Exhibit 5 - Specifications~3.docx

DOCX document 37 KB Posted

Attached to
I-84 and Biggs Patch Paving
Solicitation number
S-73000-00017779
Issued by
Oregon

About this file

This document is Exhibit 5 - Special Provisions for the I-84 and Biggs Patch Paving project managed by the Oregon Department of Transportation (ODOT). The project encompasses cold plane pavement removal and hot mix asphalt concrete (HMAC) inlay at four separate locations on Interstate 84 between mile points 114 and 183.9, plus work in Biggs Junction on Biggs Rufus Highway. All work includes traffic control, temporary pavement markers, and permanent yellow lane line pavement markings. The paving work on I-84 is limited to the travel way between existing fog and lane line striping, with existing striping to remain in place. Work in Biggs Junction is performed within fog lines with fog line striping remaining. The contractor must attend a preconstruction conference with the Project Manager and submit a detailed project schedule within 10 working days of receiving the Notice to Proceed. Work is governed by the 2024 Oregon Standard Specifications for Construction, as modified by these special provisions. Single lane closures on I-84 are permitted Monday through Thursday at all times, while closures on Biggs Rufus Highway are limited to nightly periods (8 PM to 6 AM) Monday through Thursday mornings with flagger control. The contractor must maintain business access and provide flagging at business driveways and intersections as needed.

Payment for all work is included in the bid schedule line items and constitutes full compensation for materials, equipment, labor, and incidentals. No retainage is held on work performed. The contractor must provide a copy of the job mix formula (JMF) to the Project Manager before paving begins and utilize Level 4, ¾-inch dense graded asphalt concrete pavement with lime treatment or approved alternative. Paving specifications require PG64-28 asphalt cement and placement of wearing course mixture in a single 2-inch lift at nominal compacted thickness. Load restrictions on bridges are limited to 65,000 pounds per 1,000 square feet of surface area or 25,000 pounds per 100 square feet for long-term material storage, whichever is less, with a maximum total of 200,000 pounds per bridge span. The contractor must notify the Oregon Utility Notification Center at 811 prior to performing work in the vicinity of utilities. Traffic control requirements include specific signing, portable changeable message signs (PCMS) on paving equipment, radar speed trailers positioned 1,000 feet beyond lane closure tapers, and adherence to Standard Drawings TM800, TM820, TM821, TM822, TM854, TM860, and TM880.

View the file

Other files

File Type Posted
Exhibit 6 - Site Photo.pdf PDF
00017779_Invitation to Bid.docx DOCX document
Attachment B - Sample Contract~15.docx DOCX document
Attachment A Form A-2_Bid Pricing Form~3.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Exhibit 5 – Special Provisions

PROJECT NAME: I-84 and Biggs Patch Paving

SCOPE OF WORK: On I-84 work includes cold plane pavement removal and HMAC inlay at multiple separate locations as identified in the table below and all traffic control. Paving to be within existing fog line and lane line striping, existing line striping to remain.

In Biggs Junction work includes cold plane pavement removal and HMAC inlay as shown on plan and as directed by ODOT on site. Paving to be within fog lines, fog line striping to remain. Work also includes performing all traffic control, temporary pavement markers and permanent yellow lane line pavement markings to be replaced to match existing layout.

WORK LOCATION: The work is patch paving of four separate locations on I-84 from MP 114 to MP 183.9 and in Biggs Junction on Biggs Rufus Highway.

APPLICABLE SPECIFICATIONS: The Specifications which are applicable to the work on this project are the 2024 Oregon Standard Specifications for Construction (“Standard Specifications”), which are by this reference incorporated herein and the Special Provisions. The Standard Specifications include detailed technical specifications in Sections 00200 and beyond that apply to this ITB and any resulting Contract. Some sections of the technical specifications may be identified and modified in the Plans and Specifications. Sections of the technical specifications not identified in the Plans and Specifications remain applicable to the Contract according to their original terms.

Sections in Part 00100 of the Standard Specifications (General Conditions) are not applicable to the Contract unless they are specifically identified in the Plans and Specifications as being applicable. However, if a Part 00100 section that has been identified as being applicable references another section in Part 00100, or a technical specification (Parts 00200 and beyond) references a section from Part 00100, that section from Part 00100 applies to the Contract for purposes of supporting and giving full effect to the specification that referenced it. Bidders can access the Standard Specifications online at:

http://www.oregon.gov/ODOT/Business/Pages/Standard_Specifications.aspx

COOPERATION WITH UTILITIES: This project is located within the Oregon Utility Notification Center area, which is a utilities notification system for notifying owners of utilities about work being performed in the vicinity of their facilities. The contractor shall notify owners of Utilities prior to the performance of work in the vicinity of their Utilities. The utilities notification system telephone number is 811 (or use the old number which is 1-800-332-2344).

PAYMENT: Payment for all work under this contract is to be included in the bid items contained in the Bid Schedule. Payment constitutes full compensation to the Contractor for furnishing all Materials, Equipment, labor and incidentals necessary to complete the work as specified. There will be no separate payment for items not listed, as that work will be included in payment made for the items listed in the Bid Schedule.

PAYMENT TO CONTRACTOR: The Contractor shall be paid upon completion of contract work. A bill must be submitted to the Project Manager for payment processing. There shall be no retainage for work performed under this contract.

PRECONSTRUCTION CONFERENCE, SCHEDULE AND LIMITATIONS OF OPERATIONS: The Contractor shall meet with the Project Manager for a preconstruction conference at a mutually agreed upon time. Work shall commence within 10 working days of this meeting providing the Notice to Proceed has been received. At the preconstruction conference, submit a project schedule to plan, coordinate and control the progress of construction and traffic control installations. The project schedules will take into account the orderly, timely, and efficient prosecution of the work in sufficient detail to enable both the Contractor and the Project Manager to plan, coordinate, appraise, document, and control their respective contract responsibilities. The predicted Completion date(s) for the project schedule shall be within the specified contract time.

SECTION 00210 - MOBILIZATION

Comply with Section 00210 of the Standard Specifications.

SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC

Comply with Section 00220 of the Standard Specifications modified as follows:

00220.02(a) General Requirements - Add the following bullets to the end of the bullet list:

· When paving operations create an abrupt edge, protect traffic by installing signing according to the "Divided Highway or Freeway One Lane Closure" detail shown on the Standard Drawings.

00220.40(e)(1) Closed Lanes - Replace this subsection, except for the subsection number and title, with the following:

Traffic Lanes may be closed on the Columbia River Highway (I84) when allowed, shown, or directed during the following periods of time except as specified in 00220.40(e)(2):

Single Lane Closures - One Traffic Lane in each direction on the Columbia River Highway (I84) may be closed during the following times:

Daily, Monday through Thursday, at all times.

One Traffic Lane on Celilo – Wasco Spur ( Biggs Rufus Hwy ) may be closed with flagger control during the following times:

Nightly, Monday night through Thursday morning, 8pm to 6am. Paving must be staged to always allow access in and out of all businesses. Business driveways must be flagged when within the work zone. Provide intersection flagging as needed.

Add the following subsection:

00220.41 Bridge Work - Before starting any grading or Pavement removal at Bridge ends or removal of Pavement from Bridge decks, arrange so that all Equipment, labor, and Materials required to complete the Pavement replacement Work and Bridge deck waterproofing Work are on hand or are guaranteed to be delivered. Once grading and Pavement removal begins, vigorously prosecute and complete this Work. Complete paving and membrane waterproofing Work in the shortest possible time.

Temporarily taper or bevel longitudinal and transverse grade changes or drop‑offs resulting from grading and Pavement removal and membrane waterproofing Work with asphalt concrete mixture to provide a smooth and safe transition. Construct tapers according to 00620.40.

Add the following subsection:

00220.45 Load Restrictions on Bridges - Limit the combined weight of construction vehicles, Equipment, and daily Material usage to 65,000 pounds for every 1,000 square feet of surface area plus the weight of long term storage of Materials to 25,000 pounds for every 100 square feet of surface area of the Bridge or a total of 200,000 pounds for each span of the Bridge, whichever is less.

The Contractor may request alternate loadings by submitting, 30 Calendar Days before proposed loadings, stamped loading calculations and data according to 00150.35.

SECTION 00221 – COMMON PROVISIONS FOR WORK ZONE TRAFFIC CONTROL

Comply with Section 00221 of the Standard Specifications modified as follows:

00221.02 General Requirements - Add the following to end of this subsection:

Contractor shall perform the work zone traffic control according to Standard Drawings TM800, TM820, TM821, TM822, TM854, TM860, and TM880.

SECTION 00222 – TEMPORARY TRAFFIC CONTROL SIGNS

Comply with Section 00222 of the Standard Specifications modified as follows:

00222.15(b) Portable Changeable Message Signs - Add the following paragraph to the end of this subsection:

For PCMS mounted on rollers, use 2-line PCMS from the QPL.

00222.40(e) Temporary Sign Placement ‑ Add the following to the end of the bullet list:

Install a 72 by 24-inch "CONSTRUCTION VEHICLE DO NOT FOLLOW" (CW23‑14) sign on rigid substrate on the back of all Material or Equipment delivery vehicles.

During paving and bridge work operations on the Columbia River Highway, install temporary signing and other required TCD as shown. Install temporary speed zone signing according to and as shown in the Temporary Speed Zone Order.

00222.45(b) Portable Changeable Message Signs - Add the following bullet(s) to the end of this subsection:

During paving operations, provide one 2-line PCMS on the finish roller. Display the following messages on the PCMS:

Panel 1Panel 2
WORKERSSLOW TO
IN ROADXX MPH

During paving operations, provide one 2-line PCMS on the intermediate roller. Display the following messages on the PCMS:

Panel 1Panel 2
SLOW FORWORKERS
WORKERSIN ROAD

00222.45(c) Radar Speed Trailers - Add the following bullet(s) to the end of the bullet list:

· Place a radar speed trailer approximately 1000 feet beyond the end of the lane closure taper, as shown on Standard Drawing TM880

· Install a 30 by 36-inch “SPEED LIMIT XX” (R2‑1) sign below the trailer display panel. The “XX” value is the legal speed limit as determined by a Speed Zone Order signed by the State Traffic Engineer.

· When the paving machine reaches a location that is approximately 1/2 mile beyond the start of the work shift paving operations, place a second radar speed trailer as shown on Standard Drawing TM880. Install a 36 by 36-inch “ROAD WORK XX MPH” (CW20‑1a) sign above or below the trailer display panel. Use a “XX” value equal to 15 mph below the current posted regulatory speed. If a speed is posted for a temporary regulatory speed reduction, that speed is the current posted regulatory speed.

SECTION 00223 - WORK ZONE TRAFFIC CONTROL LABOR AND VEHICLES

Comply with Section 00223 of the Standard Specifications.

SECTION 00224 - TEMPORARY TRAFFIC CHANNELIZING DEVICES

Comply with Section 00224 of the Standard Specifications modified as follows:

00224.46 Pavement Edge Delineation - Replace the paragraph that begins “Place tubular or conical markers…” with the following paragraph:

Place tubular or conical markers to delineate the edge of Pavement immediately after construction Work or paving operations create an abrupt or sloped edge drop-off greater than 1 inch in height along the right hand or left hand Shoulder.

SECTION 00225 – TEMPORARY PAVEMENT MARKING

Comply with Section 00225 of the Standard Specifications.

SECTION 00305 - CONSTRUCTION SURVEY WORK

Comply with Section 00305 of the Standard Specifications.

SECTION 00620 - COLD PLANE PAVEMENT REMOVAL

Comply with Section 00620 of the Standard Specifications:

SECTION 00730 - EMULSIFIED ASPHALT TACK COAT

Comply with Section 00730 of the Standard Specifications.

SECTION 00740 – COMMERCIAL ASPHALT CONCRETE PAVEMENT (CACP)

Comply with Section 00740 of the Standards Specifications modified as follows:

00740.10 Materials – Replace the last sentence of this subsection with the following:

Provide a copy of the JMF to the Project Manager before paving. The contractor shall utilize Level 4, ½ Inch Dense Graded, lime treated ACP or alternative treatment as outlined in sections 00745.11(d) & (e).

00740.12 Asphalt Cement – Replace the first sentence of the first paragraph with the following:

Use PG64-28 unless otherwise specified in the contract documents or approved.

Add the following subsection:

00740.20 General – Provide Pavers according to Section 00744.23 and Compactors according to Section 00744.24.

00740.44 Placing Asphalt Concrete – Replace the first paragraph of this subsection with the following:

Place the Commercial Asphalt Concrete Pavement (CACP) according to Sections 00744.40, 00744.41, 00744.42, 00744.43, 00744.44, 00744.45, and 00744.60.

Add the following to the end of this subsection:

Place the wearing course mixture in a single lift at a nominal compacted thickness of 2 inches as indicated in tables below and as marked on site. Paving on I 84 is travel way only between existing fog and lane line striping.

I 84 Lane
Beginning Mile Point
Segment Length
Depth
West bound slow lane
MP 114.6
150 feet
2 inches
West bound slow lane
MP 183.8
150 feet
2 inches
East bound slow lane
MP 138.2
100 feet
2 inches
East bound slow lane
MP 151.4
100 feet
2 inches

Rev 1/4/2019