ESBD_545166_1785800787830_2_VOL1_1B Specs-v2 Updated.pdf

PDF 32 MB Posted

Attached to
RFP 26-1392 EWCRWS Infrastructure and Expansion - Trinity Well and Phase 1D Project
Solicitation number
26-1392
Issued by
Williamson County, Texas

About this file

This is a Request for Proposal (RFP) and specifications document issued by the Brazos River Authority for the East Williamson County Regional Water System (EWCRWS) Infrastructure and Expansion project, specifically the Trinity Well and Phase 1D Projects. The RFP (No. 26-1392) was issued in July 2026 and prepared by CDM Smith, Inc., a Texas-registered engineering firm. The project encompasses comprehensive water infrastructure development including Trinity Well construction and Phase 1D expansion work, with detailed technical specifications across 46 divisions covering general conditions, general requirements, concrete work, structural elements, mechanical systems, electrical systems, process interconnections, and water treatment equipment. The document establishes the contract framework, defining the scope of work, technical standards, and procurement procedures for bidders. The specifications are organized by division with notations indicating which sections apply to Phase 1B (Trinity Well) versus Phase 1D projects, with multiple professional engineers certifying their respective technical sections.

The specifications document establishes standard contract conditions using EJCDC (Engineers Joint Contract Documents Committee) format from 1996, defining payment procedures, insurance requirements, bonding obligations, and dispute resolution mechanisms. Performance and payment bonds equal to the full contract price are required, with bonds remaining effective for at least one year after final payment. Property insurance must cover the full replacement cost of the work, with OWNER responsible for purchasing Builder's Risk coverage. The document requires CONTRACTOR to obtain liability insurance protecting against claims for bodily injury, property damage, and worker compensation, with OWNER, ENGINEER, and other identified parties listed as additional insureds. Contract conditions specify procedures for shop drawing submissions, progress payments based on accepted schedules of values, substantial completion requirements, and correction periods for defective work. The contract includes provisions for differing subsurface conditions, underground facility coordination, and equitable price adjustments where conditions materially differ from those indicated in contract documents.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Brazos River Authority

RFP NO. 26-1392

EAST WILLIAMSON COUNTY

REGIONAL WATER SYSTEM

EWCRWS Infrastructure and Expansion Trinity Well and Phase 1D Projects

Volume 1 – Trinity Well, Phase 1B

ISSUED FOR PROPOSAL

Division 00 GENERAL CONDITIONS and

SUPPLEMENTAL CONDITIONS

Division 01 GENERAL REQUIREMENTS

JULY 2026

CDM Smith, Inc.

8310-1 N. Capital of Texas Hwy

Suite 250, Austin, TX, 78731 www.cdmsmith.com

Texas Registered Engineering Firm F-3034

Divisions 02-46 TECHNICAL SPECIFICATIONS, Phase 1B

THIS PAGE HAS BEEN INTENTIONALLY LEFT BLANK.

EWCRWS Infrastructure and Expansion Trinity Well and Phase 1D Projects

Brazos River Authority July 2026

9323-291797/294846 000107-1 Seals Pages RFP No. 26-1392 ©CDM SMITH 2026

SEALS PAGES

EWCRWS Infrastructure and Expansion Trinity Well and PHASE 1D Projects Issued for Bid Design Specifications

The following individuals hereby certify that the accompanying design drawings and specifications were prepared under their direct supervision relative to their professional practice and demonstrated competency.

Specifications:

Trinity Well Project and Phase 1D Project:

Divisions: 00 and 01 (except 018819, 018839), 02, and 41, Sections: 329200, 330516.13 Phase 1D Project:

323113D

Glenn D. Barin General/ Civil CDM Smith – TBPE Firm Registration No. F-304

Specifications:

Trinity Well Project and Phase 1D Project:

Divisions: 33 Sections: 311000, 312323.33, 312500, 313700B, 321313, 321373, 321713, 329119, 400506, 400507, 400519, 400524, 400551, 400553, 400557, 400564, 400567.13, 400593.23, 404113.13D, 430553, 432356.13, 434163D, 460553, 464117 Trinity Well Project:

313700, 321723, 404213, 434164 Phase 1D Project:

400523, 400559.23, 400565.23, 400578.13, 400582, 404113.13, 434163, 464111, 464353, 466113, 466119, 466123.15

Steven V. Lynk Process Mechanical/ Civil CDM Smith TBPE Firm Registration No. F-3043

Brazos River Authority July 2026

9323-291797/294846 000107-2 Seals Pages RFP No. 26-1392 ©CDM SMITH 2026

Specifications:

Trinity Well Project and Phase 1D Project:

Sections: 400531, 400553, 400567.39, 463111, 463344, 463373 Phase 1D Project:

Sections: 434143, 463126.15

Christopher Fahlin Process Mechanical - Chemical CDM Smith – TBPE Firm Registration No. F-3043

Specifications:

Trinity Well Project:

Divisions: 03, 05 Sections: 018839, 034213, 067413, 083483

Alan H. Hahn Structural Design CDM Smith – TBPE Firm Registration No. F-3043

Specifications:

Phase 1D Project:

Divisions: 03, 05, 13 (except 134714) Sections: 018819, 067413

Samuel V. Gil Structural Design CDM Smith – TBPE Firm Registration No. F-3043

7/20/2026

Brazos River Authority July 2026

9323-291797/294846 000107-3 Seals Pages RFP No. 26-1392 ©CDM SMITH 2026

Specifications:

Trinity Well Project:

Section: 077200B

Stephen Burdett HVAC/ Building Mechanical CDM Smith – TBPE Firm Registration No. F-3043

Specifications:

Trinity Well Project and Phase 1D Project:

Divisions: 07 (except 077200B), 08 (except 083483B), 09, and 13 (except 134714) Sections: 061000, 066400 Phase 1D Project:

Divisions: 04, 10, 12

Ferdinand M. De Guzman Finishes CDM Smith – TBPE Firm Registration No. F-3043

Specifications:

Trinity Well Project and Phase 1D Project:

Sections: 310515, 310519.13, 310519.16, 310519.16A, 312000, 312319, 312333, 315000, 321123, 321216 Phase 1D Project:

Section: 310900

Sochan (Jason) Jung Geotechnical

Brazos River Authority July 2026

9323-291797/294846 000107-4 Seals Pages RFP No. 26-1392 ©CDM SMITH 2026

Specifications:

Trinity Well Project and Phase 1D Project:

Division: 26

Arturo Vasquez Electrical CDM Smith – TBPE Firm Registration No. F-3043

Specifications:

Trinity Well Project and Phase 1D Project:

Division: 27 Sections: 406121.20, 406126, 406263, 406343, 406613, 406717, 406733, 406763, 407000, 407000A, 407113, 407143, 407250, 407313, 407326, 407363, 407463, 407469, 407521, 407563, 407813, 407816, 407819, 407853, 407856, 407859, 407939 Trinity Well Project:

Sections: 406100, 406196, 407513, 407529 Phase 1D Project:

Sections: 406100, 406196, 406866, 407179, 407213, 407276 407323, 407329, 407336, 407553, 407823

Jerry Haire Instrumentation and Controls Systems CDM Smith – TBPE Firm Registration No. F-3043

Specifications:

Trinity Well Project and Phase 1D Project:

Section: 134714

Christopher L. Sheldon Cathodic Protection V&A Consulting – TBPE Firm Reg. No. 9154

Brazos River Authority July 2026

9323-291797/294846 000107-5 Seals Pages RFP No. 26-1392 ©CDM SMITH 2026

Specifications:

Trinity Well Project and Phase 1D Project:

Sections: 400567.39 Phase 1D Project:

Sections: 400578.19, 432426.16

Michael R. Clough Process Mechanical (RWPS) Walker Partners – TBPE Firm Reg. No. F-8053

Specifications:

Trinity Well Project and Phase 1D Project:

Divisions: 22, 23 Phase 1D Project:

Sections: 400561D, 400562D

Gibson G. Mammen Plumbing/ Building Mechanical CDM Smith – TBPE Firm Registration No. F-3043

Specifications:

Phase 1D Project:

Division: 28

Anjali Paithankar Security

Brazos River Authority July 2026

9323-291797/294846 000107-6 Seals Pages RFP No. 26-1392 ©CDM SMITH 2026

Specifications:

Trinity Well Project and Phase 1D Project:

Sections: 400567.39 Phase 1D Project:

Sections: 400565.23, 400578.13, 400578.29, 432358, 432426.15, 432513.35

Wenjing (Lisa) Cheng Process Mechanical CDM Smith – TBPE Firm Registration No. F-3043

Specifications:

Trinity Well Project:

Section: 236514.13

Andras Nady Cooling Tower

7-20-26

Brazos River Authority EWCRWS Infrastructure and Expansion July 2026 Trinity Well and Phase 1D Projects

9323-291797/294846 1 Table of Contents RFP No. 26-1392 ©CDM SMITH 2026

SECTION 000110 - TABLE OF CONTENTS

PROCUREMENT AND CONTRACTING DOCUMENTS GROUP

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS (Common to 1B and 1D)

000107 SEALS PAGES

007000 GENERAL CONDITIONS

008000 SUPPLEMENTARY CONDITIONS

DIVISION 01 - GENERAL REQUIREMENTS (Procurement and Contracting, Common to 1B and 1D))

010000 GENERAL REQUIREMENTS

011000 SUMMARY OF WORK

011400 WORK RESTRICTIONS

012000 PRICE AND PAYMENT PROCEDURES

012500 SUBSTITUTION PROCEDURES

012600 CONTRACT MODIFICATION PROCEDURES

012613 REQUESTS FOR INTERPRETATIONS

013100 PROJECT MANAGEMENT AND COORDINATION

013200 CONSTRUCTION PROGRESS DOCUMENTATION

013300 SUBMITTAL PROCEDURES

013529 HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES

014000 QUALITY REQUIREMENTS

014100 REGULATORY REQUIREMENTS

014216 REFERENCES

015000 TEMPORARY FACILITIES AND CONTROLS

015680 SECURITY MEASURES

015700 TEMPORARY CONTROLS

016500 PRODUCT DELIVERY REQUIREMENTS

016600 PRODUCT STORAGE AND HANDLING REQUIREMENTS

017114 MOBILIZATION AND DEMOBILIZATION

017300 EXECUTION

017400 CLEANING AND WASTE MANAGEMENT

017500 STARTING AND ADJUSTING

017700 CLOSEOUT PROCEDURES

017800 CLOSEOUT SUBMITTALS

TECHNICAL SPECIFICATIONS GROUP

Note Use of the following Suffixes:

Specification Numbers followed by “B” Are Unique to Phase 1B Specification Numbers followed by “D” Are Unique to Phase 1D Specifications NOT denoted with B/D suffixes are common to both phases

DIVISION 01 - GENERAL REQUIREMENTS (TECHNICAL)

018819D TIGHTNESS TESTING PERFORMANCE REQUIREMENTS

018839 WIND PERFORMANCE REQUIREMENTS

9323-291797/294846 2 Table of Contents RFP No. 26-1392 ©CDM SMITH 2026

DIVISION 02 - EXISTING CONDITIONS

024119 SELECTIVE DEMOLITION

DIVISION 03 – CONCRETE

030130.71 MODIFICATIONS TO EXISTING CONCRETE

031000 CONCRETE FORMING AND ACCESSORIES

031500 CONCRETE JOINTS AND ACCESSORIES

032000 CONCRETE REINFORCING

033000 CAST-IN-PLACE CONCRETE

033500 CONCRETE FINISHING

033900 CONCRETE CURING

034100B PRECAST STRUCTURAL CONCRETE

034213D PRECAST CONCRETE BUILDING

036000 GROUTING

DIVISION 04 – MASONRY

042200D CONCRETE UNIT MASONRY

042300D GLASS UNIT MASONRY

DIVISION 05 – METALS

050519 POST INSTALLED ANCHORS AND REINFORCING BARS

052100D STEEL JOIST FRAMING

053100D STEEL DECKING

055000 METAL FABRICATION

055119D METAL STAIRS

055200 METAL RAILINGS

055313D BAR GRATINGS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

061000D ROUGH CARPENTRY

066400D PLASTIC PANELING

067413 FIBERGLASS REINFORCED PLASTIC COMPONENTS

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

070150.19D PREPARATION FOR REFOOFING

071900D WATER REPELLENTS

072100D THERMAL INSULATION

074113.16D STANDING-SEAM METAL ROOF PANELS

074213.19D INSULATED METAL WALL PANELS

074293D SOFFIT PANELS

075216D SBS MODIFIED BITUMINOUS MEMBRANE ROOFING

076200D SHEET METAL FLASHING AND TRIM

077200B ROOF HATCHES

079200 JOINT SEALTANTS

DIVISION 08 – OPENINGS

081500D FIBERGLASS REINFORCED PLASTIC DOORS AND FRAMES

083113D ACCESS DOORS AND FRAMES

9323-291797/294846 3 Table of Contents RFP No. 26-1392 ©CDM SMITH 2026

083323D OVERHEAD COILING DOORS

083483B FLOOR DOORS

085113D ALUMINUM WINDOWS

086200D UNIT SKYLIGHTS

087100D DOOR HARDWARE

088000D GLAZING

089119D FIXED LOUVERS

DIVISION 09 – FINISHES

090690D PAINT COLOR SCHEDULE

092216D NON-STRUCTURAL METAL FRAMING

092900D GYPSUM BOARD

093013D CERAMIC TILING

095123D ACOUSTICAL TILE CEILINGS

099123D INTERIOR PAINTING

099673.13D WATER TREATMENT AND PURIFICATION SYSTEM COATINGS

099673.23D WATER PRELIMINARY TREATMENT COATINGS

099673.33D WATER TREATMENT CHEMICAL STORAGE COATINGS

099673.53D WATER TREATMENT TRANSMISSION SYSTEM COATINGS

099679B ATMOSPHERIC PROTECTION AND PLANT SERVICE AREAS COATINGS

099679AB COATINGS SCHEDULE

DIVISION 10 – SPECIALTIES

101416D PLAQUES

101423D PANEL SIGNAGE

101423.16D ROOM-IDENTIFICATION PANEL SIGNAGE

102800D TOILET, BATH, AND LAUNDRY ACCESSORIES

104317D FIRST AID KITS

104416D FIRE EXTINGUISHERS

DIVISION 12 – FURNISHINGS

123623.13D PLASTIC-LAMINATE-CLAD COUNTERTOPS

DIVISION 13 - SPECIAL CONSTRUCTION

133123D TENSIONED FABRIC STRUCTURES

133419D METAL BUILDING SYSTEMS

134714 CATHODIC PROTECTION SYSTEM

DIVISION 22 - PLUMBING

220517D SLEEVES AND SLEEVE SEALS FOR PLUMBING PIPING AND EQUIPMENT

220529D HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT

220553D IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT

220719D PLUMBING PIPING INSULATION

221116 DOMESTIC WATER PIPING

221119 DOMESTIC WATER PIPING SPECIALTIES

221123.13B DOMESTIC-WATER PACKAGED BOOSTER PUMPS

221316D SANITARY WASTE AND VENT PIPING

221319D SANITARY WASTE PIPING SPECIALTIES

221319.13D SANITARY DRAINS

9323-291797/294846 4 Table of Contents RFP No. 26-1392 ©CDM SMITH 2026

221429 PACKAGED PROCESS DRAIN PUMPS

221430 SUMP PUMPS

223300D ELECTRIC, DOMESTIC-WATER HEATERS

224213.13D COMMERCIAL WATER CLOSETS

224216.13D COMMERCIAL LAVATORIES

224216.16D COMMERCIAL SINKS

224713D DRINKING FOUNTAINS

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

230513 COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT

230517 SLEEVES AND SLEEVE SEALS FOR HVAC PIPING

230529 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT

230548.13 VIBRATION CONTROLS FOR HVAC

230593 TESTING, ADJUSTING, AND BALANCING FOR HVAC

230713D DUCT INSULATION

230719D HVAC PIPING INSULATION

230923.12D CONTROL DAMPERS

230923.17 TEMPERATURE INSTRUMENTS

232113 HYDRONIC PIPING

232116 HYDRONIC PIPING SPECIALTIES

233113D METAL DUCTS

233116D NONMETAL DUCTS

233300D AIR DUCT ACCESSORIES

233423 HVAC POWER VENTILATORS

236514.13B OPEN-CIRCUIT, INDUCED-DRAFT, CROSSFLOW COOLING TOWERS

233713.23D REGISTERS AND GRILLES

233723D HVAC GRAVITY VENTILATORS

236514.13B OPEN-CIRCUIT, FORCED-DRAFT COOLING TOWERS

237416.13D PACKAGED, LARGE-CAPACITY, ROOFTOP AIR-CONDITIONING UNITS

238113.11D PACKAGED TERMINAL AIR-CONDITIONERS, THROUGH-WALL UNITS

238113.13B PACKAGED TERMINAL AIR-CONDITIONERS, OUTDOOR, WALL-MOUNTED UNITS

238126D SPLIT-SYSTEM AIR CONDITIONERS

238239.19 WALL AND CEILING UNIT HEATERS

DIVISION 26 – ELECTRICAL

260010 SUPPLEMENTAL REQUIREMENTS FOR ELECTRICAL

260011D FACILITY PERFORMANCE REQUIREMENTS FOR ELECTRICAL

260505 SELECTIVE DEMOLITION FOR ELECTRICAL

260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

260523 CONTROLVOLTAGE ELECTRICAL POWER CABLES

260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

260529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

260533.13 CONDUITS FOR ELECTRICAL SYSTEMS

260533.16B BOXES AND COVERS FOR ELECTRICAL SYSTEMS

260533.23D SURFACE RACEWAYS FOR ELECTRICAL SYSTEMS

260536 CABLE TRAYS FOR ELECTRICAL SYSTEMS

260543 UNDERGROUND DUCTS AND RACEWAYS FOR ELECTRICAL SYSTEMS

260544D SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING

260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS

9323-291797/294846 5 Table of Contents RFP No. 26-1392 ©CDM SMITH 2026

260573 POWER SYSTEM STUDIES

260800 COMMISSIONING OF ELECTRICAL SYSTEMS

260923D LIGHTING CONTROL DEVICES

262200 LOW-VOLTAGE TRANSFORMERS

262413 SWITCHBOARDS

262416 PANELBOARDS

262419B MOTOR-CONTROL CENTERS

262505 480V CONTROL PANELS

262716 ELECTRICAL CABINETS AND ENCLOSURES

262726 WIRING DEVICES

262813 FUSES

262816 ENCLOSED SWITCHES AND CIRCUIT BREAKERS

262923 VARIABLE-FREQUENCY MOTOR CONTROLLERS

263600 TRANSFER SWITCHES

264113 LIGHTNING PROTECTION FOR STRUCTURES

264313 SURGE PROTECTIVE DEVICES FOR LOW-VOLTAGE ELECTRICAL POWER CIRCUITS

265000 LIGHTING

265613 LIGHTING POLES AND STANDARDS

DIVISION 27 – COMMUNICATIONS

270526 GROUNDING AND BONDING FOR COMMUNICATIONS SYSTEMS

270528 PATHWAYS FOR COMMUNICATIONS SYSTEMS

270553 IDENTIFICATION FOR COMMUNICATIONS SYSTEMS

271116D COMMUNICATIONS RACKS, FRAMES, AND ENCLOSURES

271323 COMMUNICATIONS OPTICAL FIBER BACKBONE CABLING

271513 COMMUNICATIONS COPPER HORIZONTAL CABLING

271523 COMMUNICATIONS OPTICAL FIBER HORIZONTAL CABLING

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

282000D VIDEO SURVEILLANCE

DIVISION 31 – EARTHWORK

310515 SOILS AND AGGREGATES FOR EARTHWORK

310519.13 GEOTEXTILES FOR EARTHWORK

310519.16 GEOMEMBRANE LINERS

310519.16A HDPE GEOMEMBRANE TABLES

310900D GEOTECHNICAL INSTRUMENTATION AND MONITORING

311000 SITE CLEARING

312000 EARTHWORK

312319 DEWATERING

312323.33 FLOWABLE FILL

312333 TRENCHING AND BACKFILLING

312500 EROSION AND SEDIMENTATION CONTROLS

313700B RIPRAP

315000 EXCAVATION SUPPORT AND PROTECTION

DIVISION 32 - EXTERIOR IMPROVEMENTS

321123 AGGREGATE BASE COURSES

321216 ASPHALT PAVING

9323-291797/294846 6 Table of Contents RFP No. 26-1392 ©CDM SMITH 2026

321313 CONCRETE PAVING

321373 CONCRETE PAVING JOINT SEALANTS

321713 PARKING BUMPERS

321723 PAVEMENT MARKINGS

323113D CHAIN LINK FENCES AND GATES

329119 LANDSCAPE GRADING

329200 TURF AND GRASSES

DIVISION 33 – UTILITIES

330513 MANHOLES AND STRUCTURES

330516.13 PRECAST CONCRETE UTILITY STRUCTURES

330519 BURIED DUCTILE-IRON UTILITY PIPE FOR WATER SERVICE

330524.23 STEEL UTILITY PIPE FOR WATER SERVICE

330526D UTILITY IDENTIFICATION

330531.16 POLYVINYL CHLORIDE PRESSURE PIPE FOR WATER SERVICE

330533.23 POLYETHYLENE PRESSURE PIPE FOR WATER SERVICE

331216 WATER UTILITY DISTRIBUTION GATE VALVES

331219 WATER UTILITY DISTRIBUTION FIRE HYDRANTS

331300 DISINFECTING OF WATER UTILITY DISTRIBUTION

331419 BURIED VALVES – BASIC REQUIREMENTS

333100D SANITARY UTILITY SEWERAGE PIPING

333256D FOUNDATION DRAIN WETWELL AND PUMPING SYSTEM

333400B SANITARY UTILITY SEWERAGE FORCE MAINS

334100D STORM UTILITY DRAINAGE PIPING

334213 PIPE CULVERTS

DIVISION 40 - PROCESS INTERCONNECTIONS

400506 COUPLING, ADAPTERS AND SPECIALS FOR PROCESS PIPING

400507 HANGERS AND SUPPORTS FOR PROCESS PIPING

400519 DUCTILE IRON PROCESS PIPE

400523D STAINLESS STEEL PROCESS PIPE AND TUBING

400524 STEEL PROCESS PIPE

400531 THERMOPLASTIC PROCESS PIPE

400551 COMMON REQUIREMENTS FOR PROCESS VALVES

400551A VALVE SCHEDULE

400553 IDENTIFICATION OF PROCESS PIPING

400557 ACTUATORS FOR PROCESS VALVES AND GATES

400559.23D STAINLESS STEEL SLIDE GATES

400561D GATE VALVES

400562D PLUG VALVES

400563 BALL VALVES

400564 BUTTERFLY VALVES

400565.23D SWING CHECK VALVES

400567.13 REDUCED PRESSURE ZONE BACKFLOW PREVENTORS FOR PROCESS SERVICE

400567.39 PRESSURE RELIEF VALVES

400578.13D AIR-VACUUM VALVES FOR WATER SERVICE

400578.19D COMBINATION AIR VALVES FOR WATER SERVICE

400578.29D COMBINATION AIR VALVES FOR WASTEWATER SERVICE

400582D SOLENOID VALVES FOR PROCESS SERVICE

400593.23 LOW-VOLTAGE MOTOR REQUIREMENTS FOR PROCESS EQUIPMENT

9323-291797/294846 7 Table of Contents RFP No. 26-1392 ©CDM SMITH 2026

404113.13D PROCESS PIPING ELECTRICAL RESISTANCE HEAT TRACING

404213B PROCESS PIPING INSULATION

406100B PROCESS CONTROL AND ENTERPRISE MANAGEMENT SYSTEMS GENERAL PROVISIONS

406100D PROCESS CONTROL AND ENTERPRISE MANAGEMENT SYSTEMS GENERAL PROVISIONS

406121.20 PROCESS CONTROL SYSTEM TESTING

406126 PROCESS CONTROL SYSTEM TRAINING

406196B PROCESS CONTROL DESCRIPTIONS

406196D PROCESS CONTROL DESCRIPTIONS

406263 OPERATOR INTERFACE TERMINALS

406343 PROGRAMMABLE LOGIC CONTROLLERS

406613 SWITCHES AND ROUTERS

406717 INDUSTRIAL ENCLOSURES

406733 PANEL WIRING

406763 CONTROL PANEL MOUNTED UPS

406866D CONFIGURATION OF CONTROLLER SOFTWARE

407000 INSTRUMENTATION FOR PROCESS SYSTEMS

407000A INSTRUMENT LIST

407113 MAGNETIC FLOW METERS

407143 VARIABLE AREA FLOW METERS

407179D FLOW SWITCHES

407213D ULTRASONIC LEVEL METERS

407250 CONDUCTIVITY SENSOR LEVEL CONTROL SYSTEM

407276D LEVEL SWITCHES

407313 PRESSURE AND DIFFERENTIAL PRESSURE GAUGES

407323D ABSOLUTE PRESSURE TRANSMITTERS

407326 GAUGE PRESSURE TRANSMITTERS

407329D DIFFERENTIAL PRESSURE TRANSMITTERS

407336D PRESSURE AND DIFFERENTIAL PRESSURE SWITCHES

407363 DIAPHRAGM SEALS

407463 TEMPERATURE TRANSMITTERS

407469 THERMOWELLS, PROTECTION TUBES, AND TEST THERMOWELLS

407513B pH/ORP ANALYZERS

407521 CHLORINE ANALYZERS

407529B DISSOLVED AMMONIA ANALYZERS

407553D TURBIDITY ANALYZERS

407563 MONOCHLORAMINE ANALYZERS

407813 INDICATORS AND METERS

407816 INDICATING LIGHTS

407819 SWITCHES AND PUSH BUTTONS

407823D POTENTIOMETERS AND MANUAL CONTROLLERS

407853 RELAYS

407856 ISOLATORS, INTRINSINCALLY SAFE BARRIERS, AND SURGE SUPPRESSORS

407859 POWER SUPPLIES

407939 SIGNAL CONDITIONERS AND CONVERTERS

9323-291797/294846 8 Table of Contents RFP No. 26-1392 ©CDM SMITH 2026

DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT

412213.19D JIB CRANES

412223.19D MONORAIL HOISTS

DIVISION 43 - PROCESS GAS AND LIQUID HANDLING, PURIFICATION AND STORAGE EQUIPMENT

430553 IDENTIFICATION FOR PROCESS GAS AND LIQUID HANDLING EQUIPMENT

432356.13 MAGNETIC DRIVE GEAR PUMPS

432358D ROTARY LOBE PUMPS

432426.15D VERTICAL TURBINE SHORT-SET PUMPS

432426.16D VERTICAL TURBINE SHORT-SET WET PIT PUMPS

432513.35D WET-PIT SUBMERSIBLE SOLIDS HANDLING PUMPS

434143D HIGH DENSITY POLYETHYLENE TANKS

434163D WIRE AND STRAND WRAPPED PRESTRESSED CONCRETE TANKS

434164B CONNECTION TO EXISTING WIRE AND STRAND WRAPPED PRESTRESSED CONCRETE

CLEARWELL

DIVISION 46 - WATER AND WASTEWATER EQUIPMENT

460553 IDENTIFICATION OF WATER AND WASTEWATER EQUIPMENT

463111 CHLORINE GAS FEED EQUIPMENT

463126.15D EMERGENCY GAS TREATMENT SYSTEM – CHLORINE

463344 PERISTALTIC METERING PUMPS

463373 LIQUID CHEMICAL DIFFUSERS

464111D RAPID MIXERS

464117 INLINE STATIC MIXERS

464353D SOLIDS CONTACT CLARIFIER EQUIPMENT

466113D FILTER MEDIA

466119D FIBERGLASS REINFORCED PLASTIC WASHWATER TROUGHS

466123.15D FILTER UNDERDRAIN SYSTEM

APPENDICES

APPENDIX A – 1B GEOTECHNICAL REPORT

APPENDIX B – 1D GEOTECHNICAL REPORT

APPENDIX C – SUBSURFACE UTILITY TEST HOLE DATA

END OF TABLE OF CONTENTS

EJCDC No. 1910-8 (1996 Edition ) 000700-0

STANDARD

GENERAL CONDITIONS

OF THE

CONSTRUCTION CONTRACT

Prepared by

ENGINEERS JOINT CONTRACT DOCUMENTS COMMITTEE

and

Issued and Published Jointly By

[INSERT LOGOS]

PROFESSIONAL ENGINEERS IN PRIVATE PRACTICE

a practice division of the

NATIONAL SOCIETY OF PROFESSIONAL ENGINEERS

AMERICAN CONSULTING ENGINEERS COUNCIL

AMERICAN SOCIETY OF CIVIL ENGINEERS

This document has been approved and endorsed by

The Associated General [seal] Contractors of

America Construction Specifications Institute

[seal]

This document has important legal consequences; consultation with an attorney is encouraged with respect to its use or modification. This document should be adapted to the particular circumstances of the contemplated Project and the Controlling Law.

These General Conditions have been prepared for use with the Owner-Contractor Agreements (No. 1910-8-A-1 or 1910-8- A-2) (1996 Editions). Their provisions are interrelated and a change in one may necessitate a change in the other.

Comments concerning their usage are contained in the EJCDC User’s Guide (No. 1910-50). For guidance in the preparation of Supplementary Conditions, see Guide to the Preparation of Supplementary Conditions (No. 1910-17) (1996 Edition).

EJCDC No. 1910-8 (1996 Edition ) 000700-1

Copyright ©1996

National Society of Professional Engineers 1420 King Street, Alexandria, VA 22314

American Consulting Engineers Council 1015 15th Street N.W., Washington, DC 20005

American Society of Civil Engineers 345 East 47th Street, New

York, NY 10017

EJCDC No. 1910-8 (1996 Edition ) 000700-2

TABLE OF CONTENTS

Page

ARTICLE 1 - DEFINITIONS AND TERMINOLOGY

1.01 Defined Terms

1.02 Terminology

ARTICLE 2 - PRELIMINARY MATTERS

2.01 Delivery of Bonds

2.02 Copies of Documents

2.03 Commencement of Contract Times; Notice to Proceed

2.04 Starting the Work

2.05 Before Starting Construction

2.06 Preconstruction Conference

2.07 Initial Acceptance of Schedules

ARTICLE 3 - CONTRACT DOCUMENTS: INTENT, AMENDING, REUSE

3.01 Intent

3.02 Reference Standards

3.03 Reporting and Resolving Discrepancies

3.04 Amending and Supplementing Contract Documents

3.05 Reuse of Documents

ARTICLE 4 - AVAILABILITY OF LANDS; SUBSURFACE AND PHYSICAL CONDITIONS; REFERENCE

POINTS

4.01 Availability of Lands

4.02 Subsurface and Physical Conditions

4.03 Differing Subsurface or Physical Conditions

4.04 Underground Facilities

4.05 Reference Points

4.06 Hazardous Environmental Condition at Site

ARTICLE 5 - BONDS AND INSURANCE

5.01 Performance, Payment, and Other Bonds

5.02 Licensed Sureties and Insurers

5.03 Certificates of Insurance

5.04 CONTRACTOR’s Liability Insurance

5.05 OWNER’s Liability Insurance

5.06 Property Insurance

5.07 Waiver of Rights

5.08 Receipt and Application of Insurance Proceeds

5.09 Acceptance of Bonds and Insurance; Option to Replace

5.10 Partial Utilization, Acknowledgment of Property Insurer

ARTICLE 6 - CONTRACTOR’S RESPONSIBILITIES

6.01 Supervision and Superintendence

6.02 Labor; Working Hours

6.03 Services, Materials, and Equipment

6.04 Progress Schedule

6.05 Substitutes and “Or-Equals”

6.06 Concerning Subcontractors, Suppliers, and Others

6.07 Patent Fees and Royalties

6.08 Permits

EJCDC No. 1910-8 (1996 Edition ) 000700-3

6.09 Laws and Regulations

6.10 Taxes

6.11 Use of Site and Other Areas

6.12 Record Documents

6.13 Safety and Protection

6.14 Safety Representative

6.15 Hazard Communication Programs

6.16 Emergencies

6.17 Shop Drawings and Samples

6.18 Continuing the Work

6.19 CONTRACTOR’s General Warranty and Guarantee

6.20 Indemnification

ARTICLE 7 - OTHER WORK

7.01 Related Work at Site

7.02 Coordination

ARTICLE 8 - OWNER’S RESPONSIBILITIES

8.01 Communications to Contractor

8.02 Replacement of ENGINEER

8.03 Furnish Data

8.04 Pay Promptly When Due

8.05 Lands and Easements; Reports and Tests

8.06 Insurance

8.07 Change Orders

8.08 Inspections, Tests, and Approvals

8.09 Limitations on OWNER’s Responsibilities

8.10 Undisclosed Hazardous Environmental Condition

8.11 Evidence of Financial Arrangements

ARTICLE 9 - ENGINEER’S STATUS DURING CONSTRUCTION

9.01 OWNER’S Representative

9.02 Visits to Site

9.03 Project Representative

9.04 Clarifications and Interpretations

9.05 Authorized Variations in Work

9.06 Rejecting Defective Work

9.07 Shop Drawings, Change Orders and Payments

9.08 Determinations for Unit Price Work

9.09 Decisions on Requirements of Contract Documents and Acceptability of Work

9.10 Limitations on ENGINEER’s Authority and Responsibilities

ARTICLE 10 - CHANGES IN THE WORK; CLAIMS

10.01 Authorized Changes in the Work

10.02 Unauthorized Changes in the Work

10.03 Execution of Change Orders

10.04 Notification to Surety

10.05 Claims and Disputes

ARTICLE 11 - COST OF THE WORK; CASH ALLOWANCES; UNIT PRICE WORK

11.01 Cost of the Work

11.02 Cash Allowances

11.03 Unit Price Work

ARTICLE 12 - CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIMES

12.01 Change of Contract Price

EJCDC No. 1910-8 (1996 Edition ) 000700-4

12.02 Change of Contract Times

12.03 Delays Beyond CONTRACTOR’s Control

12.04 Delays Within CONTRACTOR’s Control

12.05 Delays Beyond OWNER’s and CONTRACTOR’s Control

12.06 Delay Damages

ARTICLE 13 - TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF DEFECTIVE

WORK

13.01 Notice of Defects

13.02 Access to Work

13.03 Tests and Inspections

13.04 Uncovering Work

13.05 OWNER May Stop the Work

13.06 Correction or Removal of Defective Work

13.07 Correction Period

13.08 Acceptance of Defective Work

13.09 OWNER May Correct Defective Work

ARTICLE 14 - PAYMENTS TO CONTRACTOR AND COMPLETION

14.01 Schedule of Values

14.02 Progress Payments

14.03 CONTRACTOR’s Warranty of Title

14.04 Substantial Completion

14.05 Partial Utilization

14.06 Final Inspection

14.07 Final Payment

14.08 Final Completion Delayed

14.09 Waiver of Claims

ARTICLE 15 - SUSPENSION OF WORK AND TERMINATION

15.01 OWNER May Suspend Work

15.02 OWNER May Terminate for Cause

15.03 OWNER May Terminate For Convenience

15.04 CONTRACTOR May Stop Work or Terminate

ARTICLE 16 - DISPUTE RESOLUTION

16.01 Methods and Procedures

ARTICLE 17 – MISCELLANEOUS

17.01 Giving Notice

17.02 Computation of Times

17.03 Cumulative Remedies

17.04 Survival of Obligations

17.05 Controlling Law

EJCDC No. 1910-8 (1996 Edition ) 007000-5

ARTICLE 1 - DEFINITIONS AND

TERMINOLOGY

1.01 Defined Terms

A. Wherever used in the Contract Documents and printed with initial or all capital letters, the terms listed below will have the meanings indicated which are applicable to both the singular and plural thereof.

1. Addenda--Written or graphic instruments issued prior to the opening of Bids which clarify, correct, or change the Bidding Requirements or the Contract Documents.

2. Agreement--The written instrument which is evidence of the agreement between OWNER and CONTRACTOR covering the Work.

3. Application for Payment--The form acceptable to ENGINEER which is to be used by CON- TRACTOR during the course of the Work in requesting progress or final payments and which is to be accompanied by such supporting documentation as is required by the Contract Documents.

4. Asbestos--Any material that contains more than one percent asbestos and is friable or is releasing asbestos fibers into the air above current action levels established by the United States Occupational Safety and Health Administration.

5. Bid--The offer or proposal of a bidder submitted on the prescribed form setting forth the prices for the Work to be performed.

6. Bidding Documents--The Bidding Requirements and the proposed Contract Documents (in- cluding all Addenda issued prior to receipt of Bids).

7. Bidding Requirements--The Advertisement or Invitation to Bid, Instructions to Bidders, Bid security form, if any, and the Bid form with any supplements.

8. Bonds--Performance and payment bonds and other instruments of security.

9. Change Order--A document recommended by ENGINEER which is signed by CONTRACTOR and OWNER and authorizes an addition, deletion, or revision in the Work or an adjustment in the Contract Price or the Contract Times, issued on or after the Effective Date of the Agreement.

10. Claim--A demand or assertion by OWNER or CONTRACTOR seeking an adjustment of Contract Price or Contract Times, or both, or other relief with respect to the terms of the Contract. A demand for money or services by a third party is not a Claim.

11. Contract--The entire and integrated written agreement between the OWNER and CONTRACTOR concerning the Work. The Contract supersedes prior negotiations, representations, or agreements, whether written or oral.

12. Contract Documents--The Contract Docu- ments establish the rights and obligations of the parties and include the Agreement, Addenda (which pertain to the Contract Documents), CONTRACTOR’s Bid (including documentation accompanying the Bid and any post Bid documentation submitted prior to the Notice of Award) when attached as an exhibit to the Agreement, the Notice to Proceed, the Bonds, these General Conditions, the Supplementary Conditions, the Specifications and the Drawings as the same are more specifically identified in the Agreement, together with all Written Amendments, Change Orders, Work Change Directives, Field Orders, and ENGINEER’s written interpretations and clarifications issued on or after the Effective Date of the Agreement. Approved Shop Drawings and the reports and drawings of subsurface and physical conditions are not Contract Documents. Only printed or hard copies of the items listed in this paragraph are Contract Documents. Files in electronic media format of text, data, graphics, and the like that may be furnished by OWNER to CONTRACTOR are not Contract Documents.

13. Contract Price--The moneys payable by OWNER to CONTRACTOR for completion of the Work in accordance with the Contract Documents as stated in the Agreement (subject to the provisions of paragraph 11.03 in the case of Unit Price Work).

14. Contract Times--The number of days or the dates stated in the Agreement to: (i) achieve Substantial Completion; and (ii) complete the Work so that it is ready for final payment as evidenced by ENGINEER’s written recommendation of final payment.

15. CONTRACTOR--The

007000-6 individual or entity with whom OWNER has entered into the Agreement.

16. Cost of the Work--See paragraph 11.01.A for definition.

17. Drawings--That part of the Contract Documents prepared or approved by ENGINEER which graphically shows the scope, extent, and character of the Work to be performed by CONTRACTOR. Shop Drawings and other CONTRACTOR submittals are not DDrawings as so defined.

18. Effective Date of the Agreement--The date indicated in the Agreement on which it becomes effective, but if no such date is indicated, it means the date on which the Agreement is signed and delivered by the last of the two parties to sign and deliver.

19. ENGINEER--The individual or entity named as such in the Agreement.

20. ENGINEER's Consultant--An individual or entity having a contract with ENGINEER to furnish services as ENGINEER’s independent professional associate or consultant with respect to the Project and who is identified as such in the Supplementary Conditions.

21. Field Order--A written order issued by ENGINEER which requires minor changes in the Work but which does not involve a change in the Contract Price or the Contract Times.

22. General Requirements--Sections of Division 1 of the Specifications. The General Requirements pertain to all sections of the Specifications.

23. Hazardous Environmental Condition-- The presence at the Site of Asbestos, PCBs, Petroleum, Hazardous Waste, or Radioactive Material in such quantities or circumstances that may present a substantial danger to persons or property exposed thereto in connection with the Work.

24. Hazardous Waste--The term Hazardous Waste shall have the meaning provided in Section 1004 of the Solid Waste Disposal Act (42 USC Section 6903) as amended from time to time.

25. Laws and Regulations; Laws or Regulations-- Any and all applicable laws, rules, regulations, ordinances, codes, and orders of any and all governmental bodies, agencies, authorities, and courts having jurisdiction.

26. Liens--Charges, security interests, or encumbrances upon Project funds, real property, or personal property.

27. Milestone--A principal event specified in the Contract Documents relating to an intermediate completion date or time prior to Substantial Completion of all the Work.

28. Notice of Award--The written notice by OWNER to the apparent successful bidder stating that upon timely compliance by the apparent successful bidder with the conditions precedent listed therein, OWNER will sign and deliver the Agreement.

29. Notice to Proceed--A written notice given by OWNER to CONTRACTOR fixing the date on which the Contract Times will commence to run and on which CONTRACTOR shall start to perform the Work under the Contract Documents.

30. OWNER--The individual, entity, public body, or authority with whom CONTRACTOR has entered into the Agreement and for whom the Work is to be performed.

31. Partial Utilization--Use by OWNER of a substantially completed part of the Work for the purpose for which it is intended (or a related purpose) prior to Substantial Completion of all the Work.

32. PCBs--Polychlorinated biphenyls.

33. Petroleum--Petroleum, including crude oil or any fraction thereof which is liquid at standard conditions of temperature and pressure (60 degrees Fahrenheit and

14.7 pounds per square inch absolute), such as oil, petroleum, fuel oil, oil sludge, oil refuse, gasoline, kerosene, and oil mixed with other non-Hazardous Waste and crude oils.

34. Project--The total construction of which the Work to be performed under the Contract Documents may be the whole, or a part as may be indicated elsewhere in the Contract Documents.

35. Project Manual--The bound documentary information prepared for bidding and constructing the Work. A listing of the contents of the Project Manual, which may be bound in one or more volumes, is

007000-7 contained in the table(s) of contents.

36. Radioactive Material--Source, special nucle- ar, or byproduct material as defined by the Atomic Energy Act of 1954 (42 USC Section 2011 et seq.) as amended from time to time.

37. Resident Project Representative-- The autho- rized representative of ENGINEER who may be assigned to the Site or any part thereof.

38. Samples--Physical examples of materials, equipment, or workmanship that are representative of some pPortion of the Work and which establish the standards by which such portion of the Work will be judged.

39. Shop Drawings--All drawings, diagrams, illustrations, schedules, and other data or information which are specifically prepared or assembled by or for CONTRACTOR and submitted by CONTRACTOR to illustrate some portion of the Work.

40. Site--Lands or areas indicated in the Contract Documents as being furnished by OWNER upon which the Work is to be performed, including rights-of-way and easements for access thereto, and such other lands furnished by OWNER which are designated for the use of CONTRACTOR.

41. Specifications--That part of the Contract Documents consisting of written technical descriptions of materials, equipment, systems, standards, and workmanship as applied to the Work and certain administrative details applicable thereto.

42. Subcontractor--An individual or entity having a direct contract with CONTRACTOR or with any other Subcontractor for the performance of a part of the Work at the Site.

43. Substantial Completion--The time at which the Work (or a specified part thereof) has progressed to the point where, in the opinion of ENGINEER, the Work (or a specified part thereof) is sufficiently complete, in accordance with the Contract Documents, so that the Work (or a specified part thereof) can be utilized for the purposes for which it is intended. The terms “substantially complete” and “substantially completed” as applied to all or part of the Work refer to Substantial Completion thereof.

44. Supplementary Conditions--That part of the Contract Documents which amends or supplements these General Conditions.

45. Supplier--A manufacturer, fabricator, suppli- er, distributor, materialman, or vendor having a direct contract with CONTRACTOR or with any

Subcontractor to furnish materials or equipment to be incorporated in the Work by CONTRACTOR or any Subcontractor.

46. Underground Facilities--All underground pipelines, conduits, ducts, cables, wires, manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any encasements containing such facilities, including those that convey electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or other control systems.

47. Unit Price Work--Work to be paid for on the basis of unit prices.

48. Work--The entire completed construction or the various separately identifiable parts thereof required to be provided under the Contract Documents. Work includes and is the result of performing or providing all labor, services, and documentation necessary to produce such construction, and furnishing, installing, and incorporating all materials and equipment into such construction, all as required by the Contract Documents.

49. Work Change Directive--A written statement to CONTRACTOR issued on or after the Effective Date of the Agreement and signed by OWNER and recommended by ENGINEER ordering an addition, deletion, or revision in the Work, or responding to differing or unforeseen subsurface or physical conditions under which the Work is to be performed or to emergencies. A Work Change Directive will not change the Contract Price or the Contract Times but is evidence that the parties expect that the change ordered or documented by a Work Change Directive will be incorporated in a subsequently issued Change Order following negotiations by the parties as to its effect, if any, on the Contract Price or Contract Times.

50. Written Amendment--A written statement modifying the Contract Documents, signed by OWNER and CONTRACTOR on or after the Effective Date of the Agreement and normally dealing with the nonengineering or

007000-8 nontechnical rather than strictly construction-related aspects of the Contract Documents.

1.02 Terminology

A. Intent of Certain Terms or Adjectives

1. Whenever in the Contract Documents the terms “as allowed,” “as approved,” or terms of like effect or import are used, or the adjectives “reasonable,” “suitable,” “acceptable,” “proper,” “satisfactory,” or adjectives of like effect or import are used to describe an action or determination of ENGINEER as to the Work, it is intended that such action or determination will be solely to evaluate, in general, the completed Work for compliance with the requirements of and information in the Contract Documents and conformance with the design concept of the completed Project as a functioning whole as shown or indicated in the Contract Documents (unless tthere is a specific statement indicating otherwise). The use of any such term or adjective shall not be effective to assign to ENGINEER any duty or authority to supervise or direct the performance of the Work or any duty or authority to undertake responsibility contrary to the provisions of paragraph 9.10 or any other provision of the Contract Documents.

B. Day

1. The word “day” shall constitute a calendar day of 24 hours measured from midnight to the next midnight.

C. Defective

1. The word “defective,” when modifying the word “Work,” refers to Work that is unsatisfactory, faulty, or deficient in that it does not conform to the Contract Documents or does not meet the requirements of any inspection, reference standard, test, or approval referred to in the Contract Documents, or has been damaged prior to ENGINEER’s recommendation of final payment (unless responsibility for the protection thereof has been assumed by OWNER at Substantial Completion in accordance with paragraph 14.04 or 14.05).

D. Furnish, Install, Perform, Provide

1. The word “furnish,” when used in connection with services, materials, or equipment, shall mean to supply and deliver said services, materials, or equipment to the Site (or some other specified location) ready for use or installation and in usable or operable condition.

2. The word “install,” when used in connection with services, materials, or equipment, shall mean to put into use or place in final position said services, materials, or equipment complete and ready for intended use.

3. The words “perform” or “provide,” when used in connection with services, materials, or equipment, shall mean to furnish and install said services, materials, or equipment complete and ready for intended use.

4. When “furnish,” “install,” “perform,” or “provide” is not used in connection with services, materials, or equipment in a context clearly requiring an obligation of CONTRACTOR, “provide” is implied.

E. Unless stated otherwise in the Contract Documents, words or phrases which have a well-known technical or construction industry or trade meaning are used in the Contract Documents in accordance with such recognized meaning.

ARTICLE 2 - PRELIMINARY MATTERS

2.01 Delivery of Bonds

A. When CONTRACTOR delivers the executed Agreements to OWNER, CONTRACTOR shall also deliver to OWNER such Bonds as CONTRACTOR may be required to furnish.

2.02 Copies of Documents

A. OWNER shall furnish to CONTRACTOR up to ten copies of the Contract Documents. Additional copies will be furnished upon request at the cost of reproduction.

2.03 Commencement of Contract Times; Notice to

Proceed

A. The Contract Times will commence

007000-9 to run on the thirtieth day after the Effective Date of the Agreement or, if a Notice to Proceed is given, on the day indicated in the Notice to Proceed. A Notice to Proceed may be given at any time within 30 days after the Effective Date of the Agreement. In no event will the Contract Times com- mence to run later than the sixtieth day after the day of Bid opening or the thirtieth day after the Effective Date of the Agreement, whichever date is earlier.

2.04 Starting the Work

A. CONTRACTOR shall start to perform the Work on the date when the Contract Times commence to run. No Work shall be done at the Site prior to the date on which the Contract Times commence to run.

2.05 Before Starting Construction

A. CONTRACTOR’s Review of Contract Documents: Before undertaking each part of the Work, CONTRACTOR shall carefully study and compare the Contract Documents and check and verify pertinent figures therein and all applicable field measurements.CONTRACTOR shall promptly report in writing to ENGINEER any conflict, error, ambiguity, or discrepancy which CONTRACTOR may discover and shall obtain a written interpretation or clarification from ENGINEER before proceeding with any Work affected thereby; however, CONTRACTOR shall not be liable to OWNER or ENGINEER for failure to report any conflict, error, ambiguity, or discrepancy in the Contract Documents unless CONTRACTOR knew or reasonably should have known thereof.

B. a preliminary progress schedule indicat- ing the times (numbers of days or dates) for starting and completing the various stages of the Work, including any Milestones specified in the Contract Documents;

1. a preliminary schedule of Shop Drawing and Sample submittals which will list each required submittal and the times for submitting, reviewing, and processing such submittal; and

2. a preliminary schedule of values for all of the Work which includes quantities and prices of items which when added together equal the Contract Price and subdivides the Work into component parts in sufficient detail to serve as the basis for progress payments during performance of the Work. Such prices will include an appropriate amount of overhead and profit applicable to each item of Work.

C. Evidence of Insurance: Before any Work at the Site is started, CONTRACTOR and OWNER shall each deliver to the other, with copies to each additional insured identified in the Supplementary Conditions, certificates of insurance (and other evidence of insurance which either of them or any additional insured may reasonably request) which CONTRACTOR and OWNER respectively are required to purchase and maintain in accordance with Article 5.

2.06 Preconstruction Conference

A. Within 20 days after the Contract Times start to run, but before any Work at the Site is started, a conference attended by CONTRACTOR, ENGINEER, and others as appropriate will be held to establish a working understanding among the parties as to the Work and to discuss the schedules referred to in paragraph 2.05.B, procedures for handling Shop Drawings and other submittals, processing Applications for Payment, and maintaining required records.

2.07 Initial Acceptance of Schedules

B. Unless otherwise provided in the Contract Docu-ments, at least ten days before submission of the first Application for Payment a conference attended by CON- TRACTOR, ENGINEER, and others as appropriate will be held to review for acceptability to ENGINEER as provided below the schedules submitted in accordance with paragraph 2.05.B.

CONTRACTOR shall have an additional ten days to make corrections and adjustments and to complete and resubmit the schedules. No progress payment shall be made to CONTRACTOR until acceptable schedules are submitted to ENGINEER.

1. The progress schedule will be acceptable to ENGINEER if it provides an orderly progression of the Work to completion within any specified Milestones and the Contract Times. Such accep- tance will not impose on ENGINEER responsibility for the progress schedule, for sequencing, schedul-ing, or progress of the Work nor interfere with or relieve CONTRACTOR from CONTRACTOR’s full responsibility therefor.

2. CONTRACTOR’s schedule of Shop Drawing and Sample submittals will be

007000-10 acceptable to ENGINEER if it provides a workable arrangement for reviewing and processing the required submittals.

3. CONTRACTOR’s schedule of values will be acceptable to ENGINEER as to form and substance if it provides a reasonable allocation of the Contract Price to component parts of the Work.

ARTICLE 3 - CONTRACT DOCUMENTS:

INTENT, AMENDING, REUSE

3.01 Intent

A. The Contract Documents are complementary; what is called for by one is as binding as if called for by all.

B. It is the intent of the Contract Documents to describe a functionally complete Project (or part thereof) to be constructed in accordance with the Contract Documents. Any labor, documentation, services, materials, or equip- ment that may reasonably be inferred from the Contract Documents or from prevailing custom or trade usage as being required to produce the intended result will be provided whether or not specifically called for at no additional cost to OWNER.

C. Clarifications and interpretations of the Contract Documents shall be issued by ENGINEER as provided in Article 9.

3.02 Reference Standards

A. Standards, Specifications, Codes, Laws, and Regulations

1. Reference to standards, specifications, manuals, or codes of any technical society, organization, or association, or to Laws or Regulations, whether such reference be specific or by implication, shall mean the standard, specification, manual, code, or Laws or Regulations in effect at the time of opening of Bids (or on the Effective Date of the Agreement if there were no Bids), except as may be otherwise specifically stated in the Contract Documents.

2. No provision of any such standard, specification, manual or code, or any instruction of a Supplier shall be effective to change the duties or responsibilities of OWNER, CONTRACTOR, or ENGINEER, or any of their subcontractors, consul- tants, agents, or employees from those set forth in the Contract Documents, nor shall any such provision or instruction be effective to assign to OWNER, ENGINEER, or any of ENGINEER’s Consultants, agents, or employees any duty or authority to supervise or direct the performance of the Work or any duty or authority to undertake responsibility inconsistent with the provisions of the Contract Documents.

3.03 Reporting and Resolving Discrepancies

A. Reporting Discrepancies

1. If, during the performance of the Work, CONTRACTOR discovers any conflict, error, ambiguity, or discrepancy within the Contract Documents or between the Contract Documents and any provision of any Law or Regulation applicable to the performance of the Work or of any standard, specification, manual or code, or of any instruction of any Supplier, CONTRACTOR shall report it to ENGINEER in writing at once. CONTRACTOR shall not proceed with the Work affected thereby (except in an emergency as required by paragraph 6.16.A) until an amendment or supplement to the Contract Documents has been issued by one of the methods indicated in paragraph 3.04;

provided, however, that CONTRACTOR shall not be liable to OWNER or ENGINEER for failure to report any such conflict, error, ambiguity, or discrepancy unless CONTRACTOR knew or reasonably should have known thereof.

B. Resolving Discrepancies

1. Except as may be otherwise specifically stated in the Contract Documents, the provisions of the Contract Documents shall take precedence in resolving any conflict, error, ambiguity, or discrepancy between the provisions of the Contract Documents and:

a. the provisions of any standard, specification, manual, code, or instruction (whether or not specifically incorporated by reference in the Contract Documents); or

b. the provisions of any Laws or Regulations applicable to the performance of the Work (unless such an interpretation of the provi-sions of the Contract

007000-11

Documents would result in violation of such Law or Regulation).

3.04 Amending and

Supplementing Contract Documents

A. The Contract Documents may be amended to provide for additions, deletions, and revisions in the Work or to modify the terms and conditions thereof in one or more of the following ways: (i) a Written Amendment;

(ii) a Change Order; or (iii) a Work Change Directive.

B. The requirements of the Contract Documents may be supplemented, and minor variations and deviations in the Work may be authorized, by one or more of the following ways: (i) a Field Order; (ii) ENGINEER’s approval of a Shop Drawing or Sample; or

(iii) ENGINEER’s written interpretation or clarification.

3.05 Reuse of Documents

A. CONTRACTOR and any Subcontractor or Supplier or other individual or entity performing or furnishing any of the Work under a direct or indirect contract with OWNER: (i) shall not have or acquire any title to or ownership rights in any of the Drawings, Specifications, or other documents (or copies of any thereof) prepared by or bearing the seal of ENGINEER or ENGINEER’s Consultant, including electronic media editions; and (ii) shall not reuse any of such Drawings, Specifications, other documents, or copies thereof on extensions of the Project or any other project without written consent of OWNER and ENGINEER and specific written verification or adaption by ENGINEER. This prohibition will survive final payment, completion, and acceptance of the Work, or termination or completion of the Contract. Nothing herein shall preclude CONTRACTOR from retaining copies of the Contract Documents for record purposes.

ARTICLE 4 - AVAILABILITY OF LANDS;

SUBSURFACE AND PHYSICAL CONDITIONS;

REFERENCE POINTS

4.01 Availability of Lands

A. OWNER shall furnish the Site.

OWNER shall notify CONTRACTOR of any encumbrances or restrictions not of general application but specifically related to use of the Site with which CONTRACTOR must comply in performing the Work. OWNER will obtain in a timely manner and pay for easements for permanent structures or permanent changes in existing facilities.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .