This is a specifications document for the State of Oregon Department of Transportation (ODOT) Emerging Small Business (ESB) restricted request for competitive quotation (RFCQ) regarding the procurement and installation of new deicer tanks and distribution systems. The project encompasses the supply and installation of deicer storage and distribution infrastructure to support ODOT operations. The specifications detail the technical requirements, materials, construction standards, and performance criteria that qualified contractors must meet when submitting proposals for this capital improvement project.
The document establishes detailed engineering and construction specifications governing tank design, capacity, materials compatibility, installation procedures, safety standards, and system functionality for the deicer distribution infrastructure. This RFCQ is restricted exclusively to contractors certified by the State of Oregon as Emerging Small Businesses, creating a set-aside procurement opportunity for qualified small business enterprises. The specifications ensure that all submitted proposals meet standardized technical requirements and quality benchmarks, with successful contractors expected to comply with all applicable state and federal regulations, industry standards, and ODOT-specific requirements during both the installation and operational phases of the project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Exhibit 6 - Plans~9.pdf | ||
| 00017782_RFCQ.docx | DOCX document | |
| Attachment B - Sample Contract~16.docx | DOCX document | |
| Attachment A Form A-2_Bid Pricing Form~4.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Exhibit 5 - Specifications Oregon Department of Transportation Mosier Deicer Tanks & Distribution System
WORK LOCATION: ODOT Mosier Stockpile Site
SCOPE OF WORK: Work includes providing deicer tanks and installation of deicer distribution system.
Construction
General Requirements– Drawings are schematic and show minimum requirements that must be included. Electrical system and circuit design for equipment is by the contractor. Drawing shows minimum requirements that must be included in Contractors’ design and installation.
Tanks are to be Snyder Industries, Inc. 10,500 gallon polyethylene storage tank part No. 5330300 or approved equal. Each tank is to be molded in one piece seamless construction according to ASTM D 1998. Each tank shall be designed for liquid with a specific gravity of 1.9. Each tank shall be provided with a 24” diameter manway access port.
Each tank shall be supplied with two 3” diameter threaded fittings as near as possible to the base of the tank at the approximate locations as shown on the drawings. Fitting connections shall be liquid tight.
Tank installation shall be in accordance with the manufacturers installation instructions.
All electrical work shall be performed by a licensed electrician and shall be in accordance with the Oregon Electrical Specialty Code.
Distribution piping shall be installed in accordance with applicable code by licensed contractor.
Contractor shall furnish and install all components shown on the drawing as well as all components and materials required to provide a complete and functional deicer distribution system. All work shall be completed in a neat and workman like manner.
Contractor is responsible for applying for and obtaining electrical permit.
Conductors are to be copper wire type shall be THHN. Conduit shall be electrical metallic tubing. All wire runs are to be installed in rigid metal conduit.
Basis of design for pump panel is ABB model M1BP-2E18J6 NEMA rated combination pump panel starter. Enclosure shall be NEMA 3R.
Pump panel shall be mounted on a rigid stainless steel stand with base pf panel a minimum of 24 inches above finish floor, attached securely to structure.
Basis for design for pump is 4251-98-1750 special SS end suction centrifugal 3 x 2 pump 5 HP/1750 RPM 230V/1 TEFC, 27 FLA @ 230V/1, as supplied by Motion & Flow Control Products Inc.
Fabricate a four leg stand for pump and motor from stainless steel. Stand shall be rigid during pump operation and shall be bolted to concrete floor at each leg. Base of motor shall be 24 inches minimum above finish floor. Provide shop drawing for approval prior to fabrication.
Butterfly valves shall be Spears Manufacturing Company Model 722311-030 with locking lever handle or approved equal. Valves shall be PVC with type 316 stainless steel stem, bolts and bolt pattern conforming to ANSI B16.5 CL 150.
Wye stainer shall be Banjo Corp. Model LSM300 or approved equal, verify screen mesh size with ODOT.
Rigid piping and fitting for deicer shall be schedule 80 PVC.
Flexible piping shall be Kanaflex Corp flexible pipe in cold weather, black UV resistant and suitable for suction. Conect to barb type fittings with suitable stainless steel clamps.
Attach rigid piping securely to concrete with stainless steel UNI STRUT type channel and clamps. Piping shall be supported rigidly.
All metal components including mounting channels, fasteners, clamps, fittings, etc. shall be stainless steel. No mild steel shall be used.
Connectors for truck filling shall be Banjo type cam lever connectors.
Mount truck connectors and valves securely in a horizontal position with Uni Strut type clamps bolted to concrete structure.
All piping and fittings must be watertight. Contractor shall supply clean water to test system and demonstrate correct operation to the satisfaction of ODOT. Tanks shall be filled with 2500 gallons of water for testing.
Reference plans for structure dimensions image1.png