DTMB-0427 Project Statement 26396.pdf
PDF 164 KB Posted
- Attached to
- 472/26396. SAA; WHVCF - Roof Replacements
- Solicitation number
- RFP 171 260000002683 1
- Issued by
- Michigan
About this file
This is a Project Statement issued by the Michigan Department of Technology, Management and Budget (DTMB), Design and Construction Division, on behalf of the Michigan Department of Corrections (MDOC), soliciting professional engineering services for mechanical and electrical repair work at the Women's Huron Valley Correctional Facility located at 3201 Bemis Road, Ypsilanti, Michigan. The project encompasses HVAC repairs to Calhoun and Dickinson buildings, with services required across multiple phases: Phase 100 (comprehensive system evaluation and study report), Phases 300-500 (design services), and Phases 600-700 (construction administration). A mandatory pre-proposal meeting is scheduled for Monday, October 5, 2026, at 10:30 a.m. at the facility. Proposals must be submitted to SIGMA VSS by Thursday, October 22, 2026, at 2:00 p.m. Eastern Time, with a maximum attachment size of 25 megabytes. The desired schedule includes design contract award in November 2026, completion of the Phase 100 report and design readiness by February 2027, construction contract award in March 2027, and construction commencement in April 2027. RFP questions must be submitted via email to Sheryl Ananich by 2:00 p.m. Eastern on Wednesday, October 14, 2026.
The contract will be awarded on a billable rate basis per the DTMB Sample Billable Rate Contract, with the total cost for all phases to be submitted as the bid amount. Contractor representatives attending the mandatory pre-bid walk-through must submit a Vendor/Contractor LEIN Request form five business days prior to the meeting date. Reimbursable expenses include sub-consultants, printing and reproduction, postage, and project travel exceeding 100 miles. The project requires compliance with all applicable federal codes and standards administered by the EPA, OSHA, and DOT, as well as state agencies including DCH, EGLE, DNR, and MIOSHA. Interested firms are encouraged to combine technical and cost proposals into a single attachment for submission through the SIGMA VSS electronic system.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| DTMB-0430 RFP Billable Rate 26396.pdf | ||
| LEIN Request 26396.pdf | ||
| SAMPLE Billable Rate Contract (Rev 04-25).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DTMB-0427 (R 04/26)
PROJECT STATEMENT
STATE OF MICHIGAN
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
State Facilities Administration Design and Construction Division
3111 West St. Joseph Street Lansing, Michigan 48909
FILE NUMBER
472/26396.SAA
PROPOSAL DUE DATE
Thursday, October 22, 2026, at 2:00 pm EASTERN
CLIENT AGENCY
MDOC
PROJECT NAME AND LOCATION
Women’s Huron Valley Correctional Facility – Calhoun & Dickinson HVAC Repairs
PROJECT ADDRESS (if applicable) 3201 Bemis Rd, Ypsilanti, MI 48197
CLIENT AGENCY CONTACT
Chris Severson
TELEPHONE NUMBER
517-230-9335
DTMB - DCD PROJECT DIRECTOR
Sheryl Ananich
TELEPHONE NUMBER
517-243-7605
WALK-THROUGH INSPECTION DATE, TIME, AND LOCATION:
A MANDATORY PRE-PROPOSAL MEETING will take place on Monday, October 5, 2026, at 10:30 a.m.
We will meet in the West Administration Lobby, have a 30 minute meeting in the Warden’s Conference Room, then go inside the secure perimeter and look at Calhoun and Dickinson.
MANDATORY (Check box if Mandatory)
LEIN CHECK (Dept. of Corrections ONLY) All contractor/vendor representatives attending a Pre-Bid Walk Through Meeting must submit a Vendor/Contractor LEIN Request five business days prior to the meeting date, (See the attached Vendor/Contractor LEIN Request form). Send the LEIN Request form, filled out and signed, by email to Daniel T. Smith & Sharon Frost at email addresses: SmithD76@michigan.gov & FrostS1@michigan.gov .The email “Subject” must include (Facility Name, Project Name, Date & Time of Pre-Bid Walk Through Meeting).
NOTE: An individual is only permitted to represent one bidder at a mandatory walk-through.
PROJECT DESCRIPTION/SERVICES REQUESTED:
The Department of Technology, Management and Budget (DTMB), on behalf of the Michigan Department of Corrections (MDOC), is requesting professional engineering services for mechanical and electrical repair work at Calhoun and Dickinson. Phase 100 Study Phase is required for undertaking a comprehensive evaluation of the existing mechanical and electrical systems serving each building. The existing HVAC systems have exceeded their anticipated service life and are experiencing numerous operational issues.
The Study Phase will document findings in a Study Report that will include recommendation options with estimates of probable cost. Once the scope of work is determined, Phase 300-700 services are desired to design, bid and oversee construction of the HVAC repairs per the DTMB Sample Billable Rate Contract.
Professional services shall also include, but are not limited to the following:
• Gathering and verifying all base information required for the proper design of the project in Phase 100 Study. All available documents including limited CAD files will be supplied to the successful firm.
• Design submittals for Phases 100, 300, 400, 500 for review at 50% and 90% milestones. Cost estimates are required with each submittal.
mailto:SmithD76@michigan.gov mailto:FrostS1@michigan.gov
• Phase 600 and 700 construction administration services to include running all construction progress meetings on a bi-weekly basis – one virtual Teams meeting per month and one on-site meeting per month.
• Gathering or preparing all data and design development information that shall ultimately be necessary for plans, submittals, and permit application considerations where required. Include as reimbursable expenses.
• Provide a proposed design schedule. Schedule shall be kept up to date through the project design.
• All testing throughout construction.
• Sub-consultants, printing/reproduction, postage, and project travel (over 100 miles) are to be included as a reimbursable expense.
Please NOTE:
• Proposal responses MUST be uploaded to SIGMA VSS.
https://sigma.michigan.gov/webapp/PRDVSS1X1/Advantage4
• Please enter the total cost for all phases as the bid amount.
• Firms are encouraged to combine their technical and cost proposals into one (1) attachment for proposal submission.
• Please remember that attachments can be no larger than 25mb.
• Do not wait until just before the 2:00 p.m. solicitation deadline to submit your proposal response.
SIGMA VSS will not allow a proposal to be submitted after 2:00 p.m., even if a portion of the proposal response has been uploaded.
• If you experience issues or have questions regarding your electronic submission, you must contact the SIGMA Help Desk for assistance prior to the 2:00 p.m., solicitation deadline. You may contact the SIGMA Help Desk by telephone at 517.284.0540 or toll-free at 888.734.9749. You may also email the SIGMA Help Desk at sigma-procurement-helpdesk@michigan.gov
• Please email the Design and Construction Contract Specialists if you are having SIGMA VSS issues. Please include your SIGMA ticket number and any supporting documentation (i.e., screenshots) to Anne Watros (WatrosA@michigan.gov) and Don Klein (KleinD4@michigan.gov).
• You may be asked by our contract specialists to email your proposal. Emailed submissions will require DCD approval and will be handled on a case-by-case basis.
• Approved emailed submissions MUST be received prior to 2:00 p.m. deadline to be considered responsive and responsible.
• Responses should not be emailed to the Project Director.
NIGP CODES
92531, 92533, 92567, 92595
DESIRED SCHEDULE OF WORK
Award of Design Contract in November 2026. Complete Phase 100 Report and Phase 300-500 design ready to bid in February 2027. Award construction contract March 2027. Construction to begin in April 2027.
ACCEPTING RFP QUESTIONS UNTIL:
Please do not submit online questions via VSS. ALL questions should be emailed to Sheryl Ananich at ananichs@michigan.gov address no later than 2:00 p.m., Eastern on Wednesday, October 14, 2026.
REFERENCE STANDARDS: This project will comply with all codes, standards, regulations, and workers' safety rules that are administered by federal agencies (EPA, OSHA, and DOT), state agencies (DCH, EGLE, DNR, and MIOSHA), and any other local regulations and standards that may apply.
This form is required to be a part of the professional service contract. (Authority: 1984 PA 431) Attachment(s) https://sigma.michigan.gov/webapp/PRDVSS1X1/Advantage4 mailto:sigma-procurement-helpdesk@michigan.gov mailto:WatrosA@michigan.gov mailto:KleinD4@michigan.gov mailto:ananichs@michigan.gov
File details come from the government source that posted it. Updated .