Text version
Except as provided herein, all terms and conditions of the document referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. Name and Title of Signer (Type or Print) 16A. Name and title of Contracting Officer (Type or Print)
15B. Contractor/Offeror 15C. Date Signed 16B. United States of America
(Signature of Contracting Officer)
16C. Date Signed
(Signature of person authorized to sign)
NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV. 10-83)
PREVIOUS EDITIONS UNUSABLE Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. Contract ID Code Page of Pages 1 2
5. Project No. (if applicable) 2. Amendment/Modification No.
3. Effective Date August 27, 2018
4. Requisition/Purchase Req. No.
NMAN7200-18-01771
6. Issued By Code AJ930073 7. Administered By (If other than Item 6) Code SEE BLOCK 6
NOAA/EASTERN REGION ACQUISITION
200 GRANBY STREET
SUITE 815
NORFOLK, VA 23510
8. Name and Address of Contractor (No., Street, County, and Zip Code) (X)
X
9A. Amendment of Solicitation No.
EA-133M-18-RQ-01771
9B. Date (See Item 11) August 18, 2018 10A. Modification of Contract/Order No.
10B. Date (See Item 13)
Code Facility Code
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDG- MENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. Accounting and Appropriation Data (if required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACT/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
(x) A. This change order is issued pursuant to: (Specify authority) The changes set forth in item 14 are made in the Contract Order No. in item 10A.
B. The above numbered Contract/Order is modified to reflect the administrative changes (such as changes in paying office, appropriation date, etc.)
Set fourth item 14, pursuant to the authority of FAR 43.103 (b)
C. This supplemental agreement is entered into pursuant to authority of:
D. Other (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. Description of Amendment/Modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible.
X
See the following pages for details pertaining to the Solicitation for DOCKSIDE REPAIRS on NOAA Ship RONALD H. BROWN
RFP EA-133M-18-RP-001771
AMENDMENT 0002
This amendment is issued to extend the solicitation and make changes and corrections to the solicitation and provide responses to vendor questions, as follows:
Proposals are due no later than 12:00 p.m. EST, August 29, 2018. Past Performance documents (attachments J.3 and J.4 of the solicitation package) will be accepted up to and including the revised date.
Q1. The Section B, Schedule of Prices does not correspond with Revision 1 of the specification.
A1. Section B has been revised and uploaded with this Amendment.
Q2. Regarding Item No. 25730 – HEAVY LIFT CRANE REFURBISHMENT, Will this work to be performed directly between the OEM and NOAA or is to be performed by the contractor in accordance with the existing work package?
A2. There are no changes to this work item. This work item is to be completed as part of the work package.
Q3. Please provide all references for Work Item 12330 and 24360.
A3. For Work Item 24360, there should only be one reference drawing. Both reference drawing listed are incorrect. The new correct drawing number is 436-6932892, attached as well as revised Work Item reflecting same.
END AMENDMENT 0002