AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

N/A

PAGE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE NO. 5. PROJECT NO. (If applicable)

A001 3/25/2009 N/A AK PRA DENA 10(32)

Rip Rap Replacement at Toklat..

6. ISSUED BY CODE N/A 7. ADMINISTERED BY (If other than Item 6) CODE N/A

Department of Transportation Federal Highway Administration 610 East Fifth Street Vancouver WA 98661-3801

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code) 9A. AMENDMENT OF SOLICITATION NO.

X DTFH70-08-B-00009

9B. DATED (SEE ITEM 11)

03/19/2009

10A. MODIFICATION OF CONTRACT/ORDER NO.

N/A

10B. DATED (SEE ITEM 13)

CODE: N/A FACILITY CODE: N/A

N/A

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

| X | The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

(__ ) is extended, ( x ) is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

N/A

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN

ITEM 10A.

N/A

B THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

N/A

C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

N/A

D OTHER (Specify type of modification and authority) N/A

E. IMPORTANT: Contractor n/a is not, n/a is required to sign this document and return n/a copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

AK PRA DENA 10(32) Rip Rap Replacement at Toklat Rest Stop Amendment A001 is issued to revise the following:

Page C-2, Revises contract Clause 52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984) Alternate I (Apr 1984)

Sets different fixed completion dates for each of the 3 alternate bid schedules.

ENCLOSURE: Page C-3

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15a. NAME AND TITLE OF SIGNER (Type or print) 15a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

N/A

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY_________________________________________ BY N/A___________________________ N/A (Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070

PREVIOUS EDITION NOT USABLE

30-105 STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

C-3

Contract Clauses AK PRA DENA 10(32), Riprap Placement at Toklat Rest Stop

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities and Improvements (Apr 1984)

52.236-10 Operations and Storage Areas (Apr 1984) 52.236-11 Use and Possession Prior to Completion (Apr 1984) 52.236-12 Cleaning up (Apr 1984) 52.236-13 Accident Prevention (Nov 1991) - Alternate 1 (Nov 1991) 52.236-15 Schedules for Construction Contracts (Apr 1984) 52.236-17 Layout of Work (Apr 1984) 52.236-21 Specifications and Drawings for Construction (Feb 1997) Alt II (Apr 1984) 52.236-26 Preconstruction Conference (Feb 1995) 52.242-13 Bankruptcy (Jul 1995) 52.242-14 Suspension of Work (Apr 1984) 52.243-4 Changes (June 2007) 52.244-2 Subcontracts (June 2007) 52.244-6 Subcontracts for Commercial Items (Feb 2009) 52.246-12 Inspection of Construction (Aug 1996) 52.247-64 Preference for Privately Owned U.S. Flag Commercial Vessels (Feb 2006) 52.248-3 Value Engineering-Construction (Sep 2006) Alternate 1 (Apr 1984) 52.249-2 Termination for Convenience of the Government (Fixed Price) (May 2004)—

Alternate 1 (Sep 1996) 52.249-10 Default (Fixed-Price Construction) (Apr 1984) 52.253-1 Computer Generated Forms (Jan 1991) 1252.211-70 Index for Specifications (Apr 2005) 1252.223-73 Seat Belt Use Policies and Programs (Apr 2005) 1252.228-73 Notification of Miller Act Payment Bond Protection (Apr 2005)

(c) The surety which has provided the payment bond under the prime contract is:

________________________________(name) ________________________________(Street Address) ________________________________(City, State, Zip Code) ________________________________(Contact & Telephone number)

1252.242-73 Contracting Officer's Technical Representative (Oct 1994)

2. Full Text Clauses

52.204-1 Approval of Contract (Dec 1989)

This contract is subject to the written approval of the Western Federal Lands’ Division Engineer (or delegate) or one level above the Contracting Officer, and shall not be binding until so approved.

52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984) Alternate I (Apr 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than August 31, 2009 (Schedule C), August 20, 2009 (Schedule B), or August 10, 2009 (Schedule A) subject to such extensions as may be authorized. The time stated for completion shall include final cleanup of the premises.

The completion date is based on the assumption that the successful offeror will receive the notice to proceed by June 19, 2009 (all Schedules). The completion date will be extended by the number of calendar days after the above date that the contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.

Revised by Amendment A001