Response_to_Question_11-22-16.pdf
PDF 203 KB Posted
- Attached to
- TS Golden Bear General Contracting Work Federal contract opportunity
- Solicitation number
- DTMA9417Q00003
About this file
Question and Government Response
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_2_SF30.pdf | ||
| Amendment_1.pdf | ||
| 028.JPG | JPG image | |
| General_Contracting_Ship_Check_Notes.pdf | ||
| EBI_Crane_Info_with_Slip_Ring_Assembly.pdf | ||
| 026_(2).JPG | JPG image | |
| General_Contracting_Quote_Sheet.xlsx | XLSX spreadsheet | |
| ATTCH_CLAUSES.pdf | ||
| wage_determination_Solono_Co_2005_rev_17.pdf | ||
| SF1449.pdf | ||
| General_Contracting_T C.pdf | ||
| SOW_General_Contracting.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Response to Question – 11/22/16
Question for Cabin Flooring on item 4:
With regards to the steel replacement of the 20sqft for the bulkhead and the floor of the shower pans and the toilets, are we to assume that this is to be replaced and bid accordingly or will this be covered in a CFR if it is discovered?
Note for Bidding purposes:
Toilet Enclosures to include 6 each toilet removal and survey of steel structure underneath - open and inspect and repair as per CFR direction
• Use 3 locations to renew steel with a total space of 20 sq ft of 5/16" plate- crop out and renew)
• Use adjacent bulkhead replacement of 20 sq ft of 1/4" plate - crop out and renew
• Renew 6 each flushometers with same design and type
• Renew 20ft of piping with all fittings and to make up to new flushometer if old piping is bad
• Renew 6 each toilet paper dispenser similar to existing
i) Provide a CFR on wall mounted porcelain toilets, flushometers and plumbing with recommendations for renewal and/or refurbishment.
Reply to the above question:
The information provided as a guide to bidding contractors was to allow for a common bidding amount of steel work rather than using an “open and inspect” then have the contractor use a CFR to charge MARAD for conditions found.
Contractor to use the following in their bid for estimated costs Note for Bidding purposes:
Toilet Enclosures to include 6 each toilet removal and survey of steel structure underneath - open and inspect and repair as per CFR direction
• Use 3 locations to renew steel with a total space of 20 sq ft of 5/16" plate- crop out and renew)
• Use adjacent bulkhead replacement of 20 sq ft of 1/4" plate - crop out and renew
• Renew 6 each flushometers with same design and type
• Renew 20ft of piping with all fittings and to make up to new flushometer if old piping is bad
• Renew 6 each toilet paper dispenser similar to existing
If there is more than this amount of specific area of steel or flushometers or piping or toilet paper dispensers or toilets then following CFR guidelines apply---------
i) Provide a CFR on wall mounted porcelain toilets, flushometers and plumbing with recommendations for renewal and/or refurbishment.
Item No 4 – SR No 5187351 – Deck, Heads & Showers Repairs
SR No 5187351 Decks, Heads/Showers Repairs
ABSTRACT
This item describes the renewal or repair of ship’s decking, heads and shower pans and fixtures in the showers and heads that have become damaged or have failed. The decking system installed for repair shall be the “phoenix” system made by American Hi- Tech Flooring Co or equal approved by COTR.
REFERENCES
Ship’s blue prints for selected areas to be repaired
Manuals for bulkhead panels and their maintenance
Vessels blueprints, drawings, and materials specifications as required. All available on vessel
LOCATION / DESCRIPTION
Location:
6ea Staterooms on the 01 and 02 Levels
Description:
6ea Staterooms on the 01 and 02 Levels
Deck area of 500 sq ft to be renewed and replaced with same color and type of Phoenix system flooring
Toilet Enclosures to include 6 each toilet removal and survey of steel structure underneath - open and inspect
(Use 3 locations to renew steel with a total space of 20 sq ft of 5/16" plate- crop out and renew) and adjacent bulkhead replacement of 20 sq ft of 1/4" plate - crop out and renew
Shower Enclosures to include 6 each showers deck removal and replacement and possible steel replacement
(Use 3 locations to renew steel with a total space of 20 sq ft of 5/16" plate - crop out and renew)
GOVERNMENT FURNISHED EQUIPMENT / MATERIAL / SERVICES
None
STATEMENT OF WORK
PHOENIX ONE-STEP SYSTEM DECK REPAIRS
1) For Bidding purposes use a deck area of 500 sq ft to be renewed and replaced with same color and type of Phoenix- One Step system flooring
2) Contractor is to prepare surface of areas to be prepared so that all loose or cracked decking is removed and remaining decking is adhered tightly to the underlayment below. Exposed underlayment shall be prepared to accept and adhere to the new Phoenix decking material as per manufacturer’s recommendations. The new decking shall be applied to be the same thickness as the existing decking. The color of the existing decking is “chocolate” and the new Phoenix One-Step material shall be the same color to match as closely as possible the existing.
SHOWER PANS and HEAD DECKS
1) On six (6) of the showers and heads designated perform the following:
a) In shower area of head, mechanically clean out and remove portions of shower pans where terrazzo has cracked and separated from shower stall. Remove as much material and rust as possible in areas where corrosion build-up is “prying” pan and stall apart.
Provide both stalls and pans for inspection by COTR or Chief Engineer or Chief Mate after cleaning.
b) Cut away all wasted steel and terrazzo material not bonded. Apply 30-year silicone or Seka-Flex caulk (or other suitable material proposed by contractor and approved by COTR) into cracks and gaps.
Note for Bidding purposes
Shower Enclosures to include 6 each showers deck removal and replacement and possible steel replacement
• 3 locations to renew steel with a total space of 20 sq ft of 5/16" plate - crop out and renew)
c) Entire surface of toilet deck shall be prepared to accept new decking system. Any bare metal rust or corrosion shall be mechanically scaled to SSPC-SP3 and the surface coated with appropriate primers or coating to accept an epoxy underlayment..
d) Epoxy underlayment shall be used to build up bottom of shower such that an even, shallow slope from edge of pan to a 6-inch radius dished area in way of drain.
e) Entire deck of head and shower pan shall be renewed with a seamless deck system of American Hi-tech flooring, Phoenix One-step or equal approved by COTR over existing decking.
f) Shower area shall be coved up 12 inches and rest of toilet deck shall be coved up 6 inches.
g) Color “Chocolate” shall be as selected to match existing installations.
h) Remove existing toilets, flushometers and associated plumbing from the (6) heads.
Note for Bidding purposes:
Toilet Enclosures to include 6 each toilet removal and survey of steel structure underneath - open and inspect and repair as per CFR direction
• Use 3 locations to renew steel with a total space of 20 sq ft of 5/16" plate- crop out and renew)
• Use adjacent bulkhead replacement of 20 sq ft of 1/4" plate - crop out and renew
• Renew 6 each flushometers with same design and type
• Renew 20ft of piping with all fittings and to make up to new flushometer if old piping is bad
• Renew 6 each toilet paper dispenser similar to existing
i) Provide a CFR on wall mounted porcelain toilets, flushometers and plumbing with recommendations for renewal and/or refurbishment.
j) Prior to re-installing toilets and fittings prep all surface areas of all (6) heads’ bulkheads to a SSPC-SP3. Fill any pitted area with epoxy filler compound or other suitable filling compound to make ready for painting. Prime coat as required and paint all bulkheads with a compatible epoxy fleck coating to be applied per manufacturer’s specifications. Color to be determined by Chief Mate.
k) Re-install toilets and fittings using new gaskets and anti-seize compound after cleaning threads and flanges of rust and scale and coating with a rust-preventative coating.
l) Clean areas, re-install all detached items and remove deck protection and masking.
m) Leave work area for Chief Engineer/Chief Mate inspection to ascertain condition and cleanliness.
n) Test drain in shower and toilet to satisfaction of COTR or Chief Engineer’s assigned representative.
HOT WORK AND PREPARATIONS FOR REPAIRS
Contractor must get hotwork permit from Chief Mate or First Assistant Engineer
Contractor to take all necessary precautions and protection to adjacent structure and equipment when doing hotwork and have fire watch and extinguishers available at all times
Contractor to get chemist is necessary in preparation prior to doing hotwork and post the report if issued
Contractor to lay floor protection for all access to the staterooms being worked on and clean up on a daily basis
Contractor to provide ventilation to remove any smoke from hotwork being drawn into the ventilation systems that feed live aboard cadets and day time workers aboard ship.
If necessary have the ventilation shutdown during welding or burning
Contractor is responsible for all removal of interferences and their replacement once the repairs are completed
DELIVERABLES
SDS on flooring materials and Manufacturer’s warranty information.
Ship Check Notes: GENERAL CONTRACTING -2017
Item No 1 --- SR No 5186515--Watertight door Service and Repairs—4 doors total versus 6 per statement of work
1) Main Deck – Port and Stbd sides Main Deck – Pilot Locker WT doors – 2 total
2) Marine Lab – Port side Main Deck – one total
3) Emergency Diesel Generator Room – 03 Deck Fwd House Port side – one total
Repair each door as follows:
• Remove door from frame
• Install covering to protect internals from weather
• Marine Lab temporary covering to be security capable- valuable equipment stored in same
• Transport door to shop for repairs
• Remove all fittings and gasket and blast to remove paint and rusted areas
• Repair gasket channel to properly contain new contractor supplied gasket
• Repair any wasted steel with new
• Scale and clean all welds
• Coat with one coat of primer and two coats of top coat (see Chief Mate for paint specs)
• Install new gaskets and all fittings with proper lubricant and adjustments
• Transport repaired doors to ship for reassembly
• Remove temporary covering
• Knife Edge of door frame
1. Scale the paint from the door knife edge at least 2 inches back
2. Inspect for damaged knife edge
3. Repair knife edge as needed to provide an even seating area for the door gasket
4. Clearcoat the knife edge to protect the scaled metal
• Refit repaired door to the frame using new pins and bushings and adjust to make the door gasket seat evenly on the knife edge
• Chalk test and prove proper seating of the gasket and dogging of the door to Chief Mate/Chief Engineer
Item No 2 – SR No 0301984 – Galley Service and Upgrades
Old Convection Oven to be transported to MARAD Warehouse for parts
Item No 3 – SR No 5189796 – Annual Liferaft Service
Awarded contractor to furnish CFR with list of consumables and/or repairs after repair shop does open inspect. All deficiencies to be listed on the CFR with costs for repairs and consumables that are out of date. All consumables must be dated to last for one year past the repair date.
Item No 4 – SR No 51187351 – Deck, Heads and Showers
6 each staterooms to be done over the course of the contract
Only 2 each of the staterooms will be done at any one time due to the need to have berthing space for Cadets.
Deck area of 1000 ft (versus 500 ft in SOW) to be renewed and replaced with color and type of Phoenix system flooring
Rooms Surveyed on ship check:
02-137-2 and 02-157-2
Item No 5 – SR No 5186382 – 02 Deck Aft House – Add Door
The primary reason for this door is to separate Cadet living spaces from Officer’s living spaces
Width of the hallway is 35 inches which means the door will be about 30 inches
Door to be similar in construction to the other internal metal doors with a round port glass and ABS and USCG approved fire rating. Door needs to have a closer
Item No 6 – SR No 0301970 – Annual Crane Inspection and Repairs
Need to have details of the After Crane slip ring sent to all contractors who will be bidding on the job to allow them to order a new slip-ring. John Coyle/Jim Sundfors Action item—find the electronic copy of same to be sent!
Downtime of the after crane needs to be planned so that it does not adversely affect any other contractor work getting materials aboard. Schedule downtime with Chief Engineer and Chief Mate at least 5 days ahead of time and also give the amount of time needed to complete the repair so we know that ship’s crane will not be available to others
Item No 8 – SR No 5187704 – Replacement of Machinery Space Doors
Per statement of work use the existing door closer
Addition to statement of work, remove the existing hand pulls on either side of the doors from old doors and install on new doors.
Item No 10 – Slop Oil Tank and Removal
Plan on completing this job by April 15, 2017
This includes the open and inspect of the tanks for ABS and Chief Engineer as is done on an annual basis
Contractor has to have the over the water permit for moving the slops from the ship to the receiving tank truck or storage tank
All necessary precautions to be taken to prevent any spills or slops going into the water.
Jim Sundfors
Marine Surveyor
MARAD DPO