PROJECT_DESCRIPTION_Shoup.pdf
PDF 17 KB Posted
- Attached to
- ID PFH 91(1), Williams Creek (Shoup) Bridge Replacement Federal contract opportunity
- Solicitation number
- DTFH7016B00008
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| BidSum_Shoup.pdf | ||
| A001.pdf | ||
| Q A_Shoup_6-01.pdf | ||
| mt-a2013018_Pavement_Report.pdf | ||
| Detour-EW-2015-07-17.pdf | ||
| SWPPP-Reduced_Williams_Creek_(Shoup)_Bridge_Replacement_ID_PFH_91(1).pdf | ||
| wm_ew_10025-10270.pdf | ||
| Fife-EW-2015-07-17.pdf | ||
| shoup_bridge_mods_asbuilts_plans1.pdf | ||
| Plan_Request_for_Internet.pdf | ||
| Cole_Ranch_No_TCE.pdf | ||
| CrossSections.pdf | ||
| Hinton_No_TCE.pdf | ||
| wm_ew_10550-11150.pdf | ||
| wm_ew_10500-10550.pdf | ||
| ShoupBridgeFinalGeotechReport_20151109.pdf | ||
| mt-a2013018_Geotechnical_Bridge_Report.pdf | ||
| wm_ew_11150-11324.pdf | ||
| idpfh911_Plans_041316_Sign-Off_2.pdf | ||
| shoup_bridge_original_plans.pdf | ||
| Shoup_bridge_backgroundand_inspectionApril2013.pdf | ||
| IFB_Shoup.pdf |
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID PFH 91(1), Williams Creek (Shoup) Bridge Replacement, Lemhi County, Idaho
The work consists of replacing the existing Williams Creek (Shoup) Bridge with a two-lane structure and realigning the existing roadway approaches. The bridge replacement will be done using slide-in bridge construction methods.
The project includes construction of a single span, 224-foot long structural steel arch bridge with cast-in-place concrete deck. Abutments are founded on steel H-piles. The work includes demolition of the existing steel girder bridge upon completion of the new structure and other small items of work.
Project length: 0.264 Miles
Tentative Fixed Completion Date: Spring 2018 (Once solicitation is issued, see FAR Clause 52.211-10 for exact date.)
Tentative Advertisement Date: Spring 2016
Estimated Price Range: Between $5 million and $7 million
Location: 5 miles south of Salmon, Idaho
DESCRIPTION OF WORK in US CUSTOMARY UNITS FP-14 Schedule A
DIVISION 150 – Project Requirements 152 Construction Survey & Staking (yes/no) Yes 153 Contractor Quality Control and Assurance (yes/no) Yes 154 Contractor Sampling & Testing (yes/no) Yes 155 Schedules for Construction Contracts (construction schedules) (yes/no) Yes
DIVISION 200 – Earthwork 201 Clearing & Grubbing 1.3 ACRE 203 Removal of Structures & Obstructions (existing bridge) 1 LPSM 204 Waste 6,900 CUYD
DIVISION 250 – Slope Reinforcement and Retaining Walls 255 Mechanically Stabilized Earth Walls (retaining walls) 970 SQFT
DIVISION 300 – Aggregate and Base Courses 302 Minor Crushed Aggregate 4,200 TON
DIVISION 400 – Asphalt Pavements & Surface Treatments
DESCRIPTION OF WORK in US CUSTOMARY UNITS FP-14 Schedule A
403 Asphalt Concrete 2,300 TON
DIVISION 550 – Bridge Construction 551 Driven Piles 610 LNFT 552 Structural Concrete (concrete – major structures) 590 CUYD 554 Reinforcing Steel 111,100 LB 555 Steel Structures (structures, steel) 1 LPSM 556 Bridge Railing 520 LNFT 562 Temporary Works (bridge erection system) 1 LPSM 562 Temporary Works (temp. support structure) 1 LPSM 562 Temporary Works (work bridge) 1 LPSM 581 Structural Cable Systems 1 LPSM
DIVISION 600 – Incidental Construction 602 Culverts & Drains (18-inch pipe) 160 LNFT 602 Culverts & Drains (24-inch pipe) 130 LNFT 602 Culverts & Drains (30-inch arch pipe) 60 LNFT 604 Manholes, Inlets, & Catch Basins (catch basin) 3 EACH 611 Water Systems (irrigation system) 1 LPSM 617 Guardrail 265 LNFT 617 Guardrail (terminal section type tangent) 4 EACH 617 Guardrail (structural transition railing) 85 LNFT 622 Rental Equipment (yes/no) Yes 623 General Labor (yes/no) Yes 624 Topsoil (placing manufactured topsoil) 50 CUYD 625 Turf Establishment (seeding and mulching) 1.3 ACRE 626 Plants, Trees, Shrubs, Vines & Groundcovers 1.3 ACRE 629 Rolled Erosion Control Products & Cellular Confinement Systems (turf establishment) 160 SQYD 634 Permanent Pavement Markings (traffic pavement markings) 10,500 LNFT 635 Temporary Traffic Control – Flagger 600 FXHR 635 Temporary Traffic Control – Crash Cushion 4 EACH 635 Temporary Traffic Control – Portable Changeable Message Sign 2 EACH