NOAA Ship Okeanos Explorer (R-337)
FY 2018
DOCKSIDE REPAIRS
DETAIL SPECIFICATIONS
NOAA Ship Okeanos Explorer FY18 Dockside Repair Table of Contents
1. Scope 2
2. General 2
3. Basic Items 8 10911 ABS Intermediate Hull Survey 7 Inspection 8 12371 Bow Thruster Motor and Motor Cooler Cleaning 10 15121 Engineer’s Office (1-62-0-Q) Vent Duct and Chilled 13
Water Piping Re-Insulation 15041 Gauge and Instrument Calibration 15 13241 SCR Breaker Cleaning and Testing 17 16341 0-1 and 0-2 Deck Passageway Deck Covering Renewal 23 19851 Annual Fire Detection & Suppression Systems Inspection 27 15122 Gaylord Hood Exhaust Duct Renewal 32 15141 Air Conditioning Compressor and Spare 36
Compressor Overhauls
4. Additional Items 38
5. Option Items 40
56311 T’ween Deck Preservation 40 55121 02-34-1-Q Fan Room Cooling Coil Renewal 42 55122 HVAC System Balancing 45 51711 VSAT Antenna Mast Installation 49 63621 Mission UPS Maintenance and Battery Upgrade 54 63622 Mission UPS Infrastructure Upgrade 55
1.0 SCOPE
The National Oceanic and Atmospheric Administration (NOAA) operates a fleet of research vessels that supports research and mapping for the National Fisheries Service, National Ocean Service, Office of Atmospheric Research and the National Weather Service, as well as provides support to other Federal agencies. These research missions are time sensitive and therefore the data must be collected at specific times during the sailing season to be meaningful. At the end of each sailing season the vessels enter a repair period (drydock or dockside) to address repairs that have been previously identified, perform upgrades to mission systems or ship systems that either extend the life of the ship or provide new data collection capabilities or for safer operations of ships systems as well as address any emergent work that would adversely affect the ships ability to safely perform its mission on schedule, while meeting all regulatory body requirements (American Bureau of Shipping and United States Coast Guard) and all habitability requirements, including any that may be required as a result of contracts for personnel to augment ship staff.
The work items in the repair specification are identified well in advance of the performance period in order meet the contracting lead times. Additional work items (emergent work) may arise during the period between the work package submittal, contract award, or even prior to the start of or during the contract performance period. In accordance with Commerce Acquisition Regulation (CAR) clause 1352.271-72, the Contracting Officer may order additional changes during the contract period of performance to address any additional work items identified as necessary to ensure the intent of the drydock or dockside repair contract is met; that is, that the vessel shall be able to safely perform its mission, that it will meet all habitability requirements and regulatory body requirements, and that such repairs will be timely performed to ensure to the maximum extent practicable that the ship's schedule is not adversely impacted.1.1 This specification contains the requirements for Fiscal Year 2018 (FY18) dockside repairs and modifications to NOAA Ship Okeanos Explorer.
2.0 GENERAL
2.1 References
2.1.1 NOAA Standard Specification MOC-000-1G, “General
Requirements for Ship Repair Work on NOAA Ships”
2.1.2 NOAA Standard Specification S1600, “Structural Access
Cuts”
2.1.3 NOAA Standard Specification S2906, “Arc Welding on
Waterborne Vessels”
2.1.4 NOAA Ship Okeanos Explorer Drawing OE-601-101, Rev.
C, “General Arrangement”
2.1.5 NOAA Weight Report Form, Microsoft XL Format, Weight
Report
2.1.6 NOAA Standard Specification MOC-631-2D, “Coating
Systems for Steel Surfaces”
2.2 Requirements
2.2.1 Reference 2.1.1 forms a part of these Detail
Specifications. All provisions and requirements contained therein are applicable to all work items, including all additional work items which are authorized by the Contracting Officer.
2.2.2 References 2.1.2 and 2.1.3 are amplifications of
the requirements contained in Reference 2.1.1 sections
4.17 and 4.21.
2.2.3 Some of the drawings and information provided in
Reference 2.1.4 reflect some of the ship’s arrangements and construction changes since reactivation as a NOAA ship. Verify all current configuration, construction, and arrangement changes, as necessary, to comply with and perform the work requirements of these specifications. Contractors are encouraged to review ship’s drawings and to perform a field inspection of the ship and her existing equipment.
2.2.4 Ship’s drawings and technical publications may be
borrowed during the performance period. The Contractor can make copies of these drawings and technical publications if their intended use will be outside an office environment. Sign for all reference materials borrowed by the Contractor and his representatives, and then return to the COR after no further use of the reference materials is required.
2.2.5 Ship’s drawings are a combination of original class
drawings, ship specific drawings, conversion design drawings, and some as- built drawings. The Government cannot guarantee the accuracy of ships drawings. Field inspections and ship checks are encouraged for Contractor verifications.
2.2.6 Copies of drawings and technical manuals not included
herein may be made available for review during any scheduled pre-bid inspection and during the performance period.
Contractors may review available drawings and technical manuals on board ship.
2.2.7 Provide and maintain a status report of all American
Bureau of Shipping (ABS) inspections and technical reviews required by ABS, during the course of this contract, to ensure the ship’s ABS certification requirements are in compliance. Submit weekly ABS status reports to the COR, along with the preliminary progress reports.
2.2.8 Conduct all visual examination, hydrostatic testing, and non-destructive testing in accordance with ABS Rules for Building and Classing Steel Vessels, Survey After Construction 2005, Part 7. All contractors performing Non- Destructive Testing (NDT) and hull gauging require certification under the ABS external specialists program.
2.2.9 On the day preceding the Weekly Progress Meeting, provide revised and updated copies of the production schedule to the COR as required to reflect actual work progress on a weekly basis.
2.2.10 Provide all new equipment and furnishings for
installation with factory supplied technical manuals, complete with parts listings. Faxed copies of this information are not acceptable. Deliver all documentation to the COR after installation is completed. Provide these equipment technical manuals with detailed information necessary to operate, maintain, troubleshoot, and repair the equipment. Include detailed procedures for disassembly of equipment, parts lists, drawings, inspection criteria, troubleshooting guides, reassembly, and test procedures. Provide four paper copies of each manual, plus one electronic copy in Adobe Acrobat (.pdf) format.
2.2.11 Provide all inspection, test, and quality reports to
the COR in Microsoft Word electronic software format, in addition to providing hard paper copies.
2.2.12 Whether specified in the individual specification
item or not, all surface preparation and painting shall be accomplished by a SSPC QP1 certified painting contractor.
2.2.13 Weigh all materials and items removed, installed, or
relocated on the ship. Provide a summary report to the COR indicating the total weight in pounds of items and a breakdown of their locations by space, deck, frame, distance from centerline, and height above the deck. Reference 2.1.5 will be provided by the COR for the Contractor to identify, record, and document all weight changes for submitting the summary reports.
Contractor may use their own weight report form for documenting weight changes. All the information required must be tracked and documented on any form provided.
2.2.14 Unless otherwise stated in the individual work items, prepare and coat all new steel, all existing steel surfaces identified to be cleaned and painted, and all paint systems disturbed while accomplishing work items, in accordance with reference 2.1.6. Some of the items in this specification call out specific paint systems and types; consult with paint manufacturer’s representative for obsolete and superseded paint systems. Match the existing coating finish colors and paint type with the surrounding, unmodified area.
2.2.15 Ships force will maintain a minimal presence during
accomplishment of work to these specifications. Their availability to operate ship’s equipment will be limited with the exception of requirements for fuel transfer and ballasting to accommodate tank work and entry. Unless otherwise specified, provide a minimum of two working days’ prior notice for any equipment operations.
2.2.16 Coordinate with Ships force to operate all new
and disturbed machinery a period sufficient to indicate satisfactory performance, but not less than one hour, after all adjustments and deficiency corrective actions have been made, without further adjustment.
2.2.17 Provide manufacturer’s technical representatives where required in the individual work items, to witness and to provide technical guidance during operational testing of equipment and systems. All tests and trials of equipment or systems are to be witnessed by the COR, CME and ABS, as applicable, to ensure compliance with regulatory body requirements to maintain the ship’s ABS class certification, and to complete all requirements of these specifications.
2.2.18 Habitability
2.2.18.1 The ship shall be deemed uninhabitable when any one
or a combination of the following conditions exist and it is impossible for management to correct the problem in a timely manner (4 hours or as noted below):
a. Heat and/or air conditioning is not furnished.
b. Potable water (hot or cold) is not provided for a period of 12 or more consecutive hours.
c. When a working toilet, shower and sanitary drainage are not furnished.
d. At all times when the vessel is in drydock overnight, unless the ship is fully habitable with all facilities including heat and/or air conditioning, lights, hot and cold running water, shower and sanitary facilities (working toilets and sanitary drainage). Portable toilets do not meet the requirements for sanitary facilities.
e. Work such as chipping, welding, riveting, hammering and/or pounding, or other noises of a similar nature are being performed in or around vessel personnel quarters or noxious fumes are present that disrupts the employees ability to rest for more than three (3) hours. Note: Wage mariners not assigned to a watch, are assigned to work during eight (8) hours of duty between 0800 and 1700, Monday through Friday.
f. Flooding of quarters or common areas due to bilge or sewage backup not repaired within 24 hours.
2.2.18.2 When a vessel is in port and declared uninhabitable, no employee will be allowed to live on board. Individual quarters may be deemed uninhabitable when the respective quarters have been painted, the paint is not absolutely dry, and other suitable quarters are not furnished aboard. It is also not intended that any wage mariner shall be assigned to sleep in a flooded berthing area.
2.2.19 On repairs or overhauls of existing equipment, follow
Original Equipment Manufacturer’s (OEM’s) recommendations for parts and service in such a manner that the manufacturer’s warranty on parts and labor is not voided. Unless specified elsewhere in the detail specification, all replacement parts shall be new parts from the OEM.
2.2.20 Provide a copy of ABS-approved welding procedures and
maintain a list of currently qualified welders.
2.2.21 Develop, in consultation with the American Bureau of
Shipping (ABS) Surveyor, a written survey schedule that lists the items to be inspected and the scheduled dates and times of the inspections. Submit the survey schedule to the COR within 48 hours after the start of the contract performance period.
Provide the survey schedule with all initial inspections required by the ABS Surveyor. In addition, schedule the services of an ABS Surveyor as required by ABS for performing inspections of all new installations, hull modifications, tank inspections, gauging inspections, and load tests. NOAA will pay for all ABS surveys under a separate purchase agreement with
ABS.
2.2.22 These Detailed Specifications are a combination of
performance specifications and design specifications.
Whenever possible, the Government has provided performance specifications, giving the Contractor the opportunity to accomplish the work requirements as best as he or she sees fit, while providing a fully functional repair and/or equipment/system installation in accordance with all work requirements. When specific details are required, the Government will provide design/detail specifications; this will be more the exception, than the rule.
2.2.23 Frame numbers and space names are derived from ship’s
drawings.
2.2.24 All equipment changes and space modifications over the ship’s life span may not all be reflected in the referenced drawings. Contractors are encouraged to review all referenced drawings and to perform a field inspection of the ship prior to submitting a bid.
2.2.25 The Order of Precedence when interpreting these
Government specification and requirements is as follows:
Detailed Specifications, Standard Specifications, General Requirements, Drawings, General Provisions, referenced industry standards, and others.
2.2.26 Zinc chromate paint is known to exist on the ship
on interior steel surfaces from original construction.
Contractor is advised to anticipate encountering zinc chromate paint in the course of this repair work and to take necessary precautions to minimize hazards associated with same (i.e., use solvent to remove zinc chromate from suspected areas before cutting, grinding, etc.).
2.2.27 The following descriptive data of the ship
is provided for information:
Length, Overall...................224’ 0” Length, Between Perpendiculars....194’ 0” Beam, Molded...................... 43’ 0” Mean Draft, Loadline.............. 15’ 1” Displacement, Loadline............2311.5 LT Displacement, Lightship...........1591.2 LT Cruising Speed.....................11 knots Officer & Crew Size Scientists and Technicians Electric Service...................450 VAC, 60 Hz, 3 PH, 800 Amp Service Propulsion.........................Diesel electric, twin screw
2.2.28 NOAA Ship Okeanos Explorer maintains ABS
approved class certificate identified with the following:
Official Number - CG023672
ABS ID - 901987
IMO NUMBER – 8835114
2.3 Government Furnished Material
ITEM QTY DESCRIPTION EST COST
15141 1 Carrier 5H86 air conditioning compressor $15,000 55122 1 Cooling coil $11,000 53621 49 Mission UPS batteries $15,000 51711 1 Seatel 5012 VSAT $XX,XXX
3.0 Basic Items
3.1 ABS INTERMEDIATE HULL SURVEY 7 INSPECTION (10911)
3.1.1 References
3.1.1.1 NOAA Standard Specification MOC-100-1A, "ABS Load Line Survey"
3.1.1.2 Drawing No. OE-601-101, "General Arrangement"
3.1.1.3 Drawing No. OE-123-101, "Okeanos Explorer Tank Sounding Tables”
3.1.2 Government Furnished Material
3.1.2.1 None.
3.1.3 Requirements
3.1.3.1 Schedule the services of an American Bureau of Shipping (ABS) surveyor to accomplish all inspections required under Intermediate Hull Survey No. 7 (see Note 3.1.5.1). Government will compensate ABS directly for survey costs under a separate purchase order.
3.1.3.2 Assist ship’s Chief Engineer in transferring ballast water from one ship’s ballast tank to another as necessary to accomplish tank boundary inspections. Boundary inspections shall be accomplished under a full head of liquid. Use existing ballast water or fresh water provided by Contractor for ballast tank boundary inspections.
3.1.3.3 Open and prepare the following ballast tanks and void spaces for inspection in accordance with all requirements of Reference 3.1.1.1, section 3.4, “Tank Inspections.” See Note 3.1.5.2.
“Cleaning” shall include power washing followed by removal of all residual water and power washing residue. In addition to “Safe for Entry” requirements of paragraph 3.4.1, all tanks scheduled for opening and inspection shall be certified “Safe for Hot Work” by a Marine Chemist. Erecting scaffolding or temporary staging inside tanks, if required, will be accomplished as additional work.
Ballast Tanks Fore Peak Tank (4-B-0-W) Ballast Tank (4-23-0-W) Ballast Tank (4-23-2-W) Ballast Tank (4-23-3-W) Anti-Roll Dump Tank (4-40-0-W) Ballast Tank (4-52-0-W) Anti-Roll Tank (2-72-0-W) Ballast Tank (4-86-2-W) Ballast Tank (4-86-1-W) Aft Peak Tank - P (3-94-2-W) Aft Peak Tank - S (3-94-1-W)
Void Spaces Void (4-6-0-V) Speed Log Trunk (4-23-1-T) Depth Finder Transducer Trunk (4-32-1-T) Void (4-34-0-V) Void (4-34-01-V)
While not required to be inspected by ABS for the Intermediate Survey, accomplish the same cleaning procedures on clean the following waste water tank Laundry Room Waste Water (3-23-1-W).
3.1.3.4 Accomplish all inspections jointly with ABS surveyor and COR (or other designated government representative) present. Contractor shall prepare tanks for survey and shall bear cost of re-survey due to improper or inadequate vessel preparation. Neither the Government nor the Contractor shall be compensated by the other for delay of a scheduled survey if the delay is caused by ABS for which neither Contractor nor Government is at fault.
3.1.3.5 Open all vent valves associated with the subject tanks and voids and prepare the valve components for inspection by ABS surveyor.
Any valve components requiring repair or renewal will be handled as additional work. Re-assemble and re-install valves following inspection.
3.1.3.6 Close up and perform 2 psi air tests on all opened tanks and voids in accordance with paragraphs 3.4.7 and 3.4.8 of Reference
3.1.1.1. Air tests must be accomplished using a manometer to protect tanks and voids from over-pressurizing. Air test not required on Laundry Room Waste Water Tank (3-23-1-W).
3.1.4 Quality Assurance
3.1.4.1 As per Reference 3.1.1.1.
3.1.5 Notes
3.1.5.1 Intermediate Hull Survey inspection requires Ultrasonic Testing (UT) of “suspect areas.” There are no indications of suspect areas from previous ABS surveys. The tanks and voids were last inspected by ABS during drydocking in February 2016 and found to be in good condition. If UT readings are found to be required, they will be accomplished as additional work.
3.1.5.2 The local ABS surveyor may elect not to inspect certain tanks or voids at his/her discretion; however, that does not automatically relieve Contractor of the requirements herein to accomplish the preparation for inspection of all tanks and voids listed in paragraph
3.1.3.3. Contractor and COR may agree to an equitable price
adjustment under such circumstances.
3.1.5.3 Additional information on tank locations and capacities may be found in References 3.1.1.2 and 3.1.1.3.
END OF ITEM
3.2 BOW THRUSTER MOTOR AND MOTOR COOLER CLEANING (12371)
3.2.1 References
3.2.1.1 NOAA Standard Specification MOC-300-1, “Overhaul of
Electrical Rotating Machinery”
3.2.1.2 Technical Manual GE GEK-91658 “GE752 High – Torque
Horizontal Drilling Motor"
3.2.2 Government Furnished Equipment
3.2.2.1 None
3.2.3 Requirements
3.2.3.1 Provide the on-site services of a manufacturer’s factory certified field service engineer for all work in this item (see Note 3.2.5.1).
3.2.3.2 Conduct an operational test prior to accomplishing
repair work. Ship’s force will operate machinery. Measure and record all electrical parameters (i.e., megger and surge test).
Photograph the condition of the commutator before, during, and after cleaning and repairs.
3.2.3.3 Prior to the start of work, contact the Chief Engineer to coordinate the implementation of the ship’s Lock Out/Tag Out Program for the entire performance period of this item.
3.2.3.4 Disconnect the bow thruster electrical motor.
Disconnect the bow thruster cooler system.
3.2.3.5 Remove all interferences in way of the bow thruster
motor access: cooler ventilation and ductwork, and the auxiliary sea water cooling connections to the bow thruster cooler, and insulation.
3.2.3.6 Remove the cooling system cooler to a shop for cleaning and overhaul. Disassemble the cooler and remove all debris, ensuring all tubes are clean water flow in unrestricted. Re-assemble cooler, renewing all gaskets, washers, o-rings, and seals. Treat cooler ends with RidLime, or equal.
3.2.3.7 Clean the bow thruster motor in place in accordance with Reference 3.2.1.1 using information in Reference 3.2.1.2 for guidance. Remove all debris, oil, carbon dust, and grease.
3.2.3.8 Apply Class H varnish on exposed electrical wiring
assemblies in accordance with manufacturer’s instructions. Re-measure and record all electrical parameters.
3.2.3.9 Clean and polish the commutator using caution to
protect insulating assemblies.
3.2.3.10 Restore bow thruster sleeve and housing to as found
configuration.
3.2.3.11 Install reconditioned cooler, auxiliary seawater
cooling piping, ventilation ductwork and all disturbed interferences.
3.2.3.12 Prepare and coat all disturbed surfaces to match
surrounding areas.
3.2.3.13 Reconnect bow thruster motor and bow thruster
ventilation cooling system.
3.2.3.14 Ship’s force will assist in clearing electrical
lockout/tagout devices.
3.2.3.15 Perform operational test of the bow thruster motor and bow thruster cooling system with the COTR and ABS witnessing.
Ship’s Force will operate equipment. Measure and record all electrical parameters (i.e., megger, surge test). Photograph commutator after repairs and provide electronic images to the
COTR.
3.2.4 Quality Assurance
3.2.4.1 Operational tests to bow thruster motor and bow thruster cooling system are noted above.
3.2.5 Notes
3.2.5.1 One recommended source for GE tech rep support:
N. Waller & Associates 6300 Grelot Rd. Ste G-204 Mobile, AL 36609 Attn: Buddy Waller Tel: (251) 634-8100 Cell: (251) 421-7040 e-mail: N_Waller@prodigy.net
3.2.5.2 Bow Thruster Motor Nameplate data is as follows:
General Electric 752 High Torque Armature Volts – DC – 750 Armature Amps DC – 1185 Type Winding – Shunt Base RPM – 1040 Max RPM – 1800 Shaft HP – 1130 Torque 5705 lb. –ft.
Field amps – 60 Insulation Class H
3.3 ENGINEERS’ OFFICE (1-62-0-Q) VENT DUCT and CHILLED WATER
PIPING RE-INSULATION (15121)
3.3.1 References
3.3.1.1 Drawing No. 512-6233801, “HVAC Main Deck.”
3.3.1.2 Drawing No. 514-6629787, “Chilled Water System
Diagram.”
3.3.1.3 Drawing No. 512-6233799, “HVAC Standard Notes and
Details.”
3.3.2 Government Furnished Material
3.3.2.1 None.
3.3.3 Requirements
3.3.3.1 Remove all existing insulation from the ventilation
ducts and chilled water piping in the Engineers’ Office (1-62- 0-Q). This space is located on the Main Deck, starboard side, between frames 62-67. Reference 3.3.1.1 shows the HVAC system on the Main Deck. Sheet 4 of that drawing show the details of the ventilation ductwork in Engineers’ Office (1-62-0-Q).
Reference 3.3.1.2 (Chilled Water System Diagram) shows two chilled water pipes (one 3-inch and one 2½-inch) running through the space.
3.3.3.2 Following is a detail from Reference 3.3.1.1 with the ventilation ducting in the Engineers’ Office highlighted in yellow. See Note 3.3.5.1.
3.3.3.3 Visually inspect the exposed galvanized steel duct
material and chilled water piping. Provide a Condition Report to the COR with repair recommendations, if any. Duct and piping repairs, if required and approved by the Contracting Officer, will be the subject of additional work.
3.3.3.4 Re-insulate all ductwork and chilled water piping in
Fan Room 02-34-1-Q as original in accordance with References 3.3.1.1, 3.3.1.2, and 3.3.1.3.
3.3.3.5 Apply identifying stencils to the exterior of the
insulation on the ductwork and chilled water piping, same as existing.
3.3.4 Quality Assurance
3.3.4.1 Visual inspection.
3.3.5 Notes
3.3.5.1 Contractor is advised that Reference 3.3.1.1 is the
original as-built drawing and may not reflect modifications made to ducting during conversion or at other times throughout the life of the ship. Reference 3.3.1.1 is provided as guidance only. The intent of this item is to renew all insulation on ducts and chill water piping in the space, whether it appears on the drawing or not.
3.4 GAUGE AND INSTRUMENT CALIBRATION (15041)
3.4.1 References
3.4.1.1 EX Gauge List 2017 (in .pdf format)
3.4.2 Government Furnished Equipment
3.4.2.1 None
3.4.3 Requirements
3.4.3.1 This item describes the requirements to inspect and
calibrate the ship’s pressure gauges, thermometers, and other instrumentation.
3.4.3.2 Prior to the start of work, contact the Chief Engineer to coordinate the implementation of the Tag Out Program for the entire performance period of this item.
3.4.3.3 Engage the services of a company that specializes in
the calibration of instruments and gauges (see Note 3.4.5.1) to accomplish the perform the periodic calibration of the ship’s gauges and instruments.
3.4.3.4 Calibrate and adjust all the devices listed in
Reference 3.4.1.1. In addition, calibrate the two (2) salinometers (Alfa Laval part no. DS-20, range 0.5 – 20 ppm), located in the Generator Room.
3.4.3.5 Calibrate gauges, meters, thermometers, instruments and accessories in place, where possible.
3.4.3.6 Renew all seals and gaskets. Renew all defective
terminal lugs and fasteners, where applicable, with new components.
3.4.3.7 Submit a condition report to the COR identifying any
gauges or instruments found that are not listed on Reference
3.4.1.1 as well as all devices that will require replacement or repair prior to being able to be calibrated. Upon approval of the Contracting Officer, such additional instrumentation and repairs will be the subject of additional work.
3.4.3.8 Calibrate gauges, meters, thermometers, and all other instrumentation using a transfer measurement standard, traceable to the National Institute of Standards and Technology (NIST) and in accordance with the manufacturer’s specifications. Use standards which have an accuracy level at least four times that of the instrument being calibrated.
3.4.3.9 Provide a certificate of calibration for each
instrument which includes the date, manufacture, model and serial number, full name of the individual performing the calibration, and traceability number of the standard used in the calibration.
3.4.3.10 Prove to the COR and/or the Chief Engineer that all
gauges, meters, thermometers and instrumentation that were worked are operational and connections are tight.
3.4.3.11 Upon completion of all work, affix a tamper-proof
calibration label denoting the name of the calibrating facility and the date of the calibration to the face of the device.
Place labels over calibration adjusting screws, where applicable. Calibrations shall be valid for two years following date of calibration.
3.4.4 Quality Assurance
3.4.4.1 Calibration standards are noted in paragraph 3.4.3.7.
3.4.5 Notes
3.4.5.1 A potential source for maintenance and calibration of the gauges and instruments:
Mobile Instrument Co., Inc.
745 Lakeside Dr.
Mobile, AL 36693 Tel: (251) 660-7474
3.5 SCR BREAKER CLEANING and TESTING (13241)
3.5.1 References
3.5.1.1 NOAA Standard Specification AMC-300-2, “Circuit Breaker Overhaul.”
3.5.1.2 Pearl Reconditioning Standards Section 6000 Tables
3.5.2 Government Furnished Material
3.5.2.1 None.
3.5.3 Requirements
3.5.3.1 Provide the on-site services of a manufacturer’s
factory certified field service engineer for all work in this item (see Note 3.5.5.1).
3.5.3.2 Prior to the start of work, contact the Chief Engineer to coordinate the implementation of the ship’s Lock Out/Tag Out Program for the entire performance period of this item.
3.5.3.3 Remove the three General Electric Silicon Controlled
Rectifier (SCR) breakers from the ship’s 600 Volt panel and take to an electrical shop for inspection and testing (Port Propulsion Motor, Stbd Propulsion Motor, Bow Thruster).
3.5.3.4 Clean and overhaul the SCR circuit breakers in
accordance with Reference 3.5.1.1 and the following:
3.5.3.4.1 Open the case. Inspect all internal parts for signs of overheating, deterioration, excessive carbon buildup, or corrosion.
3.5.3.4.2 Inspect contacts for signs of excessive wear cracks or pitting.
3.5.3.4.3 Clean all metal parts of contamination and corrosion.
3.5.3.4.4 Clean/degrease operating mechanism per manufacturer’s guidelines.
3.5.3.5 Accomplish the following inspections and tests of the SCR circuit breakers. Prepare an Inspection and Test form for each breaker and record results of all the following tests and inspections on the form:
3.5.3.5.1 Inspection
3.5.3.5.1.1 Case
(A) Ensure the labels are legible
(B) Inspect the case for cracks, chips and unused holes
(C) Inspect case for signs of overheating
(D) Inspect all control wire for signs of deterioration, overheating, or damage
(E) Inspect for missing parts
(F) Record as-found trip settings
3.5.3.5.1.2 Lugs
(A) Inspect for tightness
(B) Inspect for signs of overheating
(C) Inspect plating
(D) Inspect for signs of cross-threads or stripped threads
3.5.3.5.1.3 Phase Separators
(A) Inspect for dust, dirt, or foreign materials
(B) Inspect for chips, cracks, or deterioration
(C) Inspect for overheating
(D) Ensure phase separators match application
3.5.3.5.1.4 Arc Extinguishers
(A) Inspect for loose or missing parts
(B) Inspect for dust, dirt, foreign material, cracks, corrosion, chips, or signs of overheating
(C) Inspect for excessive deterioration or carbon buildup on the separator
3.5.3.5.1.5 Contacts
(A) Inspect for excessive deterioration, heat
(B) Inspect for cracks, chips, or pitting
(C) Check for proper alignment/seating in the closed position
3.5.3.5.1.6 Devices
(A) Inspect all devices such as shunt trips, bell alarms, undervoltage releases, and auxiliary switches for missing or defective screws, bolts, nuts, fasteners, or keepers
(B) Inspect all devices for signs of overheating and deteriorated insulation
(C) Check all devices for loose or defective terminal connectors
(D) Check all devices for proper operation range
(E) Inspect fuse indicator trip unit for missing or defective screws, bolts, nuts, fasteners or keepers
(F) Inspect fuse indicator trip unit for signs of overheating and deteriorated insulation
(G) Check fuse indicator trip unit for loose or defective terminal connectors
(H) Check fuse indicator trip unit for proper operation range
(I) Ensure you cannot close the breaker, and the breaker trips with the fuse indicator trip activated, on all phases
3.5.3.5.1.7 Control Wiring
(A) Inspect for overheating
(B) Inspect for damage or deteriorated insulation
(C) Check for loose or defective terminal connectors
3.5.3.5.1.8 Torque
(A) Check all screw and bolt connection for the proper torque per manufacturer’s recommendations or industrial standards
3.5.3.5.2 Operation
3.5.3.5.2.1 Manually operate (close – open) circuit breaker
five (5) times while checking for proper operation of the operating mechanism
3.5.3.5.2.2 Verify proper mechanical operation of all auxiliary device features of the circuit breaker
3.5.3.5.3 Tests
3.5.3.5.3.1 Insulation Resistance
(A) Perform an insulation resistance test at test values specified in Reference 13241.1.2 Table 2 as follows on all phases:
(1) Circuit breaker in the open position
(a) Line to Load
(b) Line to Ground
(c) Load to Ground
(d) Phase to Phase on Line Side
(e) Phase to Phase of Load Side
(2) Circuit breaker in the closed position
(a) Phase to Phase
(b) Phase to Ground
(3) Correct for temperature; use Reference 3.5.1.2 Table 11 if necessary
(4) Performa an insulation resistance test on all control wiring at test values specified in Reference 3.5.1.2 Table
(B) Compare results to manufacturer’s recommendations, industrial standards (Reference 3.5.1.2 Table 2), or company guidelines
3.5.3.5.3.2 Contact Resistance
(A) Perform a contact resistance, millivolt drop test, or watt loss test from line to load on each phase of a closed circuit breaker in accordance with company guidelines
(B) Compare results to manufacturer’s recommendations, industrial standards, or company guidelines.
3.5.3.5.3.3 Time Overcurrent (Thermal) Trip Test
(A) Perform a time overcurrent trip test (recommend using 300% of range) to the circuit breaker, if applicable
(B) Use specific length and size of wire as per manufacturer’s guidelines, NEC standards, or company guidelines
(C) Compare results to manufacturer’s recommendations, industrial standards (Reference 3.5.1.2 Table 3), or company guidelines
3.5.3.5.3.4 Instantaneous Overcurrent (Magnetic) Trip Test
(A) Perform an instantaneous overcurrent trip test to the circuit breaker, if applicable
(B) Compare results to manufacturer’s recommendations, industrial standards (Reference 3.5.1.2 Table 4), or company guidelines
3.5.3.5.3.5 Shunt Trip Test
(A) Close circuit breaker
(B) Connect appropriate voltage source to shunt trip input leads
(C) Increase voltage until shunt trip unit operates
(D) Compare results to manufacturer’s recommendations or company guidelines for the shunt trip pickup range
3.5.3.5.3.6 Undervoltage Unit Test
(A) Connect voltage source to undervoltage input leads
(B) Apply rated voltage to the undervoltage unit
(C) Close circuit breaker
(D) Decrease voltage until undervoltage unit operates and trips the circuit breaker
(E) Compare results to manufacturer’s recommendations or company guidelines for the undervoltage unit dropout range
3.5.3.6 Submit a condition report to the COR with all findings and recommendations. Any parts requiring replacement or repairs found necessary will be the subject of additional work and must be approved by the Contracting Officer.
3.5.3.7 Reinstall and reconnect SCR breakers.
3.5.3.8 Submit two copies of the completed Inspection and Test form for each breaker to the COR.
3.5.4 Quality Assurance
3.5.4.1 Per Reference 3.5.1.1
3.5.5 Notes
3.5.5.1 One recommended source for GE tech rep support:
N. Waller & Associates 6300 Grelot Rd. Ste G-204 Mobile, AL 36609 Attn: Buddy Waller Tel: (251) 634-8100 Cell: (251) 421-7040 e-mail: N_Waller@prodigy.net
3.5.5.2 SCR breakers are General Electric 800 Amp Tri-Break
breakers with UV trip and auxiliary coil.
3.5.5.3 Some photographs of the SCR breakers on Okeanos
Explorer and sister ship Gordon Gunter follow:
3.6 0-1 and 0-2 Deck Passageway Deck Covering Renewal (16341)
3.6.1 References
3.6.1.1 PPI NBR 63421-006H (Rev 04), Preservation Process
Instruction (PPI) for Cosmetic Polymeric Deck Coverings Type II, Classes 1 & 2 for Wet and Dry Interior Spaces
3.6.1.2 Navy MIL-D-3134J, Deck Covering Materials
3.6.1.3 Drawing No. OE-601-101, “NOAA Ship Okeanos Explorer
General Arrangement”
3.6.2 Government Furnished Equipment
3.6.2.1 None.
3.6.3 Requirements
3.6.3.1 Engage the services of a deck coating specialist
certified to apply the poured rubber deck system as described in this specification (see Note 3.6.5.1).
3.6.3.2 Replace the deck covering in the 0-1 Deck Passageway
(01-10-0-L) and the 0-2 Deck Passageway (02-20-0-L with a Poured Rubber deck covering per the following requirements. The following diagrams are taken from Reference 3.6.1.3 and show the subject areas on the 0-1 and 0-2 Decks respectively highlighted in yellow:
3.6.3.2 Prove all deck drain(s) in the 0-1 and 0-2 Deck
Passageways to be clear and free flowing. Plug the drain(s) to preclude introduction of debris resulting from this work item.
Upon completion of the decking renewal, remove the plug(s) and again prove the drain(s) to be clear and free flowing. The COR shall witness testing of all drains.
3.6.3.3 Submit a condition report to the COR listing any
drain(s) found to be obstructed. Clearing such drains, if determined to be necessary by the COR, shall be handled as additional work subject to the approval of the Contracting Officer.
3.6.3.4 Install protective covering to protect the vessel's
equipment and to contain the dust generated by this work item within the Passageway areas. Seal all stateroom doors, ladder wells and hatches and post signs to prevent accidental access from disturbing the new deck covering while drying. The COR will approve the protective covering prior to the start of productive work.
3.6.3.5 Remove the existing deck tiles and rubber cove
moulding. Chip up and remove the existing underlayment in its entirety. Remove debris from the vessel and properly dispose of it on a daily basis.
3.6.3.6 Power tool clean the entire deck, the bulkheads up to a line 4 inches above the deck, as well as all foundations, clips for equipment and retainer rings around deck drains, reach rods, sounding tubes, scuttles, and hatches to bare metal in accordance with Reference 3.6.1.1. Blow down and/or vacuum the compartment to remove all dirt and dust generated by the surface preparation activities.
3.6.3.7 Inspect the surface preparation with the COR.
Inspection shall include the condition of all permanently attached fixtures in way of the deck covering installation.
Upon approval of the surface preparation by the COR, apply one
(1) coat of 150 zinc primer or equivalent product per flooring underlayment manufacturer's recommendations to all prepared surfaces. The primer shall be 3-4 mils DFT. COR to witness DFT readings.
3.6.3.8 Submit a condition report to the COR listing
deteriorated foundations, deck drain retainer rings, etc., found during the inspection after all power tool cleaning has been completed. Additional repairs, if deemed necessary by the COR and approved by the Contracting Officer, shall be the subject of a change order.
3.6.3.9 Upon approval by the COR, wipe down the primed surfaces with solvent. When dry, install ultra lightweight underlayment similar to Epmar 1290. The underlayment shall be a minimum of thickness per manufacturer's recommendations and shall fair-in irregularities in the deck including weld seams, depressions, etc., and be coved up the bulkheads 4 inches. Total thickness of the underlayment shall be dependent upon, and adjusted upward as necessary, to conform to the rubber deck covering thickness requirements as set forth in paragraph 16341.3.10. In way of the transition from the passageway into the Medical Treatment Room, underlay height must be adjusted to provide a smooth transition from the passageway into the Medical Treatment Room where the new deck covering will meet the existing remaining tile.
Note: Ultra light weight underlayment, poured rubber membrane decking, and sealer are to be designed for installation as a complete deck cover solution. All materials shall be specifically intended for shipboard use on steel decking and are to be of suitable quality to stand up to heavy foot traffic.
3.6.3.10 Upon inspection and approval of the underlayment by
the COR, install rubber deck membrane material (color to be determined by ship’s force) similar to American Safety MS1600 in accordance with References 3.6.1.1 and 3.6.1.2. The base coat shall be a minimum of ¼ inch thick but shall not exceed ½ inch thick. The thickness of the rubber basecoat shall be maintained within these limits with no allowable deviation. All flooring shall be sloped for positive drainage to the deck drains and shall be coved up the bulkheads 4 inches. The finished surface shall be even and free of pour marks or settling irregularities.
NOTE: Poured decking must be pre-colored, painting the rubber decking after being poured will not be acceptable.
Ship’s force will determine the color.
3.6.3.11 When cured, prepare surface to a smooth and fair
profile. Final surface shall be nonporous, smooth and free of pits, spalls, crevices and pour marks. Apply mixed white and gold colored flakes, uniformly distributed, firmly embedded and visible at the surface. Apply low profile texture coat and 3 coats of sealer similar to American Safety SC100. Cracks or voids found in the urethane or sealant shall be rejected as defects. Such defects shall not be patched. Acceptable corrective action shall be removal and re-installation of the sealer and subsequent layers.
3.6.3.12 When surface preparation of the rubber deck is
completed, blow-down and vacuum the entire compartment, including protective covering and equipment and fixtures in the compartment.
3.6.3.13 Clean and paint disturbed surfaces to match the
surrounding areas.
3.6.3.17 Remove all protective covering. Clean the
compartment(s) and leave in a condition ready for use and meeting sanitary requirements. The COR shall inspect all areas after cleaning to be free of haze, film or other surface contamination on any surfaces.
3.6.4 Quality Assurance
3.6.4.1 Test the drainage in the passageways. Prove that the
drainage is positive and without low spots which would tend to collect water.
3.6.4.2 In accordance with References 3.6.1.1 and 3.6.1.2.
3.6.5 Notes
3.6.5.1 One recommended source for deck renewal work:
Surface Technologies Corp.
6607 Hwy 90 East Moss Point, MS 39563 Attn: Elmer Headrick Tel: (228) 475-6777 Cell: (228) 218-9375 e-mail: elmerstc@cableone.net
3.7 ANNUAL FIRE DETECTION and SUPPRESSION SYSTEMS INSPECTION
and FIRE DETECTION PANEL TROUBLESHOOTING (19851)
3.7.1 References
3.7.1.1 Drawing OE-555-001, Rev A, “Fire Control Plan”
3.7.1.2 Drawing OE-436-001, “Fire & General Alarm System
Modifications”
3.7.1.3 T-AGOS 13 Drawing 555-6233815, Rev C, “Fire
Extinguishing System Diagram”
3.7.1.4 T-AGOS 13 Drawing 436-6233675, Rev H, “Fire & Smoke
Detection System”
3.7.1.5 T-AGOS 13 Drawing 436-6233675, Rev H, “Fire & Smoke
Detection System” Redline
3.7.1.6 Siemens Marine Fire Detection System Manual, System 3TM Control Panel.
3.7.1.7 Cut sheet for Siemens DI-3, DI-A3 and DI-B3 Ionization Smoke Detector.
3.7.2 Government Furnished Material
3.7.2.1 None
3.7.3 Requirements
3.7.3.1 Annual Fire Detection and Suppression Systems
Inspection
3.7.3.1.1 All personnel (shop or sub-contractors) are to be
trained at a manufacturer’s approved course and specialized in the inspection and repair of fixed and portable CO2, Halon, AFFF, dry chemical, fire main and sprinkling systems and equipment and be certified by the American Bureau of Shipping (ABS) to conduct these inspections. See Note 3.7.5.1 for a recommended source.
3.7.3.1.2 Portable Extinguishers: Inspect and weigh all
portable extinguishers identified in Reference 3.7.1.1, including the discharge hose. Check the condition of the powder in dry chemical type extinguishers.
3.7.3.1.2.1 Submit a report to the COR indentifying the size
and number of extinguishers requiring recharging or hydrostatic testing.
3.7.3.1.2.2 Any extinguisher found to be rejected, for whatever reason shall be set aside. Submit a report to the COR identifying the extinguisher(s) found to be rejected and the reason(s) why.
3.7.3.1.2.3 Upon completion, return all portable extinguishers to their designated stations (or stowage locations in the case of spares).
3.7.3.1.3 Fixed CO2 Systems: Port and Starboard Main Motors
(direct inject) and Paint Locker.
3.7.3.1.3.1 Inspect and weigh fixed CO2 cylinders identified in Reference 3.7.1.3.
3.7.3.1.3.2 Demonstrate all interlocks, shutdowns, time delays (see Note 3.7.5.5), automatic fire dampeners and controls operate correctly and verify intake and exhaust fan shutdowns, and main motor breaker trips (Note: Main Motors must be online to verify breakers trip).
3.7.3.1.3.3 Submit a report to the COR identifying the size and number of cylinders requiring recharging or hydrostatic testing (if any).
3.7.3.1.3.4 Inspect hoses between fixed cylinders and the
distribution piping. Submit a report to the COR identifying any issues found and recommendations.
3.7.3.1.3.5 Visually inspect all fixed piping, nozzles and
valves to ensure their satisfactory material condition. Connect an inert gas (nitrogen) to the system and blow-out the piping to prove it is clear.
3.7.3.1.4 Fixed Halon Systems: Main Generator Room, Propulsion Motor Room, AC Machinery Room, Emergency Generator Room, and Bow Thruster Compartment.
3.7.3.1.4.1 Inspect all fixed Halon cylinders identified in
Reference 3.7.1.2.
3.7.3.1.4.2 Demonstrate that all interlocks, shutdowns, time
delays (see Note 3.7.5.5), automatic fire dampeners and controls operate correctly and verify that intake and exhaust fans shutdown. Coordinate with the COR to start the Ship Service Diesel Generators (SSDG’s) for testing (Note: SSDG’s must be running to test shutdowns).
3.7.3.1.4.3 Inspect hoses between fixed cylinders and the
distribution piping. Submit a report to the COR, identifying any issues found and recommendations.
3.7.3.1.5 Galley Gaylord Hood System (ProTex II MCH2)
3.7.3.1.5.1 Accomplish inspection and testing of the Galley
Gaylord Hood system and associated heat sensing vent closure devices in the exhaust ducting, including over the oven, the fryer, and the griddle.
3.7.3.1.5.2 Prepare a Certificate of Servicing and report, listing the Gaylord Hood System and heat sensing vent closure devices, equipment, and components inspected and tested, and the results. Submit the original and two (2) copies of the service report to the COR.
3.7.3.1.6 Seafire System.
3.7.3.1.6.1 Inspect and weigh the Seafire System bottle on the flame locker in the Upper Motor Room.
3.7.3.1.7 Fire Detection System (see Refs. 3.7.1.4 and 3.7.1.5)
3.7.3.1.7.1 Test all smoke and/or fire detection systems and
demonstrate their proper functioning. Upon completion of the tests and demonstrations, all systems shall be restored to normal operating configuration and left in a ready for use condition.
3.7.3.1.7.2 Testing shall include all smoke detectors using
spray smoke and all heat detectors.
3.7.3.1.7.3 Inspect all alarm bells for corrosion and verify
proper operation.
3.7.3.1.7.4 Submit a condition report to the COR with test
results and any recommendations.
3.7.3.1.8 SCBA Respirators and Cylinders
3.7.3.1.8.1 Conduct a visual inspection of eighteen (18) SCBA Cylinders.
3.7.3.1.8.2 Conduct a flow test on ten (10) SCBA respirators.
3.7.3.1.8.3 Submit a condition report to the COR with findings and any recommendations.
3.7.3.1.9 After completion of testing, all fire-fighting
systems shall be reconnected, the cylinders properly secured in the bank, and the system left in a ready for use condition.
3.7.3.1.10 All extinguishers, hoses and fixed systems shall
have tags attached indicating the date of service and the name of the company performing the servicing.
3.7.3.1.11 Prepare a Certificate of Servicing, listing all
portable extinguishers and fixed systems examined and tested and the results of those tests and inspections. Deliver the original and two (2) copies of the report to the COR.
3.7.3.2 Fire Detection Panel Troubleshooting
3.7.3.2.1 Three (3) new zones were added to the fire detection system in 2014. Over the last several months, the system has experienced multiple trouble alarms that, when silenced go away, then come back. The ship has attempted to troubleshoot and repair the system with the assistance of a tech rep remote from the ship and has had some success, but the issue has not been fully resolved. The situation as it stands now is that the ship has jumped out the two modules that control the 3 new zones.
Therefore, effectively, the 3 new zones are not being monitored.
That seems to be the only way to eliminate the nuisance trouble alarms.
3.7.3.2.2 Provide the services of an experienced, authorized
Pyrotronics System 3TM technical representative (tech rep) to troubleshoot and repair the fire detection system.
3.7.3.2.3 For bidding purposes, assume the tech rep will be
onboard ship, performing troubleshooting and repair activities for two full days (in addition to travel to/from city of origin).
3.7.3.2.4 If additional time or materials are required, submit a condition report to the Contracting Officer’s Representative (COR). Any such additional work must be approved in advance by the Contracting Officer.
3.7.4 Quality Assurance
3.7.4.1 Results of troubleshooting and testing.
3.7.5 Notes
3.7.5.1 One recommended source for this work is:
Hiller Systems, Inc.
3751 Joy Springs Drive Mobile, AL 36693 Tel: (251) 661-1275
3.7.5.2 Adequate fire protection must remain on the ship at all times during the performance of this item. No more than 30% of the portable extinguishers are to be removed from the vessel at any one time. No fixed fire-fighting system shall be left in an inoperable condition overnight.
3.7.5.3 Reference 3.7.1.2 shows system modifications that were made during the ship’s 2008 conversion.
3.7.5.4 Reference 3.7.1.5 is a redline of the original drawing, showing 3 zones added to the fire detection system in 2014 (total of 26 zones in the system).
3.7.5.5 Time delay standards are +20% / -0%. (Ref: 46 CFR
§193.05-10; §95.16-45(a)(2); NFPA 12, Section 9.4.3.2. For 30-second time delays, the maximum time allowed is 36 seconds. For 20-second time delays, the maximum time allowed is 24 seconds. The ship has 30-second time delays on Halon and 20-second time delays on the direct inject CO2.
3.8 GAYLORD HOOD EXHAUST DUCT RENEWAL (15122)
3.8.1 References
3.8.1.1 T-AGOS drawing 512-6233799, “HVAC Standard Notes and
Details”
3.8.1.2 T-AGOS drawing 512-6233801, “HVAC Main Deck”
3.8.2 Government Furnished Material
3.8.2.1 None.
3.8.3 Requirements
3.8.3.1 Remove the stainless steel overhead sheathing from the Galley overhead to the extent necessary to access the Gaylord Hood exhaust duct. Contractor, at his/her own discretion, may elect to cut access openings and install a series of hinged access doors, similar to those existing rather than wholesale removal/reinstallation of the overhead panels.
3.8.3.2 The following highlighted views of the Gaylord Hood
exhaust duct are taken from Reference 3.8.1.2.
3.8.3.3 Remove and scrap the entire run of ducting from flange at the Gaylord Hood connection (see Section 12-C above) to the flange at the 0-1 Deck penetration at approximately Frame 48½ (see Elevation 11-C above).
3.8.3.4 Templating off the old ducting and using References
3.8.1.1 and 3.8.1.2 for guidance, fabricate and install new ducting in place of that removed. Seal all joints to prevent condensation internal to the duct from leaking into the false overhead. Install a new ball valve for draining condensation in the exhaust duct, similar to that existing.
3.8.3.5 Install new insulation on the exterior of the new
ducting as original in accordance with References 3.8.1.1 and 3.8.1.2.
3.8.3.6 If overhead stainless…