AK PRA DENA 10(32), Riprap Placement at Toklat Rest Stop, Denali National Park, Denali Borough, Alaska
The work consists of excavation of existing streambed material along existing sheetpile wall and installing approximately 900 lnft of class 4 riprap revetment along with 5 class 6 riprap barbs. Also, stockpiling of an additional 100 cuyd of class 6 riprap to be used for future barb repairs and other small items of work.
Project length: 0.171 Miles
Fixed Completion Date: This project is being offered under three schedules.
(Schedule A –July 13, 2009) (Schedule B –July 23, 2009) (Schedule C –August 4, 2009)
Estimated Price Range: $500,000 to $1 million
Location: 170 miles Southwest of Fairbanks, Alaska
DESCRIPTION OF WORK in US CUSTOMARY UNITS
DIVISION 150 –Project Requirements (All Schedules) 152 Construction Survey & Staking X YES NO 153 Contractor Quality Control and Assurance X YES NO 154 Contractor Sampling & Testing YES X NO 155 Schedules for Construction Contracts (construction schedules) X YES NO
DIVISION 200 –Earthwork Blasting Consultant (Consultant/Engineering Services) Yes X No
207 Earthwork Geotextiles (geotextiles) Sched A –2017 sqyd Sched B –2677 sqyd Sched C –3410 sqyd
208 Structure Excavation Sched A - 714 cuyd Sched B –874 cuyd Sched C –1052 cuyd
DIVISION 250 - Slope Reinforcement and Retaining Walls 251 Riprap Schedule A
Class 4 - 1210 cuyd Class 6 –575 cuyd
Schedule B Class 4 - 1606 cuyd Class 6 –575 cuyd
Schedule C Class 4 - 2046 cuyd Class 6 –575 cuyd