Bridge Inspection Report - Coles Creek.pdf

PDF 2 MB Posted

Attached to
Natchez Trace Parkway
Solicitation number
DTFH71-11-B-00017
Issued by

About this file

Bridge Inspection Report - Coles Creek

View the file

Other files

File Type Posted
IFB Solicitation - PRA-NATR 3A15 3W12.pdf PDF
FP03 Errata.pdf PDF
VETS-100A - 2010.pdf PDF
Bridge Inspection Report - Bear Creek.pdf PDF
Bidder's Qualifications Form.doc DOC document
Subcontracting plan.doc DOC document
Plans.pdf PDF
FP03_Eng .pdf PDF
Synopsis - PRA-NATR 3A15 3W12.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BRIDGE INSPECTION REPORT

COLES CREEK BRIDGE

NATCHEZ TRACE PARKWAY OVER COLES CREEK

NATCHEZ TRACE PARKWAY

LS

STRUCTURE NO. 5570-184P

INSPECTION TYPE: ROUTINE

INSPECTION DATE: 11/11/08

Federal Highway Administration

Report prepared by: EU

MILE POINT:

KILOMETER POINT:

16.16 26.01

Federal Lands Bridge Office Bridge Inspection and Management Program 21400 Ridgetop Circle Sterling, Virginia 20166 http://www.efl.fhwa.dot.gov/FLHBO/BIP

STRUCTURE SUMMARY STRUCTURE NO. 5570-184P

COLES CREEK BRIDGE INSPECTION DATE: 11/11/08

BRIDGE IDENTIFICATION AND DESCRIPTION

MAIN SPAN MATERIAL: ....... STEEL CONTINUOUS NO. OF MAIN SPANS:

MAIN SPAN TYPE: ............... STRINGER/MULTI-BEAM or GIRDER NO. OF APPR. SPANS:

# OF BEAMS, MAIN SPAN: .. 4 STRUCT. TOTAL LENGTH: .. 721.0 FT (219.8 M)

DECK TYPE: ......................... CONCRETE CAST-IN-PLACE MAX. SPAN LENGTH: .......... 60.0 FT (18.3 M) WEARING SURFACE: .......... BITUMINOUS DECK WIDTH: ...................... 29.5 FT (9.0 M) ABUT. FOUNDATIONS: ........ SPREAD FOOTING ON PILES CURB TO CURB WIDTH: ..... 26.0 FT (7.9 M)

PIER FOUNDATION(S): ........ SPREAD FOOTING ON PILES YEAR BUILT:

ABUTMENT / PIER MAT'L: ... CONCRETE YEAR RECONSTRUCTED: .. N/A

PROJ./PLAN REF. NO: ......... 3W3 / 20198 SKEW ANGLE: ..................... 0 °

NPS ROAD CLASS: .............. 1 - PRINCIPAL PARK ROAD FRACTURE CRITICAL: ........ NO

STRUCTURE HISTORY: ...... 2002-PATCHED SPALL AT PIER #9

2008-STRUCTURE AND APPROACHES REPAVED

LOCATION

NATCHEZ TRACE PARKWAY MILE POINT: ..................... 16.16 (KM PT 26.01)

STATE: ................................. MISSISSIPPI LOCATION: 3.9 MILES SOUTH OF MS ROUTE 553.

8.0 MILES NORTH OF U.S. ROUTE 61 (SOUTH FACILITY CARRIED: ............ NATCHEZ TRACE PARKWAY

INTERSECTION).

FEATURE INTERSECTED: .. COLES CREEK

STRUCTURE EVALUATION SUMMARY

This steel girder bridge is in good condition overall. The main significant change in the structural condition since the previous inspection is a deteriorating mortar pad for the bearing of Girder #2 in Span #3 at Pier #3 which, if not repaired, may result in a loss of bearing for the girder.

The bridge and approaches were repaved with asphalt in 2008. The paving operation left the bridge deck expansion joints packed with asphalt. The drainage system for the expansion joints is also clogged with asphalt and debris. The expansion joints and associated drainage system should be cleared of debris to allow for free expansion and contraction of the structure, and adequate drainage of the roadway surface.

Other main problems, which remain relatively unchanged from the previous inspection, include widespread paint failure on the structural steel with some minor rusting, erosion beneath Spans #1, #9 and #10, and heavy accumulation of flood debris in the channel at Pier #11. Repairs should be made as outlined in this report to prevent the possible development of more serious or costly problems in the future.

INSPECTION TEAM: D.B. TAYLOR, L.M. MUELLER (CLARK NEXSEN)

CONDITION ASSESSMENT:

DANIEL B. TAYLOR, FIELD TEAM LEADER

REPORT REVIEW:

SAMANTHA LUBKIN, FIELD TEAM LEADER 703-404-6256

REPORT APPROVAL: DATE: 4/16/09

MARCUS MILLER, P.E., LEAD STRUCTURAL ENGINEER 703-404-6252

RECOMMENDATIONS AND ESTIMATED COSTS STRUCTURE NO. 5570-184P

226 PRIORITY OF IMPROVEMENT C

A (Critical) - Structure is closed, in imminent danger of collapse, or presents a critical safety hazard.

B (Major) - Structure is seriously deficient or presents a safety hazard, but can remain in service at reduced loads or with frequent inspections.

C (Moderate) - Structure is deficient, functionally obsolete, or requires substantial repairs to prevent a serious deficiency or unsafe condition.

D (Minor) - Structure is generally in good condition. Preventative maintenance may be required.

E (Special) - Structure is under construction or reconstruction.

ITEM

NO.

MAINTENANCE RECOMMENDATIONS

(GENERALLY NOT FLHP ELIGIBLE)

QTY. UNIT

COST

UNIT

ESTIMATE

COST

PRELIM.

60.17 FILL AND STABILIZE EROSION BENEATH SPANS #9 AND #10. 30 CY $1,000 $30,000

58.2,7, 60.15

CLEAN ASPHALT AND DEBRIS FROM BRIDGE DECK EXPANSION JOINTS AND

EXPANSION JOINT DRAINAGE SYSTEM. REMOVE ASPHALT AND DEBRIS BUILD-UP

FROM TOP OF PIER CAPS.

1 LS $10,000 $10,000

58.2,3 REPAIR DETERIORATED MORTAR PAD BENEATH BEARING OF GIRDER #2, SPAN

#3 AT PIER #3.

1 LS $7,500 $7,500

61.4 REMOVE FLOOD DEBRIS FROM PIERS #10 & #11. 1 LS $2,000 $2,000

222.7 REPLACE MISSING TYPE 3 OBJECT MARKER AT NORTHEAST CORNER. 1 EA $300 $300

PRELIM. MAINTENANCE TOTAL : $49,800

ITEM

NO.

REHABILITATION/RECONSTRUCTION

(TYPICALLY NEEDED WITHIN 5 YEARS)

QTY. UNIT UNIT

COST ESTIMATES

PRELIM. COST

REHAB. RECONSTR.

59.1,2,6,7 CLEAN AND PAINT STRUCTURAL STEEL. 18,750 SF $20 $375,000 $0

PRELIM. REHABILITATION/RECONSTRUCTION TOTAL : $375,000 $0

COST ESTIMATE SUMMARY

PRELIM. MAINTENANCE TOTAL:

PRELIM. REHABILITATION TOTAL:

PRELIM. RECONSTRUCTION TOTAL:

TOTAL ITEMIZED COSTS:

$0 $375,000 $49,800

$424,800

PRELIMINARY ESTIMATE TOTAL* :

(*Includes typical contract costs for mobilization, traffic control, and design/construction engineering; but does not include detour bridges, work beyond the bridge limits, or work not listed above. Estimates are approximate and are for preliminary planning purposes only; they should not be used as a complete or final engineers estimate.)

$849,600

REMARKS: Cost estimates assume that the recommended actions will be combined with similar work being performed on other structures.

FIELD INSPECTION REPORT STRUCTURE NO. 5570-184P

CONDITION RATING CODES FOR ITEMS 58 - 62, 222, 223

N NOT APPLICABLE 3 SERIOUS CONDITION - loss of section, deterioration, spalling, or scour have seriously affected primary structural components. Local failures are possible.

9 EXCELLENT CONDITION Fatigue cracks in steel or shear cracks in concrete may be present.

8 VERY GOOD CONDITION - no problems noted. 2 CRITICAL CONDITION - advanced deterioration of primary structural elements. Fatigue cracks in steel or shear cracks in concrete may be present

7 GOOD CONDITION - some minor problems. or scour may have removed substructure support. Unless closely monitored it may be necessary to close the structure until corrective action can be taken.

6 SATISFACTORY CONDITION - structural elements show some minor deterioration. 1 “IMMINENT” FAILURE CONDITION - major deterioration or section loss present in critical structural components or obvious vertical or horizontal 5 FAIR CONDITION - all primary structural elements are sound but may have movement affecting structure stability. Structure is closed to traffic but minor section loss, cracking, spalling, or scour. corrective action may return structure to light service.

4 POOR CONDITION - advanced section loss, deterioration, spalling, or scour. 0 FAILED CONDITION - out of service; beyond corrective action.

CONDITION RATING CODE EQUIVALENTS FOR SUB-ELEMENTS

G = GOOD (CODES 7 - 9) F = FAIR (CODES 5 - 6) P = POOR (CODES 0 - 4)

58. DECK 7

ABUTMENTS

ITEM REFERENCE AND REMARKS

G1. DECK SLAB

F2. EXPANSION JOINTS

G3. WEARING SURFACE

G4. RIDEABILITY

G5. CURBS, SIDEWALKS, AND MEDIAN

G6. PARAPETS AND/OR RAILINGS

P7. DRAINS AND DRAINAGE

N8. UTILITIES

G9. DEFLECTION AND/OR VIBRATION

N10. OTHER

59. SUPERSTRUCTURE 6

F1. BEARING DEVICES

G2. GIRDERS OR BEAMS

N3. ARCH(ES) OR SLAB(S)

N4. FLOOR BEAMS AND STRINGERS

N5. TRUSSES

G6. DIAPHRAGMS AND BRACING

F7. PAINT

G8. FASCIA(E)

G9. DEFLECTION AND/OR VIBRATION

G10. ALIGNMENT

N11. OTHER

60. SUBSTRUCTURE 7

58.1 MINOR TRANSVERSE CRACKING OF DECK UNDERSIDE WITH

EFFLORESCENCE.

58.2 OPEN (FINGER) EXPANSION JOINTS ARE PACKED WITH ASPHALT

FROM NEW PAVEMENT OVERLAY OPERATION. EXPANSION JOINT

DRAINAGE SYSTEM CLOGGED. SEE ITEM 58.7.

58.3, 222.4 NEW ASPHALT PAVEMENT OVER BRIDGE AND APPROACHES.

58.6 MINOR CRACKING OF PARAPETS. MINOR SPALLING OF TOP RAIL

ON WEST SIDE OF SPAN #6 (VEHICLE IMPACT). MINOR VEHICLE

SCRAPES AT RANDOM LOCATIONS THROUGHOUT.

58.7 MINOR ACCUMULATION OF DEBRIS ALONG CURBLINES. DRAINAGE

SCUPPERS ALONG CURBLINES ARE CLEAR.

EXPANSION JOINT DRAIN AT PIER #3 CLOGGED WITH DEBRIS

(ASPHALT). EXPANSION JOINT DRAIN AT PIER #6 AND #9 CLOGGED

AND OUTLETS BURIED BELOW GROUND.

59, 60 GRAFFITI ON FACES OF PIERS AND AT SOME LOCATIONS ON

SUPERSTRUCTURE.

59.1,2,6,7 MODERATE PEELING OF PAINT OF ALL STRUCTURAL STEEL.

RANDOM AREAS OF MINOR SURFACE RUSTING WITH NO LOSS OF

SECTION.

59.1, 60.3,15 MORTAR PAD BENEATH BEARING OF GIRDER #2 (FROM WEST) IN

SPAN #3 AT PIER #3 BREAKING UP, EXTENDING 5" BACK UNDER

BEARING PLATE. MORTAR IS CURRENTLY STILL IN PLACE,

HOWEVER A 50% LOSS OF BEARING WILL RESULT IF IT BREAKS

FREE. MINOR CRACKING OF MORTAR PADS AT SEVERAL OTHER

BEARING SEAT LOCATIONS.

MINOR DEBRIS BUILD-UP ON CAP OF SOUTH ABUTMENT. HEAVY

DEBRIS BUILD-UP (UP TO 12" HIGH) ON CAPS OF PIERS #3, #6 AND

#9 BELOW OPEN JOINTS.

1. BREASTWALLS OR COLUMNS G

2. PILE BENTS N

3. CAPS AND/OR BEARING SEATS G

4. BACKWALLS AND/OR BULKHEADS G

5. FOUNDATIONS N

6. WINGWALLS G

7. WEEP HOLES G

8. EXPANSION JOINTS N

9. EROSION AND/OR SCOUR F

10. SETTLEMENT OR DEFLECTION G

11. SLOPE PROTECTION F

12. OTHER N

PIER(S)

WALLS AND/OR COLUMNS 13. G

PILE BENTS14. N

CAPS AND/OR BEARING SEATS15. G

FOUNDATIONS16. N

EROSION AND/OR SCOUR17. F

SETTLEMENT OR DEFLECTION18. G

OTHER 19. N

FIELD INSPECTION REPORT STRUCTURE NO. 5570-184P

ITEM REFERENCE AND REMARKS

STREAM BED COMPOSITION : 9.

AVERAGE CLEAR OPENING 8.

NORMAL VELOCITY 7.

ADEQUACY OF OPENING 6.

OTHER 5.

WATERWAY OBSTRUCTIONS 4.

CHANNEL PROTECTION3.

EROSION AND/OR SCOUR2.

ALIGNMENT1.

61. CHANNEL 6

G G N F N

MED

SUFF

10 FT.

SAND, SILT

222. APPROACHES 7

OTHER 9.

ALIGNMENT 8.

SIGNS7.

SETTLEMENT 6.

EROSION5.

SURFACING4.

APPROACH GUARDRAIL 3.

2. RELIEF JOINTS

APPROACH SLABS1. N

N N G G G F G N

223. RETAINING WALL N

OTHER 6.

SETTLEMENT OR DEFLECTION5.

EROSION AND/OR SCOUR4.

FOUNDATION3.

WEEP HOLES2.

1. WALL

36. TRAFFIC AND SAFETY FEATURES

APPROACH GUARDRAIL ENDSD.

APPROACH GUARDRAILSC.

TRANSITIONSB.

BRIDGE RAILINGSA. 1

N N N

TRAFFIC SAFETY RATING CODES

N

Does not meet standards or a safety feature is required and none is provided.

Meets currently acceptable standards.

Not applicable or a safety feature is not required.

59.8 MINOR CRACKING OF CONCRETE FASCIAE WITH EFFLORESCENCE

MIDWAY BETWEEN DECK DRAINS; MOSS ON FASCIAE UNDER DECK

DRAINS. MODERATE STAINING THROUGHOUT.

60.1 MINOR VERTICAL CRACKING OF ABUTMENT BREASTWALLS.

60.6 MINOR VERTICAL CRACKING OF NORTH ABUTMENT WINGWALLS

WITH EFFLORESCENCE.

60.9 MINOR EROSION IN FRONT OF SOUTH ABUTMENT AT WEEP HOLES

AND EXPANSION JOINT DRAINAGE SYSTEM OUTLET; SOME RIPRAP

IN PLACE. MINOR EROSION OF SLOPE AT NORTH ABUTMENT.

60.11 MODERATE CRACKING AND SETTLEMENT OF NORTH ABUTMENT

SLOPE PROTECTION. EROSION OF CHANNEL BANK AT DRAINAGE

OUTFALL ON WEST SIDE OF NORTH ABUTMENT.

60.13 APPROXIMATELY 6' X 3' PATCHED AREA ON NORTH SIDE OF PIER

#9; TOP SECTION OF PATCH SPALLED OFF (7" HIGH X 20" WIDE X 7"

DEEP) WITH EXPOSED REBAR.

60.17 MODERATE TO HEAVY EROSION UNDER SPANS #9 AND #10. MINOR

SCOUR AT PIER #10. <<MODERATE PONDING ON SOUTH SIDE OF

PIERS #2 AND #4>> (UNABLE TO VERIFY DURING THIS INSPECTION).

61.4 HEAVY ACCUMULATION OF DRIFT AT UPSTREAM SIDE OF PIER #11;

MINOR AT UPSTREAM SIDE OF PIER #10. MODERATE

ACCUMULATION OF SILT ON NORTH SIDE OF PIER #10.

222.7 TYPE 3 OBJECT MARKER TAPE MISSING AT NORTHEAST CORNER.

STRUCTURE LOAD RATING STRUCTURE NO. 5570-184P

TRUCK TYPE

INVENTORY RATING (NORMAL TRAFFIC) OPERATING RATING (MAXIMUM LOAD)

TONS METRIC TONS TONS METRIC TONS

H 15 14 25 23

HS 19 17 31 28

TYPE 3 17 16 29 26

TYPE 3S2 25 22 41 37

TYPE 3-3 30 27 50 45

DESIGN LOADING: H15 (M13.5)

X CAPACITY MEETS OR EXCEEDS DESIGN LOAD

CAPACITY IS LESS THAN DESIGN LOAD

ORIGINAL LOAD RATING CALCULATION APPLICABLE

ORIGINAL LOAD RATING CALCULATION REVISED

DATE OF LOAD RATING CALCULATION:

LOAD RATING CONTROLLED BY:

REMARKS: RATING IS BASED ON DESIGN LOAD OF STRUCTURE.

STRUCTURE INVENTORY AND APPRAISAL STRUCTURE NO. 5570-184P

STRUCTURE IDENTIFICATION

(201) PARK: NATCHEZ TRACE PARKWAY (1) STATE: ....................................... 284 - MISSISSIPPI (MS)

(202) STRUCTURE NAME: .......... COLES CREEK BRIDGE (2) STATE HWY. AGENCY DIST:

(203) STRUCTURE KIND: ............1 - BRIDGE (3) COUNTY CODE: ........................ 063 - JEFFERSON

(204) STRUCTURE NUMBER: ..... 5570-184P (4) CITY/PLACE CODE:

(205) NPS REGION: .................... 4 - SOUTHEAST (5) INVENTORY ROUTE:

(206) ROUTE CODE NUMBER: ... 1 (6) FEATURES INTERSECTED:....... COLES CREEK

(207) ROAD SECTION NO: ..........184P (7) FACILITY CARRIED: .................. NATCHEZ TRACE PARKWAY

(208) NPS ROAD CLASS: ............ 1 - PRINCIPAL PARK ROAD (8) STATE STRUCTURE NO: .......... 5570184P0000000

(209) WITHIN NPS BNDRY?: .......YES (9) LOCATION: ................................ 3.9 MILES SOUTH OF MS RO

(210) OPERATING UNIT: .............NATCHEZ (10) INV. RTE. - MIN. VERT. CLR: .. 99.99 FT (99.99 M)

(211) PROJECT NO(S): ................3W3 (11) MILE POINT: ............................. 16.16 (KM PT 26.01)

(212) DRAWING NUMBERS: ....... 20198 (27) YEAR BUILT:

(21) MAINTAINED BY: ................. 66 - NATIONAL PARK SERVICE (106) YEAR RECONSTRUCTED: .... N/A

(22) OWNER: ............................... 66 - NATIONAL PARK SERVICE (20) TOLL: ........................................ 3 - FREE ROAD

(37) HISTORICAL DESIGNATION: .. 5 - NOT ELIGIBLE

STRUCTURE DESCRIPTION, FOUNDATION, AND DECK TYPE

(43A) MAIN STR. MATERIAL: ..

(43B) MAIN STR. TYPE:

(45) NO. OF MAIN SPANS:

(48) MAX. SPAN LENGTH:

(49) STRUCTURE LENGTH:

(216A) ABUTMENT #1 FDN:

(216B) ABUTMENT #2 FDN:

(217A) PREDOM. PIER FDN.: ..

(217B) SECOND. PIER FDN: ...

(107) DECK TYPE:

4 - STEEL CONTINUOUS

02 - STRINGER/MULTI-BEAM or GIRDER

60.0 FT (18.3 M)

721.0 FT (219.8 M)

3 - SPREAD FOOTING ON PILES

3 - SPREAD FOOTING ON PILES

3 - SPREAD FOOTING ON PILES

3 - SPREAD FOOTING ON PILES

1 - CONCRETE CAST-IN-PLACE

(44A) APPR. STR. MATERIAL: ........ 0 - OTHER

(44B) APPR. STR. TYPE: ................ 00 - OTHER

(46) NO. OF APPROACH SPANS: .. 0

(108) WEAR SURFACE/PROTECT SYSTEM:

A) TYPE WEARING SURFACE: .. 6 - BITUMINOUS

B) TYPE MEMBRANE: ................. 0 - NONE

C) TYPE PROTECTION: .............. 0 - NONE

(218) IS SALT USED?: ..................... NO

LOAD RATING AND POSTING

(31) DESIGN LOAD: ................. 2 - H15 (M13.5) (41) LOAD RESTRICTION: ......... R - POSTED (OTHER)

(66) INVENTORY RATING: ...... 18.7 TONS (17.0 METRIC TONS) (70) BRIDGE POSTING: .............. 3 - POSTING REQUIRED

(64) OPERATING RATING: ...... 30.9 TONS (28.0 METRIC TONS)

INSPECTION DATES

(90) INSPECTION DATE: 11/08 (91) FREQ. OF INSP: 24 MONTHS (92 / 93) CRITICAL FEATURE INSPECTION (CFI):

(219) ADD. STUDIES NEEDED: N - 0 - NONE (A) FRACTURE CRITICAL: ... NO

INSP. EVERY: MONTHS - LAST INSP. : (220) SPECIAL STUDY TYPE: 0 - NONE

(B) UNDERWATER: .............. NO

(221) SPECIAL STUDY DATE: INSP. EVERY: MONTHS - LAST INSP. :

(C) SPECIAL INSPECTION: .. NO

INSP. EVERY: MONTHS - LAST INSP. :

STRUCTURE INVENTORY AND APPRAISAL STRUCTURE NO. 5570-184P

GEOMETRY, TRAFFIC, AND NAVIGATIONAL DATA

(16) LATITUDE: ............................. 31°41'36.66" (51) CURB TO CURB WIDTH: ........... 26.0 FT (7.9 M)

(17) LONGITUDE: ......................... 91°10'51.96" (52) DECK WIDTH: ............................ 29.5 FT (9.0 M)

(19) DETOUR LENGTH: ............... 37 MI (60 KM) (32) APPR. ROADWAY WIDTH: ........ 34.0 FT (10.4 M)

(28A) LANES ON STRUCT: .......... 02 (213) APPR. PAVEMENT WIDTH: ..... 22.0 FT (6.7 M)

(28B) LANES UNDER STRUCT: ... 00 LEFT SHOULDER: .................. 6.0 FT (1.8 M)

(42A) SERVICE ON: ..................... 1 - HIGHWAY RIGHT SHOULDER: ................ 6.0 FT (1.8 M)

(42B) SERVICE UNDER: .............. 5 - WATERWAY (33) BRIDGE MEDIAN: ....................... 0 - NO MEDIAN

(29) AVG. DAILY TRAFFIC: .......... 410 (34) SKEW ANGLE: ............................ 0 °

(30) YEAR OF ADT: ...................... 2008 (35) DECK FLARE?: ........................... NO

(114) FUTURE ADT: ..................... 451 (47) TOTAL HORIZ. CLEARANCE: .... 26.0 FT (7.9 M)

(115) YEAR OF FUTURE ADT: ..... 2028 (50) SIDEWALKS:

(101) PARALLEL STRUCTURE: ... N - NONE LEFT : ...................................... 0.0 FT (0.0 M)

(38) NAVIGATION CONTROL?: ... 0 RIGHT : ................................... 0.0 FT (0.0 M)

(39) VERTICAL CLEARANCE: ...... 0.0 FT (0.0 M) (214) BRIDGE RAIL TYPE:

(40) HORIZ. CLEARANCE: ........... 0.0 FT (0.0 M) RAIL CONFIGURATION: ......... 1 - FULL HEIGHT (NO PARAPE

(111) ABUT. OR PIER PROT: ....... MATERIAL: .............................. 1 - CONCRETE

DESIGN TYPE: ........................ 1 - CONTINUOUS RAIL LATERAL UNDERCLEARANCE:

(55) RIGHT: ....................... 0.0 FT (0.0 M) (215) BRIDGE RAIL HEIGHT: ............ 2.58 FT (0.79 M)

(56) LEFT: ......................... 0.0 FT (0.0 M) (53) MIN. VRT. CLEAR. OVER DECK: 99.99 FT (99.99 M)

(54) MIN. VRT. UNDERCLEARANCE: 0.00 FT (0.00 M)

CONDITION AND APPRAISAL DATA, PROPOSED IMPROVEMENTS, AND COST

(58) DECK:

(59) SUPERSTRUCTURE:

(60) SUBSTRUCTURE:

(61) CHANNEL:

(62) CULVERT: ........................... N

(222) APPROACHES:

(223) RETAINING WALL: ...........N

(224) EST. REMAINING LIFE: ....25 YEARS

(36) TRAFFIC SAFETY FEAT: ... 1NNN

(75A) TYPE OF WORK:

(75B) WORK DONE BY:

(76) IMPROVEMENT LENGTH: ..

(67) STRUCTURAL EVALUATION:

(68) DECK GEOMETRY:

(69) UNDERCLEARANCES:

(71) WATERWAY ADEQUACY:

(72) APPROACH ALIGNMENT:

(113) SCOUR CRITICAL:

(225) PURPOSE OF IMPROVEMENT:

(226) PRIORITY OF IMPROVEMENT:

(227) MAINTENANCE COST:

(228) REHAB./RECONSTR. COST: ...

(229) CONSTRUCTION COST:

N

6 - Not yet evaluated for scour p

2 - REHAB/RECONSTRUCTION

C - MODERATE

$49,800

$375,000

$0

ADDITIONAL INFORMATION

(230) STRUCTURE HISTORY:

2002-PATCHED SPALL AT PIER #9

2008-STRUCTURE AND APPROACHES REPAVED

(231) ADDITIONAL CONSIDERATIONS:

(330) ADDITIONAL CONFIG. INFO.:

APPENDIX STRUCTURE NO. 5570-184P

PHOTOGRAPHS STRUCTURE NO. 5570-184P

PHOTO #1 - LOOKING NORTHBOUND TOWARD JACKSON

FLOW

PHOTO #2 - WEST (DOWNSTREAM) SIDE

PHOTO #3 - GENERAL TOPSIDE VIEW

LOOKING NORTH

PHOTO #4 - TYPICAL ACCUMULATION OF

DEBRIS ALONG CURBLINE; EAST CURBLINE IN

SOUTH SPAN SHOWN

PHOTO #5 - TYPICAL ACCUMULATION OF

DEBRIS (ASPHALT) IN OPEN (FINGER)

EXPANSION JOINTS; JOINT OVER SOUTH

ABUTMENT SHOWN

PHOTO #6 - OPEN (FINGER) EXPANSION JOINT

OVER NORTH ABUTMENT

PHOTO #7 - TYPICAL CRACKING OF RAILING; WEST SIDE OF SPAN #4

SHOWN

PHOTO #8 - SPALLING OF TOP RAIL ON WEST SIDE IN SPAN #6

PHOTO #9 - GENERAL UNDERSIDE VIEW

LOOKING NORTH, SOUTH SPAN

PHOTO #10 - TYPICAL CRACKING OF DECK

UNDERSIDE WITH EFFLORESCENCE; BAY #1

IN SPAN #4 SHOWN

PHOTO #11 - TYPICAL BEARING ASSEMBLY AT EXPANSION JOINTS;

BEARING FOR GIRDER #4 AT SOUTH ABUTMENT SHOWN

PHOTO #12 - TYPICAL CONTINUOUS BEARING ASSEMBLY; BEARING

FOR GIRDER #2 AT PIER #4 SHOWN

PHOTO #13 - DETERIORATION OF MORTAR PAD FOR BEARING OF

GIRDER #2, SPAN #3 AT PIER #3

PHOTO #14 - CLOSE-UP OF PREVIOUS PHOTO

PHOTO #15 - TYPICAL PEELING OF PAINT ON

GIRDERS; INTERIOR SIDE OF GIRDER #1 IN

SOUTH SPAN SHOWN

PHOTO #16 - TYPICAL PEELING OF PAINT AND

RUSTING OF DIAPHRAGMS; BAY #1 AT PIER #2

SHOWN

PHOTO #17 - MOSS GROWTH ON FASCIA

UNDER DECK DRAINS; SPAN #2 ON EAST SIDE

SHOWN

PHOTO #18 - GENERAL VIEW OF SOUTH

ABUTMENT

PHOTO #19 - EROSION OF SOUTH ABUTMENT SLOPE CAUSED BY

BRIDGE DRAINAGE

PHOTO #20 - GENERAL VIEW OF PIER #1, SOUTH FACE

PHOTO #21 - PATCH ON NORTH FACE OF PIER #9; TOP OF PATCH

SPALLED OFF WITH EXPOSED REBAR.

PHOTO #22 - TYPICAL GRAFFITI ON PIER WALL; SOUTH SIDE OF PIER

#10 SH0WN

PHOTO #23 - ACCUMULATION OF DEBRIS (ASPHALT) ON PIER #3 CAP

PHOTO #24 - CLOGGED (ASPHALT) BRIDGE DECK EXPANSION JOINT

DRAIN OUTLET, BASE OF NORTH SIDE OF PIER #3

PHOTO #25 - EROSION UNDER SPAN #9

PHOTO #26 - EROSION OF SLOPE UNDER

SPAN #10, EAST SIDE

PHOTO #27 - MINOR SCOUR AT DOWNSTREAM END OF PIER #10; NOTE

BUILD-UP OF SILT IN CHANNEL ALONG NORTH SIDE OF PIER

PHOTO #28 - EROSION OF CHANNEL BANK AT DRAINAGE OUTFALL ON

WEST SIDE OF NORTH ABUTMENT

PHOTO #29 - CLOSE-UP OF PREVIOUS PHOTO

PHOTO #30 - ACCUMULATION OF DRIFT ON UPSTREAM END OF PIER

#11

PHOTO #31 - UPSTREAM CHANNEL

PHOTO #32 - LOOKING UPSTREAM THROUGH STRUCTURE

PHOTO #33 - DOWNSTREAM CHANNEL

PHOTO #34 - LOOKING DOWNSTREAM THROUGH STRUCTURE

File details come from the government source that posted it. Updated .