Amend_0001_MS_FLTP_FS_967(1).pdf

PDF 96 KB Posted

Attached to
Tombigbee National Forest Federal contract opportunity
Solicitation number
DTFH71-17-B-00018
Issued by
Department of Transportation Federal Highway Administration

About this file

Amendment 0001 NOTE: The new Bid Opening date is May 3, 2017, 2:00 PM EST.

View the file

Other files for this federal contract opportunity

Other files attached to Tombigbee National Forest, newest first.
File Type Posted
ROBO_-_MS_FLTP_FS_967(1).pdf PDF
Amend_0002_MS_FLTP_FS_967(1).pdf PDF
Notice_of_Amendment_0002.docx DOCX document
Plans_-_MS_FLTP_FS_967(1).pdf PDF
VETS-4212.pdf PDF
Report_5_-_Choctaw_Lake_Pedestrian_Bridge_Design_Plans.pdf PDF
IFB_Solicitation_-_MS_FLTP_FS_967(1).pdf PDF
Report_2_-_Soils_and_Foundations.pdf PDF
Report_4_-_Choctaw_Lake_Bridge_Inspection_Report_2012.pdf PDF
Report_3_-_Certification_Program_for_Bridge_Temporary_Works_(FHWA-RD-93-033).pdf PDF
ADV_Bidder's_Qualifications_Form.doc DOC document
FP14_Eng.pdf PDF
Report_1_-_NEPA.pdf PDF
Synopsis_MS_FLTP_FS_967(1).pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

DTFH7117B00018

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

Sterling VA 20166-6511

EFLHD-CO

21400 Ridgetop Circle Construction Office Eastern Federal Lands Highway Div.

Federal Highway Administration

Sterling VA 20166-6511

EFLHD-AC

21400 Ridgetop Circle Acquisitions Office Eastern Federal Lands Highway Div.

Federal Highway Administration

SEE BLOCK 1404/21/20170001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

03/23/2017

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

MS FLTP FS 967(1)

The purpose of this Amendment is to provide a summary of responses to questions/clarifications asked by potential bidders and extend the bid opening date.

Questions can be submitted at any time, but questions submitted within 7 days of the bid opening may not be answered in time for the bidder to properly incorporate the responses into their bids.

The new Bid Opening date is May 3, 2017, 2:00 PM EST.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

Amendment No. 0001

Info Page 1 of 2

U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

MS FLTP FS 967(1)

Tombigbee National Forest Choctaw Lake Bridge and Spillway Solicitation: DTFH71-17-B-00018

The purpose of this Amendment is to provide a summary of responses to questions/clarifications asked by potential bidders and extend the bid opening date.

Questions can be submitted at any time, but questions submitted within 7 days of the bid opening may not be answered in time for the bidder to properly incorporate the responses into their bids.

The new Bid Opening date is May 3, 2017, 2:00 PM EST.

Questions / Clarifications

Bidders can send written questions or inquiries for clarification to: eflhd.contracts@dot.gov.

Questions can be submitted at any time, but questions submitted within 7 days of the bid opening may not be answered in time for the bidder to properly incorporate the responses into their bids.

The following questions and issues were submitted via email. The Government response or clarification is provided. Due to the repetitive nature of several questions and issues, the wording of the questions may have been revised and some questions have not been included.

The Government’s direct response to the sender may also have been updated below for better clarity.

1. The bid schedule includes 30 LNFT of 18-inch arched corrugated plastic pipe (pay item 60202-0200). My supplier of this material stated that 18-inch corrugated plastic pipe is not available in arch pipe. What kind of pipe is acceptable in lieu of corrugated plastic?

Response: Asphalt-coated pipe is an acceptable alternative if the corrugated plastic pipe cannot be found.

2. What is the pedestrian bridge weight?

Response: Information regarding the pedestrian bridge weight can be found on the “Choctaw Lake Pedestrian Bridge_Design Plans” which was included as Report #5 on the Federal Business Opportunities (FBO) website for the project.

mailto:eflhd.contracts@dot.gov

Info Page 2 of 2

3. After the main road bridge is removed, who will the slabs belong too?

Response: The main road bridge will not be salvaged after removal; it will become the property of the Contractor. Please review Section 203 of the FP (standard specifications book) and the Special Contract Requirements (pages J-8 and J-9 of the solicitation booklet) for requirements of removal and disposal of structures.