof(s) of insurance, driver license(s), and a picture ID(s) to obtain a pass for entry onto the base. The Pass and Registration building is located inside the twenty-four (24) hour gate right off of Wrightstown / Cookstown Rd.
SECURITY FORCE AND FIRE PROTECTION: The Base Security Police telephone number is 609-754-2001 and the Base Fire Department telephone number is 911 for reporting a fire. General information telephone number is 609-754-3326.
PERFORMANCE PERIOD: All work shall be completed within a thirty (30) calendar day period, excluding holidays.
INSPECTION / ACCEPTANCE OF PROJECT COMPLETION: Upon completion, the Government will conduct an inspection of all items and attachments installed. Contact the Quality Assurance Evaluator two (2) days prior to completion for a inspection.