Exhibit 1 - Special Provision for Maintaining Traffic.pdf

PDF 105 KB Posted

Attached to
Milling & HMA resurfacing, M-71 in Shiawassee County
Solicitation number
RFP 591 260000002304 1
Issued by
Michigan

About this file

This is a Special Provision for Maintaining Traffic issued by the Michigan Department of Transportation (MDOT) for milling and Hot Mix Asphalt (HMA) resurfacing work on M-71 in the city of Corunna, Shiawassee County. The provision establishes comprehensive traffic management requirements for contractors performing work on M-71 from approximately 0.5 miles north and south of Shiawassee Street to 1 mile south of Dutcher Street. The Construction Influence Area extends to intersecting roads and ramps adjacent to the work zone for approximately 0.25 miles in advance of the work zone, including Comstock Street. Contractors must maintain a minimum of one lane of traffic in each direction at all times on M-71 and all intersecting roads, with a maximum closure length of one mile unless Engineer-approved. Lane closures are restricted during the Labor Day holiday period (September 4-8, 2026) and must follow specified time windows tied to sunrise and sunset as defined by the National Oceanic and Atmospheric Administration. No more than one closure is permitted in each direction of travel simultaneously, and traffic switch operations are exempt from lane rental assessments for up to 8 hours per switch.

Contractors are required to develop and submit a Type A Internal Traffic Control Plan (ITCP) for Engineer approval at the preconstruction meeting, with a seven-calendar-day review window, and must submit Lane Closure Notification/Request Forms seven calendar days in advance of any lane closure. All traffic control devices must comply with the Michigan Manual on Uniform Traffic Control Devices and ATSSA quality guidelines. Traffic regulators must maintain two-way traffic using approved sequences covering a maximum of 0.5 miles, with intermediate traffic regulators positioned at intersections and commercial driveways. Contractors must resurface all HMA milled areas the same day as milling operations and maintain all pedestrian and non-motorized facilities in accordance with Americans with Disability Act requirements and Public Rights-of-Way Accessibility Guidelines. No additional payment is provided for transporting traffic control items, providing vehicles and staff for changes, or removing closures from the roadway. All costs associated with obtaining an approved ITCP, deploying traffic control devices, coordinating with emergency services and local agencies, and conducting required traffic control operations are considered included in the pay items for minor traffic devices.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

V4.0

MICHIGAN

DEPARTMENT OF TRANSPORTATION

SPECIAL PROVISION

FOR

MAINTAINING TRAFFIC

DAV:HI 1 of 6 2/27/2026

a. Description. This special provision consists of requirements and restrictions to maintain traffic for milling and HMA resurfacing on M-71 in the city of Corunna, Shiawassee County.

b. General. Maintain traffic throughout the project in accordance with the standard specifications, typicals, and supplemental specifications.

c. Construction Influence Area (CIA). The CIA includes the right-of-way of the following roadways, within the approximate limits described below:

1. On M-71 from approximately 1/2 mile north and south of Shiawassee St. to 1 mile south of Dutcher St.

2. In addition, the CIA includes the right-of-way of any designated detour route or alternate route, intersecting roads and ramps adjacent to the work zone for a distance of approximately 1/4 mile in advance of the work zone or as far as the construction or detour signing extends. The roads include but are not limited to Comstock St.

d. Traffic Restrictions. Maintain traffic in accordance with the Maintaining Traffic Typicals contained herein, except as noted below. Changes or adjustments to the Maintaining Traffic Typicals may be necessary to fit field conditions, subject to approval of the Engineer or as determined by the Engineer.

1. Utilize the following Maintaining Traffic Typicals:

A. 100-GEN-KEY Typical Numbering Key

B. 101-GEN-SPACING-CHARTS "B", "D", and "L" Tables, Channelizing Device

Spacing, Sign Border Key, and Roll-Ahead Spacing

C. 110-TR-NFW-2L Lane Closure Utilizing Traffic Regulators on a 2-Lane

Undivided Roadway

D. 130-CLT-1(CLT) Center Lane Closure on a Multi-Lane Undivided Roadway

E. 137-CLT-SHIFT-0LC Lane Shift on a 3-Lane Undivided Roadway

2. Do not deliver material, or close lanes (other than approved stage closures) during the holiday periods as defined in Table 1 https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=67f64e52-8d1e-43fa-80c6-67291cc005a2&fileName=100-GEN-KEY.pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=6dfdabdf-c842-4cf5-8187-5f7d8565fd86&fileName=101-GEN-SPACING-CHARTS.pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=5a12ba74-ea80-4f60-ac3b-4881792081a1&fileName=110-TR-NFW-2L.pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=bbf5a220-0873-41cc-b0dc-f0ba609ccc3f&fileName=130-CLT-1(CLT).pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=4ea149ab-b129-4729-84f1-8cc341c8db46&fileName=137-CLT-SHIFT-0LC.pdf

DAV:HI 2 of 7 02/27/26

Table 1: 2026 Holiday Periods

Holiday Start Date and Time End Date and Time

Labor Day 3:00 pm Friday, September 4, 2026 6:00 am Tuesday, September 8, 2026

3. Perform work and lane closures within the allowable time frames as shown in Table 2, unless otherwise approved by the Engineer. Traffic switch operations on freeways may take place within the allowable times listed below in the traffic restriction tables and/or as otherwise approved by the Engineer. Additional lane, ramp, and/or roadway closures and shifts may be implemented during maintaining traffic stage and traffic switch operations with prior Engineer approval.

4. Traffic switch operations are exempt from lane rental assessments or liquidated damage assessments for 8 hours for each traffic switch. Perform traffic switch operations within the allowable “traffic restriction tables” as shown below.

A. A traffic switch is defined as a change in the existing (original or staged) traffic configuration which requires multiple (more than one) lane lines and/or edge lines to be relocated in a new location and the old lines to be removed either between construction stages, or maintenance of traffic stages.

Table 2: M-71 Traffic Restrictions

Closure Type Start Time

End Time

M Tu W Th F Sa Su

SB M-71 130-CLT-

1(CLT)

☼ ▼ 3 3 3 3 3 3 3

SB M-71 110-TR-

NFW-2L

☼ ▼ 3 3 3 3 3 3 3

NB M-71 130-CLT-

1(CLT)

☼ ▼ 3 3 3 3 3 3 3

NB M-71 110-TR-

NFW-2L

☼ ▼ 3 3 3 3 3 3 3

NB and SB M-71

137-CLT-SHIFT-0LC

☼ ▼ 3 3 3 3 3 3 3

☼ = half hour before sunrise as defined by the National Oceanic and Atmospheric Administration (NOAA) ▼ = half hour after sunset as defined by NOAA # = The number of times closures can take place during the project timeframe.

5. Maintain a minimum of one lane of traffic in each direction at all times on M-71 and all intersecting roads.

6. Maintain a minimum of one lane of traffic in each direction at all times on all signalized side roads.

7. No more than one closure will be allowed in each direction of travel at the same time.

A. The maximum closure length is one mile unless otherwise approved by the

Engineer.

https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=bbf5a220-0873-41cc-b0dc-f0ba609ccc3f&fileName=130-CLT-1(CLT).pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=bbf5a220-0873-41cc-b0dc-f0ba609ccc3f&fileName=130-CLT-1(CLT).pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=5a12ba74-ea80-4f60-ac3b-4881792081a1&fileName=110-TR-NFW-2L.pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=5a12ba74-ea80-4f60-ac3b-4881792081a1&fileName=110-TR-NFW-2L.pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=bbf5a220-0873-41cc-b0dc-f0ba609ccc3f&fileName=130-CLT-1(CLT).pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=bbf5a220-0873-41cc-b0dc-f0ba609ccc3f&fileName=130-CLT-1(CLT).pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=5a12ba74-ea80-4f60-ac3b-4881792081a1&fileName=110-TR-NFW-2L.pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=5a12ba74-ea80-4f60-ac3b-4881792081a1&fileName=110-TR-NFW-2L.pdf https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fmdotjboss.state.mi.us%2FTSSD%2FgetTSDocument.htm%3FdocGuid%3D4ea149ab-b129-4729-84f1-8cc341c8db46%26fileName%3D137-CLT-SHIFT-0LC.pdf&data=05%7C02%7CInmanH%40michigan.gov%7C7713428c0dea4c9e6d2e08ded7ab21cf%7Cd5fb7087377742ad966a892ef47225d1%7C0%7C0%7C639185327510547187%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=NbSvje91NCt9lpjcBS6tTks9TFqw1D2SHIXrJMqHnrM%3D&reserved=0 https://gml.noaa.gov/grad/solcalc/ https://gml.noaa.gov/grad/solcalc/

DAV:HI 3 of 7 02/27/26

8. Close any dedicated lanes (exit, ramp, turn, etc.) prior to the location under construction.

9. When a lane is closed, place channelizing devices at cross streets and major drives to form a radius that clearly defines the approaches to the through and turning traffic.

10. Failure to meet the traffic restrictions described herein will result in the assessment of liquidated damages for other Department costs per subsection 108.10.C.2 of the Standard Specifications for Construction.

11. Restrict access to M-71 from side roads for short durations at specific locations as the

Engineer directs or approves. Where an intersection is closed or partially closed, allow the adjacent intersections one block to the north and south to remain open to traffic, unless otherwise approved by the Engineer.

12. Maintain access to all driveways as directed by the Engineer unless prior agreements are made with the respective property owners. The cost of constructing driveways part width will not be paid for separately but will be considered included in the cost of other driveway pay items.

e. Traffic General.

1. For any lane open to traffic, provide a minimum lane width of 11 feet with 2 feet of shy distance on both sides unless otherwise directed by the Engineer.

2. Do not close lanes or utilize traffic regulation sequences where work can be accomplished with a shoulder closure. Do not occupy any part of the active traffic lane with personnel or equipment when utilizing a shoulder closure. Place lane closures and traffic regulation operations only in areas as directed by the Engineer.

3. Prior to shifting traffic onto shoulders or opening any lanes/shoulders and/or ramps, remove, by sweeping all accumulated debris that has collected within the shoulder and/or within the closed lane/shoulder.

4. A speed reduction will not be used.

5. Develop and submit to the Engineer an Internal Traffic Control Plan (ITCP) per subsection 104.11.B of the Standard Specifications for Construction. The requirements listed herein are the requirements for a Type A ITCP. Submit the Type A ITCP at the preconstruction meeting. The Engineer will have 7 calendar days to review the ITCP for approval or provide comments for revisions required to obtain approval. Include in the ITCP, at a minimum, the proposed ingress/egress locations for construction equipment and vehicles, traffic control devices that will be utilized to warn the motoring public of ingress/egress locations, and measures that will be taken to ensure compliance with the ITCP. Ensure that the ITCP minimizes conflicts between construction vehicles and motorists and maintains overall safety and mobility within the work zone. No work may begin prior to approval of the ITCP. Additional time required to obtain an approved ITCP will not be cause for delay or impact claims. All costs associated with obtaining an approved ITCP, providing and executing all parts of the approved ITCP including required traffic control devices, or resolving an incomplete or unacceptable ITCP will be borne by the Contractor.

https://www.michigan.gov/mdot/-/media/Project/Websites/MDOT/Business/Construction/Standard-Specifications-Construction/2020-Standard-Specifications-Construction.pdf https://www.michigan.gov/mdot/-/media/Project/Websites/MDOT/Business/Construction/Standard-Specifications-Construction/2020-Standard-Specifications-Construction.pdf https://www.michigan.gov/mdot/-/media/Project/Websites/MDOT/Business/Construction/Standard-Specifications-Construction/2020-Standard-Specifications-Construction.pdf

DAV:HI 4 of 7 02/27/26

6. Upon approval of the ITCP, complete and submit the “Lane Closure Notification/Request Form” [see MDOT LANE CLOSURE NOTIFICATION/REQUEST FORM (state.mi.us)] to the Engineer for approval prior to the actual closure date. Submit the lane closure request 7 calendar days in advance of the lane closure for approval. This includes all shifts/shoulder/lane/ramp closures as stated per the proposal or any new lane closure requests submitted by the Contractor. The Engineer will have 4 calendar days to review the lane closure request for approval or provide comments for revisions required to obtain approval. Do not implement a lane closure prior to approval by the Engineer. In addition, notify the Engineer when the lane closure is removed or cancelled.

7. Protect the work area at the end of each day. Close all open access points on the project to traffic with Type III barricades or other devices approved by the Engineer.

8. The Engineer will be responsible for notifying emergency services, transit agencies, law enforcement and schools prior to any lane closures, detours or major traffic shifts. In addition, the Contractor will be responsible for working with and complying with any coordination that is necessary with the Department and emergency services, transit agencies, law enforcement and schools. All costs associated with these coordination efforts will be considered included in the pay item “Minor Traf Devices”.

9. Obtain all necessary permits from local governments within areas of local jurisdiction, including noise/dust ordinance waivers when required, prior to placing construction signing on local roads.

10. Remove all temporary traffic control devices from MDOT right-of-way during any shut down periods unless needed for directly maintaining or channelizing traffic. No additional payment will be made for removal and/or redeployment of these devices except for in the case of an approved extension of time.

11. Cover or remove construction signing that refers to work zone speed when work at a location is planned to be inactive for a period greater than 2 days, unless otherwise specified on the plans or as directed by the Engineer.

12. Once work is initiated that includes any lane restrictions, that work must be continued daily until completed. A lack of work activity for more than 3 days will require the removal of lane closures at no expense to the Department.

f. Traffic Regulator Control.

1. Maintain two-way traffic at all times on M-71 from Parmenter Rd. to Dutcher St. using traffic regulator control. A traffic regulator sequence is allowed to cover a maximum closure length of 1/2 mile. Place the arrow panel, signs and channelizing taper for the traffic regulator operation at locations approved by the Engineer for adequate visibility by oncoming traffic.

2. Do not utilize more than (1) traffic regulator operation(s) at one time on M-71 https://mdotjboss.state.mi.us/webforms/GetDocument.htm?fileName=0561.pdf https://mdotjboss.state.mi.us/webforms/GetDocument.htm?fileName=0561.pdf

DAV:HI 5 of 7 02/27/26

3. Crossroads should remain open to traffic at all times. Use intermediate traffic regulators at each intersection approach and commercial driveways within the closure limits, as directed by the Engineer. Use traffic regulator control as directed by the Engineer for cross street traffic while paving through intersections.

4. Follow the Michigan Traffic Regulating Instruction Manual for operations at signalized intersections. Contact the MDOT region electrician or applicable maintaining agency prior to work on traffic signals. Only the MDOT region electrician or applicable maintaining agency may make changes to the traffic signal controllers.

g. Pedestrian or Non-Motorized Facilities.

1. Maintain all facilities in accordance with The Americans with Disability Act (ADA) requirements and the Public Rights-of Way Accessibility Guidelines (PROWAG). Provide facilities equivalent to or better than the route a person would have encountered prior to construction activities.

2. Submit an “ADA Work Plan” for sidewalk and ADA ramp construction prior to any sidewalk ramp closures or removals. The work plan must address pedestrian access and detours. Plan will allow a ramp closure up to (96) hours. The Engineer will have 7 calendar days to review the plan for approval or provide comments for revisions required to obtain approval. Do not proceed with the work until the Engineer has approved the plan.

3. Close and detour any sidewalk ramps and crosswalk areas to pedestrian traffic that are impacted by the work. Cover pedestrian signal heads when the crosswalk or ramp is affected.

4. Always keep sidewalk areas clear of any equipment or materials when the sidewalks are open to pedestrian traffic. When open to pedestrian traffic, maintain a 4 foot clear path on all sidewalks.

h. Hot Mix Asphalt (HMA) Work.

1. Resurface all HMA milled areas the same day as the HMA cold milling operation.

2. No traffic is allowed on the HMA milled surface, unless directed by the Engineer.

i. Traffic Control Devices. Ensure all traffic control devices are in accordance with the

MMUTCD and must meet the “acceptable” criteria as defined in the ATSSA publication entitled “Quality Guidelines for Temporary Traffic Control Devices and Features” at the time of initial deployment and after each major stage change.

1. During non-working periods, place applicable advance signs and channelizing devices at specific locations, as directed by the Engineer, at no additional cost to the Department.

2. Notify the Engineer 24 hours in advance of when traffic control devices are being delivered to the project site, to allow for initial inspection of devices to take place.

3. Remove from the project site all traffic control devices (including detour signing) no longer needed for a particular operation and equipment for construction within 10 calendar days of reopening the shoulder/lane/roadway.

https://www.michigan.gov/mdot/-/media/Project/Websites/MDOT/Business/Work-Zone-Mobility/MDOT-Traffic-Regulator-Instruction-Manual.pdf?rev=4e80cb12722b4143b0edb53bcab115e3 https://mdotjboss.state.mi.us/TSSD/getCategoryDocuments.htm?categoryPrjNumbers=1403854,1403855&category=MMUTCD

DAV:HI 6 of 7 02/27/26

4. Channelizing Devices.

A. Ensure all devices have sufficient ballast to prevent moving or tipping. If moving or tipping occurs, place additional ballast, as directed by the Engineer, at no additional cost to the Department. No more than two ballasts are allowed on each channelizing device.

B. Do not use caution tape on channelizing devices for traffic control and/or pedestrian traffic control on this project.

5. Temporary Signs.

A. Additional W20-1 (ROAD WORK AHEAD) signs are included in the quantities to be placed on all intersecting or adjacent roads where construction activities may be encountered.

6. Portable Changeable Message Signs (PCMS’s). Use PCMS’s to warn traffic of upcoming and changing traffic control during the life of the project. Obtain approval from the Engineer for all sign locations.

A. Install PCMS’s and make them operational a minimum of 7 calendar days prior to the start of work, unless otherwise directed by the Engineer. Messages displayed on the PCMS’s must conform to MDOT’s policy on PCMS’s. Notify the Engineer if displaying a different message than those listed below for the project.

B. Do not leave PCMS’s with a blank screen within the clear zone of any roadway at any time. Remove the PCMS or display flashing dots in each corner of the screen when there is no message to display. Update the PCMS messages at the end of each work period to reflect current traffic lane restrictions.

j. Temporary Pavement Markings.

1. Remove conflicting pavement markings, pavement markings in taper/transition areas and other markings as directed by the Engineer, for operations occupying a location longer than 3 days. Durable markings in these areas should be covered rather than be removed.

2. Quantities for temporary tape to be placed during paving operations are based on the

MDOT PAVE 900 Series Standard Plans [all Pavement Marking Standards may be found at MDOT - Transportation Standards and Special Details (state.mi.us)].

3. When Type R or NR tape is used, ensure that all temporary pavement markings adhere to the pavement surface until permanent markings are installed.

4. Complete temporary pavement markings in each stage prior to shifting traffic as directed by the Engineer.

5. Replace all existing pavement markings that are removed for traffic control or obliterated during construction.

6. Delineate the edge line using 42” channelizing devices spaced at 50’.

https://mdotjboss.state.mi.us/TSSD/getSubCategoryDocuments.htm?prjNumber=2668206&category=Pavement%20Markings&subCategory=Standards%20Apr%202024%20let%20and%20later&subCategoryIndex=subcat8Pavement%20Markings&categoryPrjNumbers=1403856,1403857,1403858,2677852,2668204,1403859,2677853,1403860,2668206

DAV:HI 7 of 7 02/27/26

7. Place permanent pavement markings within 1 week of the completion of over-band crack sealing on each section of roadway.

v. Measurement and Payment. Payment will be in accordance with the standard specifications unless otherwise specified. No additional payment will be made for the following activities:

1. Transporting traffic control items from site to site.

2. Providing sufficient vehicles and staff to make changes as-needed on site during work.

3. Providing sufficient vehicles and staff to remove closures from the roadway.