Attachment_L.3_Representative_Task_Quote_(Amendment_4).docx

DOCX document 23 KB Posted

Attached to
Triennial Review Program
Solicitation number
DTFT60-13-R-00001
Issued by

About this file

Attachment L.3 RTQ

View the file

Other files

File Type Posted
DTFT60-13-R-00001_(Amendment_4).pdf PDF
Attachment_L.8_(Amendment_4).pdf PDF
Attachment_L.3_Representative_Task_Quote_(Amendment_3).docx DOCX document
Attachment_L.7_(Amendment_3).pdf PDF
DTFT60-13-R-00001_(Amendment_3).pdf PDF
DTFT60-13-0001_Amendment_000002.pdf PDF
DTFT60-13-0001_Amendment_000002.pdf PDF
Attachment_L_4_(Amendment_2).pdf PDF
Attachment_L.6_(Amendment_2).pdf PDF
Attachment_L.5_(Amendment_2).pdf PDF
DTFT60-13-0001_Amendment_000001.pdf PDF
DTFT60-13-0001_Amendment_000001_Attachment_L.6.pdf PDF
DTFT60-13-0001_Amendment_000001_Attachment_L.4.pdf PDF
DTFT60-13-0001_Amendment_000001_Attachment_L.5.pdf PDF
Attachment_J-1_Acronyms_Terms_and_Definitions.pdf PDF
Attachment_J-5_Draft_Triennial_Review_Workbook.pdf PDF
Attachment_J-3_Draft_SOP.pdf PDF
Attachment_J-7_COI_Matrix.xls XLS spreadsheet
Attachment_J-2_FTA_5307_Grantees.xlsx XLSX spreadsheet
Attachment_J-4_Pricing_Matrix.docx DOCX document
Attachment_L.3_Representative_Task_Order.docx DOCX document
DTFT60-13-R-0001_Triennial_Review_RFP.pdf PDF
Attachment_L.2__Past_Performance_Questionnaire.docx DOCX document
Attachment_L-1_Triennial_Review_Vendors_Day_Presentation.pdf PDF
Attachment_J-6_Draft_QASP.doc DOC document
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment L.3

DTFT60-13-R-00001

Triennial Review Program

Representative Task Quote

This Representative Task Quote is for Evaluation purposes only and does not commit the government to any work described herein. In the interest of clarity; this Representative Task Quote is written as if ONE CONTRACTOR was tasked to complete all work under this contract statement of work.

The contractor shall provide professional contracting services for the Triennial Review Contract in accordance with the SOW using the Labor Categories and loaded labor rates in the Section B Labor Categories and rates for the contract year, period of performance. For this RTQ, assume period of performance is May 1, 2013 to April 30, 2014.

The Government is providing a level of effort (LOE), Not-to-Exceed, NTE estimate of hours for each CLIN. The estimated LOE Total is the TOTAL LOE required for the contract year. The ESTIMATED QUANTITY is an FFP quantity for the corresponding CLIN. LOE hours are provided to assist vendors in estimating FFP for each CLIN.

Please provide a quote for:

CLIN
Description
Estimated LOE TOTAL/ Year
Estimated Quantity
Price
1
Annual HQ Kickoff and Program Review Meeting
30 Labor Hours
1
$__________
2
TR, Part 1, Tier 1 Grantee - Pre-review Assessment through Prep for Site Visit
170 Labor Hours
2
$__________
2A
TR, Part 2, Tier 1 Grantee –Site Visit ,Draft Report; Final Report & Closeout
500 Labor Hours
2
$__________
3
TR, Part 1, Tier 2 Grantee - Pre-review Assessment through Prep for Site Visit
340 Labor Hours
8
$__________
3A
TR, Part 2, Tier 2 Grantee - Site Visit ,Draft Report; Final Report & Closeout
425 Labor Hours
8
$__________
4
TR, Part 1, Tier 3 Grantee - Pre-review Assessment through Prep for Site Visit
6600 Labor Hours
174
$__________
4A
TR, Part 2, Tier 3 Grantee - Site Visit ,Draft Report; Final Report & Closeout
7600 Labor Hours
174
$__________
5
Corrective Action Support -- All Tiers
1050 Labor Hours
NTE LH
$__________
6
Enhanced Review Module, Tier 1 Grantee (Technical Capacity)
60 Labor Hours
1
$__________
7
Enhanced Review Module, Tier 2 Grantee (Financial Capacity)
210 Labor Hours
5
$__________
8
Enhanced Review Module, Tier 3 Grantee (Procurement)
500 Labor Hours
20
$__________
9
Technical Assistance
3500 Labor Hours
NTE LH
$__________
10
Triennial Review Guide(s) and Work Shop Materials
FFP
1
$90,000*
11
Triennial Review Workshops and Training
FFP
15
$600,000*
12
Monthly Program Reports
FFP
12
$18,000*
13
Oversight Program Support and Special Assignments
2000 Labor Hours
NTE LH
$__________
14
Other Direct Costs
Cost
NTE
$125,000*
15
Travel
Cost
NTE
$300,000*
Total Price
$

*Dollar figures provided as “plug in estimates” based on historical data to be used for evaluation purposes only.