Amendment 0001 The Bid Opening date has changed to July 13, 2017, at 2:00 p.m.

View the file

Other files

File Type Posted
ROBO_-_NP-MANA_001S(1).pdf PDF
FP14_Eng.pdf PDF
Plans_-_NP-MANA_001S(1).pdf PDF
VETS-4212_Form.pdf PDF
IFB_Solicitation_-_NP-MANA_001S(1).pdf PDF
ADV_Bidder's_Qualifications_Form.doc DOC document
Report_2_Bridge_Inspection_Report.pdf PDF
Report_1_NEPA.pdf PDF
Synopsis_-_NP-MANA_001S(1).doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

DTFH7117B00026

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

Sterling VA 20166-6511

EFLHD-CO

21400 Ridgetop Circle Construction Office Eastern Federal Lands Highway Div.

Federal Highway Administration

Sterling VA 20166-6511

EFLHD-AC

21400 Ridgetop Circle Acquisitions Office Eastern Federal Lands Highway Div.

Federal Highway Administration

SEE BLOCK 1407/07/20170001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

06/08/2017

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

NP MANA 001S(1)

The purpose of this Amendment is to:

1) Provide a summary of responses to questions/clarifications submitted by potential bidders.

2) Change the Bid Opening date to July 13, 2017, at 2:00 p.m.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

Amendment No. 0001

Info Page 1 of 3

U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

Project NP MANA 001S(1)

Manassas National Battlefield Park - Stone Bridge Solicitation: DTFH71-17-B-00026

The purpose of this Amendment is to:

1) Provide a summary of responses to questions/clarifications submitted by potential bidders.

2) Change the Bid Opening date to July 13, 2017, at 2:00 p.m.

Questions/Clarifications

Bidders can send written questions or inquiries for clarification to: eflhd.contracts@dot.gov.

Questions can be submitted at any time, but questions submitted within 7 days of the bid opening may not be answered in time for the bidder to properly incorporate the responses into their bids.

The following questions and issues were submitted via email. The Government response or clarification is provided. Due to the repetitive nature of several questions and issues, the wording of the questions may have been revised and some questions have not been included.

The Government’s direct response to the sender may also have been updated below for better clarity.

1. Estimated quantities of stone masonry repointing is given as “1,500 LF.” The linear footage of the mortar joints in this structure measures approximately 3 LF per 1 SF. By this estimation only 500 SF of stone masonry would be repointed. Just the parapet alone has approximately 1,100 LF of mortar joints on the roadbed side. Please clarify if 1,500 LF is the quantity of repointing that should be included in the bid.

Response: The entire bridge does not require repointing. We are only proposing the repointing to be done after field review by the Contractor and CO. Please use the quantities as shown in the Bid Schedule.

2. Are the stone walls which are not part of the bridge structure but appear to be retaining walls (which abut the bridge structure on the north side) included in the masonry restoration scope.

The retaining wall question is in addition to the scope that does include “cleaning the 2 weep holes” noted in the “Estimated Repair Quantities” List.

Response: The walls are included in the scope and only two weep holes were located in the field.

mailto:eflhd.contracts@dot.gov

Info Page 2 of 3

3. Will a Site Walk be scheduled, if so, when?

Response: No.

4. There appear to be significant bulges in the existing bridge structure at the Northwest and Southeast Abutment walls that may require removal and reconstruction. There does not appear to be any allowance made in the design documents for any of this work. Are we to include any rebuilding in the cost proposal?

Response: The bulges in the walls have been there for more than 20 years (per past inspection reports) and will not be reconstructed.

5. Please provide a Mortar Specification.

Response: The mortar is required to match the existing mortar in color and texture, as stated in Section 620 of the Special Contract Requirements (SCRs), pages J-17 and -18 of the solicitation booklet. The motor also has to meet the material requirements as shown in Subsections 620.02 and 712.02 of the FP (standard specifications book).

• Will testing be required? if so, what type and quantity of testing will be required?

Response: For testing requirements, see Section 620 of the FP and Subsection 712.02 of the FP.

6. We believe that when mortar is removed for repointing that some stones will become loose due to the fragile state of the walls and mortar joints in places. Is there an allowance for replacing these stones?

Response: The pay item 62002-0000 “Stone Masonry” is for stone replacement. The stones are to be reset if they come loose. See sheet R05 of the plans and Section 620 of the SCRs.

7. Is there a supply of replacement stones that are available for use in any reconstruction that may be required?

Response: As stated in Section 620 of the SCRs, existing stone, original to the bridge, is to be reused to the extent possible. If there is not enough existing stone available, it is the Contractor’s responsibility to supply stone and obtain approval from the CO before its use.

8. Please provide a schedule start and finish date for planning purposes. If the project is started in the fall, Winter Protection (heat and tarping) may be required. If Winter protection is needed, it will be included in the price of the project.

Response: Please see page 2, last paragraph, of the B Pages - Bid Schedule Instructions (in the solicitation booklet), which states “Bidders are to assume … the start of construction activities to be no earlier than October 2017.” Please also see Subsection 108.01 of the SCRs which includes several work restrictions.

Info Page 3 of 3

9. Follow up to OHWM question asked previously.

• Drawing M04 refers to OHWM 161.3. Is this a "2 year" or "10 Year" elevation?

Response: This is the Ordinary High Water Mark as surveyed.

• Drawing M04 refers to 930 CUFT. Is this Cubic Feet per Minute or per Hour?

Response: 930 CUFT is the volume of water that the stone will replace and OHWM.

• Drawing M04 refers to 437 CUFT. Is this CF per Min or CF per Hour?

Response: 437 CUFT is the volume of water that the Diversion Berm will replace and OHWM.

• Drawing M05 has similar questions for values referencing CF. Is this CF per Min or per Hour?

Response: As noted, the CUFT values on M05 are displaced volumes of water in relation to construction activities.

• Will historical storm water elevation levels be provided so the bid costs can be attributed to water control methods?

Response: See plan sheets M04 and M05 for Ordinary High Water Level (OHWL).