PROJECT_DESCRIPTION(2).pdf

PDF 117 KB Posted

Attached to
MT DAR 2016(2), 2016 By Mile Wheatland Area
Solicitation number
DTFH70-16-B-00029
Issued by

About this file

Project Description

View the file

Other files

File Type Posted
BID_SUMMARY_Wheatland.pdf PDF
A002.pdf PDF
A001_Wheatland.pdf PDF
mt-d201602_DAR2016(2)_K-03_ew.pdf PDF
Plan_Request__Wheatland.pdf PDF
mt-d201602_DAR2016(2)_Plans_Signoff.pdf PDF
IFB_Wheatland_Area.pdf PDF
Prelim_Letter_DAR_2016(2).pdf PDF
Preliminary_Plans.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MT DAR 2016(2), 2016 By Mile – Wheatland Area, Judith Basin and Wheatland Counties, Montana

The work consists of roadway reconditioning, aggregate surfacing, aggregate stabilization, grading, drainage, and other small items of work.

Project length: 20.74 miles

Tentative Fixed Completion Date: Summer 2017 (Once solicitation is issued, see FAR Clause 52.211-10 for exact date.)

Estimated Price Range: Between $1 and $2 million

IMPORTANT NOTICE - Bidders will be quoting how many miles of work can be completed for $1,983,283.31. The Government will set the order in which the work must be performed. The successful Bidder will be based on the largest amount of work quoted. In the case of a tie, the successful Bidder will be determined by a drawing by lot limited to those Bidders

Location: Three roads, each located between Hobson, MT and Harlowton, MT.

K-03 Road located approximately 4 miles N of Harlowton, MT L-06 Road located approximately 7 miles E of Judith Gap, MT L-09 Road located approximately 6 miles SW of Hobson, MT

DESCRIPTION OF WORK in US CUSTOMARY UNITS FP-14 One

Schedule

DIVISION 150 – Project Requirements 152 Construction Survey & Staking (yes/no) Yes 153 Contractor Quality Control and Assurance (yes/no) Yes 154 Contractor Sampling & Testing (yes/no) Yes 155 Schedules for Construction Contracts (construction schedules) (yes/no) Yes 157 Soil Erosion & Sediment Control (erosion control devices) 3000 lnft 158 Watering for Dust Control 2500 mgal

DIVISION 200 – Earthwork 201 Clearing & Grubbing 0.8 ac 204 Excavation & Embankment 3300 cuyd 207 Earthwork Geosynthetics 2200 sqyd

DESCRIPTION OF WORK in US CUSTOMARY UNITS

FP-14 One Schedule

DIVISION 250 – Slope Reinforcement and Retaining Walls 251 Riprap 20 cuyd

DIVISION 300 – Aggregate and Base Courses 302 Minor Crushed Aggregate 750 ton 303 Road Reconditioning 20.5 mi 311 Stabilized Aggregate Surface Course 67000 ton

DIVISION 600 – Incidental Construction 602 Culverts 350 lnft 607 Cleaning, Relaying, & Repairing Existing Drainage Structures 10 each 622 Rental Equipment (yes/no) Yes 623 General Labor (yes/no) Yes 624 Topsoil (landscaping & related items) 0.5 ac 625 Turf Establishment (indicate seeding or mulching separately) 4 slry 635 Temporary Traffic Control – Flagger 1500 hr 635 Temporary Traffic Control – LPSM Yes

File details come from the government source that posted it. Updated .