Statement of Work (SOW) For
Asbestos Abatement Removal & Cleaning
Overview
The Maritime Administration seeks a qualified and licensed contractor to provide management, tools, supplies, equipment and labor necessary to complete Asbestos Abatement & Cleaning for two facilities (Land Hall and Library Main Deck) on the U.S. Merchant Marine Academy (USMMA) campus. The services shall take place at the:
USMMA
300 Steamboat Road Kings Point, NY 11024
Scope of Work
In Accordance with federal, state and local regulations and ordinances, the contractor will provide the following products/services for the following USMMA Facilities:
Land Hall
• Abatement and disposal of asbestos and lead paint
• Characterize the material removed in order to determine proper disposal requirements
• Display prominent caution signs of affected areas as required by federal and state laws and regulations
• Utilize a High Efficiency Particulate Air (HEPA) vacuum to wet wipe the:
floors walls ceilings in the stairway entire basement including the pipe insulation
• Identify location/configuration of critical barriers/and or isolation methods of decontamination areas (Note: Includes equipment room, shower and clean change room)
• Secure and tag out ventilation systems in the work areas, blank systems to prevent contamination in other areas
• Identify removal routes to avoid asbestos contamination and obtain the Contracting Officer Representative’s (COR) approval prior to proceeding
• Patch and plaster all holes along the basement stairway
• Apply one (1) coat of lead lock paint to the basement stairway (Note: Also, this includes the north wall of the reefer room)
Library Main Deck
• Abatement and disposal of asbestos tile/mastic (Approximately 160 sq. ft.)
• Remove all loose tiles in the area identified by the COR
• Scrape mastic to provide a smooth surface
• Glue and install the usable tiles (Note: Additional tiles will be provided by the USMMA)
• Identify configuration of critical barriers or isolation methods
• Identify location/configuration of critical barriers/and or isolation methods of decontamination areas
(Note: Includes equipment room, shower and clean change room)
• Secure and tag out ventilation systems in the work areas, blank systems to prevent contamination in other areas
• Display prominent caution signs of affected areas as required by federal and state laws and regulations
• Identify removal routes to avoid asbestos contamination along those routes and obtain COR approval prior to proceeding
Training/Certifications Requirements
• Provide OSHA or state approved 40-hour Asbestos Supervisor’s Course and annual refreshers
• Provide written substantiation of the credentials for Qualified Person(s)
• Provide copies(s) of current licenses for all asbestos workers
• Personnel shall possess a valid state driver’s license
Contractor Responsibilities
• Monitor work practices, maintain daily logs for Land Hall and the Library Main Deck, conduct on-site inspections for each facility, and set up regulated areas – all work to be conducted in accordance with federal, state and local regulations
• Specify the necessary protection and precautions to be taken when working with asbestos and lead
• Waste generated must be handled, stored, managed, transported and disposed of in accordance with
OSHA and EPA/state/local requirements
• Provide completed manifests for asbestos and lead paint disposal as well as all laboratory analyses conducted for profiling the waste generated
• Provide copies of all federal, state and local notifications
• Interruption of any services to any part of the Academy will be as minimal as possible
• All work must be scheduled with COR at least 48 hours before work is to be accomplished
• All work will be prepared in advance and only with prior approval of the COR
• Maintain safe, clean and secure work areas on a daily basis
• Any damages to existing facilities or appurtenances shall be repaired or replaced, in kind, at no additional cost to the Government
Security Considerations
• Submit schedule to the COR at least 48 hours prior to commencing work
• Coordinate schedule with the COR and identify days and times to secure the area for any necessary equipment being used for the project