Tabulation of Bids Report Date: 08/11/15
1 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: CA FLAP CR4F009(1)
Project Name: J F Kennedy Memorial Drive
Schedule: A
Schedule Type: Base
Solcitation No: DTFH6814B00017
Division: Central Federal Lands
State: CA County: Shasta
Federal Land: Whiskeytown NRA Opened at: Lakewood
Opened by: Jeremiah Rogers
Date: 08/06/15
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
McCullough Construction Inc. $3,563,455.00 57 Alder Grove Road Arcata, CA, CA 95521
Hat Creek Construction & Materials, Inc. $3,692,398.00 24339 Highway 89 N Burney, CA 96013
Engineer's Estimate $4,094,730.00
2 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: CA FLAP CR4F009(1)
Project Name: J F Kennedy Memorial Drive
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0010 15101-0000 MOBILIZATION
McCullough Construction Inc. Lump Sum $300,000.00 Hat Creek Construction & Materials, Inc. Lump Sum $366,257.00 Engineer's Estimate ALL LPSM Lump Sum $302,003.00
A0020 15206-0000 SLOPE, REFERENCE, AND CLEARING AND GRUBBING STAKE
McCullough Construction Inc. $300.00 $5,700.00 Hat Creek Construction & Materials, Inc. $390.00 $7,410.00 Engineer's Estimate 19.000 STA $295.00 $5,605.00
A0030 15210-3000 CENTERLINE, VERIFICATION AND STAKING
McCullough Construction Inc. $100.00 $24,800.00 Hat Creek Construction & Materials, Inc. $117.00 $29,016.00 Engineer's Estimate 248.000 STA $45.00 $11,160.00
A0040 15215-3000 SURVEY AND STAKING, DRAINAGE STRUCTURE
McCullough Construction Inc. $500.00 $15,000.00 Hat Creek Construction & Materials, Inc. $595.00 $17,850.00 Engineer's Estimate 30 EACH $2,000.00 $60,000.00
A0050 15216-2000 SURVEY AND STAKING, GRADE FINISHING STAKES
McCullough Construction Inc. $1,250.00 $15,000.00 Hat Creek Construction & Materials, Inc. $230.00 $2,760.00 Engineer's Estimate 12.000 STA $400.00 $4,800.00
A0060 15301-0000 CONTRACTOR QUALITY CONTROL
McCullough Construction Inc. Lump Sum $80,000.00 Hat Creek Construction & Materials, Inc. Lump Sum $75,000.00 Engineer's Estimate ALL LPSM Lump Sum $45,000.00
A0070 15401-0000 CONTRACTOR TESTING
McCullough Construction Inc. Lump Sum $45,000.00 Hat Creek Construction & Materials, Inc. Lump Sum $90,000.00 Engineer's Estimate ALL LPSM Lump Sum $45,000.00
3 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: CA FLAP CR4F009(1)
Project Name: J F Kennedy Memorial Drive
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0080 15501-0000 CONSTRUCTION SCHEDULE
McCullough Construction Inc. Lump Sum $10,000.00 Hat Creek Construction & Materials, Inc. Lump Sum $10,000.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00
A0090 15702-1000 SOIL EROSION CONTROL, TEMPORARY DIVERSION CHANNEL (CULVERT)
McCullough Construction Inc. Lump Sum $400.00 Hat Creek Construction & Materials, Inc. Lump Sum $10,000.00 Engineer's Estimate ALL LPSM Lump Sum $12,000.00
A0100 15705-1500 SOIL EROSION CONTROL, SEDIMENT WATTLE
McCullough Construction Inc. $5.00 $44,500.00 Hat Creek Construction & Materials, Inc. $5.50 $48,950.00 Engineer's Estimate 8,900 LNFT $3.50 $31,150.00
A0110 15706-0200 SOIL EROSION CONTROL, CHECK DAM (RIPRAP)
McCullough Construction Inc. $200.00 $32,000.00 Hat Creek Construction & Materials, Inc. $180.00 $28,800.00 Engineer's Estimate 160 EACH $200.00 $32,000.00
A0120 15706-0200 SOIL EROSION CONTROL, CHECK DAM (SEDIMENT LOG)
McCullough Construction Inc. $100.00 $10,000.00 Hat Creek Construction & Materials, Inc. $125.00 $12,500.00 Engineer's Estimate 100 EACH $160.00 $16,000.00
A0130 15706-0300 SOIL EROSION CONTROL, SANDBAG
McCullough Construction Inc. $10.00 $200.00 Hat Creek Construction & Materials, Inc. $18.00 $360.00 Engineer's Estimate 20 EACH $20.00 $400.00
A0140 15706-1000 SOIL EROSION CONTROL, INLET PROTECTION
McCullough Construction Inc. $200.00 $2,400.00 Hat Creek Construction & Materials, Inc. $335.00 $4,020.00 Engineer's Estimate 12 EACH $116.00 $1,392.00
4 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: CA FLAP CR4F009(1)
Project Name: J F Kennedy Memorial Drive
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0150 15706-1700 SOIL EROSION CONTROL, WATER BAR (ROLLING DIP)
McCullough Construction Inc. $750.00 $750.00 Hat Creek Construction & Materials, Inc. $2,000.00 $2,000.00 Engineer's Estimate 1 EACH $550.00 $550.00
A0160 15802-0000 WATERING FOR DUST CONTROL
McCullough Construction Inc. Lump Sum $25,000.00 Hat Creek Construction & Materials, Inc. Lump Sum $20,000.00 Engineer's Estimate ALL LPSM Lump Sum $25,000.00
A0170 20102-0000 CLEARING AND GRUBBING
McCullough Construction Inc. Lump Sum $20,000.00 Hat Creek Construction & Materials, Inc. Lump Sum $75,000.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00
A0180 20301-1400 REMOVAL OF INLET
McCullough Construction Inc. $1,000.00 $6,000.00 Hat Creek Construction & Materials, Inc. $300.00 $1,800.00 Engineer's Estimate 6 EACH $725.00 $4,350.00
A0190 20301-1900 REMOVAL OF PIPE CULVERT
McCullough Construction Inc. $1,000.00 $10,000.00 Hat Creek Construction & Materials, Inc. $700.00 $7,000.00 Engineer's Estimate 10 EACH $1,000.00 $10,000.00
A0200 20301-2300 REMOVAL OF SIGN/MARKER
McCullough Construction Inc. $120.00 $7,200.00 Hat Creek Construction & Materials, Inc. $40.00 $2,400.00 Engineer's Estimate 60 EACH $100.00 $6,000.00
A0210 20302-0300 REMOVAL OF CURB AND GUTTER, CONCRETE
McCullough Construction Inc. $30.00 $1,950.00 Hat Creek Construction & Materials, Inc. $65.00 $4,225.00 Engineer's Estimate 65 LNFT $17.00 $1,105.00
5 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: CA FLAP CR4F009(1)
Project Name: J F Kennedy Memorial Drive
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0220 20302-0400 REMOVAL OF CURB, ASPHALT
McCullough Construction Inc. $2.00 $22,600.00 Hat Creek Construction & Materials, Inc. $1.50 $16,950.00 Engineer's Estimate 11,300 LNFT $4.00 $45,200.00
A0230 20302-1200 REMOVAL OF GUARDRAIL (SALVAGE RAIL AND HARDWARE)
McCullough Construction Inc. $4.00 $32,000.00 Hat Creek Construction & Materials, Inc. $3.95 $31,600.00 Engineer's Estimate 8,000 LNFT $4.75 $38,000.00
A0240 20303-1600 REMOVAL OF PAVEMENT, ASPHALT
McCullough Construction Inc. $2.00 $4,940.00 Hat Creek Construction & Materials, Inc. $5.00 $12,350.00 Engineer's Estimate 2,470 SQYD $9.50 $23,465.00
A0250 20303-3000 REMOVAL OF SIDEWALK, ASPHALT
McCullough Construction Inc. $15.00 $1,125.00 Hat Creek Construction & Materials, Inc. $50.00 $3,750.00 Engineer's Estimate 75 SQYD $15.00 $1,125.00
A0260 20401-0000 ROADWAY EXCAVATION
McCullough Construction Inc. $24.00 $79,200.00 Hat Creek Construction & Materials, Inc. $25.00 $82,500.00 Engineer's Estimate 3,300 CUYD $50.00 $165,000.00
A0270 20402-0000 SUBEXCAVATION
McCullough Construction Inc. $70.00 $147,000.00 Hat Creek Construction & Materials, Inc. $80.00 $168,000.00 Engineer's Estimate 2,100 CUYD $54.00 $113,400.00
A0280 20425-1000 DITCH, EXCAVATION
McCullough Construction Inc. $20.00 $2,000.00 Hat Creek Construction & Materials, Inc. $20.00 $2,000.00 Engineer's Estimate 100 LNFT $25.00 $2,500.00
6 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: CA FLAP CR4F009(1)
Project Name: J F Kennedy Memorial Drive
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0290 20440-0000 ROUNDING CUT SLOPES
McCullough Construction Inc. $30.00 $13,500.00 Hat Creek Construction & Materials, Inc. $20.00 $9,000.00 Engineer's Estimate 450 LNFT $10.00 $4,500.00
A0300 20465-0000 CONSERVE AND PLACE BOULDER
McCullough Construction Inc. $200.00 $1,600.00 Hat Creek Construction & Materials, Inc. $500.00 $4,000.00 Engineer's Estimate 8 EACH $300.00 $2,400.00
A0310 20466-0000 CONSERVE AND STOCKPILE TOPSOIL
McCullough Construction Inc. $35.00 $4,200.00 Hat Creek Construction & Materials, Inc. $50.00 $6,000.00 Engineer's Estimate 120 CUYD $12.00 $1,440.00
A0320 25101-2000 PLACED RIPRAP, CLASS 2
McCullough Construction Inc. $100.00 $26,000.00 Hat Creek Construction & Materials, Inc. $165.00 $42,900.00 Engineer's Estimate 260 CUYD $225.00 $58,500.00
A0330 25101-3000 PLACED RIPRAP, CLASS 3
McCullough Construction Inc. $100.00 $6,000.00 Hat Creek Construction & Materials, Inc. $165.00 $9,900.00 Engineer's Estimate 60 CUYD $250.00 $15,000.00
A0340 25101-7000 PLACED RIPRAP, CLASS 7
McCullough Construction Inc. $100.00 $8,000.00 Hat Creek Construction & Materials, Inc. $165.00 $13,200.00 Engineer's Estimate 80 CUYD $300.00 $24,000.00
A0350 25305-1000 REVET MATTRESS, GALVANIZED OR ALUMINIZED COATED
McCullough Construction Inc. $500.00 $6,000.00 Hat Creek Construction & Materials, Inc. $600.00 $7,200.00 Engineer's Estimate 12 SQYD $250.00 $3,000.00
7 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: CA FLAP CR4F009(1)
Project Name: J F Kennedy Memorial Drive
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0360 30302-1000 DITCH RECONDITIONING
McCullough Construction Inc. $5.00 $22,500.00 Hat Creek Construction & Materials, Inc. $6.00 $27,000.00 Engineer's Estimate 4,500 LNFT $3.80 $17,100.00
A0370 30306-0000 PULVERIZING
McCullough Construction Inc. $2.05 $148,625.00 Hat Creek Construction & Materials, Inc. $1.80 $130,500.00 Engineer's Estimate 72,500 SQYD $2.50 $181,250.00
A0380 30802-2000 ROADWAY AGGREGATE, METHOD 2
McCullough Construction Inc. $60.00 $186,000.00 Hat Creek Construction & Materials, Inc. $45.00 $139,500.00 Engineer's Estimate 3,100 TON $30.00 $93,000.00
A0390 40101-5600 SUPERPAVE PAVEMENT, 1/2-INCH OR 3/4-INCH NOMINAL MAXIMUM SIZE AGGREGATE, 0.3 TO <3 MILLION
ESAL
McCullough Construction Inc. $86.00 $1,062,100.00 Hat Creek Construction & Materials, Inc. $80.00 $988,000.00 Engineer's Estimate 12,350 TON $110.00 $1,358,500.00
A0410 40105-3000 ANTISTRIP ADDITIVE, TYPE 3
McCullough Construction Inc. $7.00 $840.00 Hat Creek Construction & Materials, Inc. $10.00 $1,200.00 Engineer's Estimate 120 TON $260.00 $31,200.00
A0430 40920-1000 FOG SEAL, EMULSIFIED ASPHALT GRADE CSS-1 OR CSS-1H, SS-1 OR SS-1H
McCullough Construction Inc. $600.00 $21,000.00 Hat Creek Construction & Materials, Inc. $500.00 $17,500.00 Engineer's Estimate 35 TON $320.00 $11,200.00
A0440 40960-0000 BLOTTER
McCullough Construction Inc. $700.00 $7,000.00 Hat Creek Construction & Materials, Inc. $70.00 $700.00 Engineer's Estimate 10 TON $100.00 $1,000.00
8 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: CA FLAP CR4F009(1)
Project Name: J F Kennedy Memorial Drive
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0450 41201-1000 TACK COAT GRADE CSS-1, CSS-1H, SS-1, OR SS-1H
McCullough Construction Inc. $400.00 $26,000.00 Hat Creek Construction & Materials, Inc. $375.00 $24,375.00 Engineer's Estimate 65 TON $625.00 $40,625.00
A0460 60103-0140 CONCRETE, HEADWALL FOR 24-INCH PIPE CULVERT
McCullough Construction Inc. $3,200.00 $9,600.00 Hat Creek Construction & Materials, Inc. $6,500.00 $19,500.00 Engineer's Estimate 3 EACH $5,000.00 $15,000.00
A0470 60103-2080 CONCRETE, HEADWALL FOR 72-INCH EQUIVALENT DIAMETER PIPE CULVERT (HEADWALL AND
WINGWALLS)
McCullough Construction Inc. $12,500.00 $25,000.00 Hat Creek Construction & Materials, Inc. $40,000.00 $80,000.00 Engineer's Estimate 2 EACH $30,000.00 $60,000.00
A0480 60201-0800 24-INCH PIPE CULVERT
McCullough Construction Inc. $185.00 $46,250.00 Hat Creek Construction & Materials, Inc. $175.00 $43,750.00 Engineer's Estimate 250 LNFT $170.00 $42,500.00
A0490 60201-1000 36-INCH PIPE CULVERT
McCullough Construction Inc. $200.00 $11,000.00 Hat Creek Construction & Materials, Inc. $170.00 $9,350.00 Engineer's Estimate 55 LNFT $260.00 $14,300.00
A0500 60202-0400 24-INCH EQUIVALENT DIAMETER ARCH OR ELLIPTICAL PIPE CULVERT
McCullough Construction Inc. $200.00 $25,000.00 Hat Creek Construction & Materials, Inc. $170.00 $21,250.00 Engineer's Estimate 125 LNFT $170.00 $21,250.00
A0510 60202-1200 72-INCH EQUIVALENT DIAMETER ARCH OR ELLIPTICAL PIPE CULVERT
McCullough Construction Inc. $450.00 $27,000.00 Hat Creek Construction & Materials, Inc. $400.00 $24,000.00 Engineer's Estimate 60 LNFT $360.00 $21,600.00
9 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: CA FLAP CR4F009(1)
Project Name: J F Kennedy Memorial Drive
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0520 60210-0800 END SECTION FOR 24-INCH PIPE CULVERT
McCullough Construction Inc. $600.00 $3,000.00 Hat Creek Construction & Materials, Inc. $700.00 $3,500.00 Engineer's Estimate 5 EACH $1,000.00 $5,000.00
A0530 60210-1000 END SECTION FOR 36-INCH PIPE CULVERT
McCullough Construction Inc. $750.00 $750.00 Hat Creek Construction & Materials, Inc. $1,200.00 $1,200.00 Engineer's Estimate 1 EACH $1,600.00 $1,600.00
A0540 60211-0800 END SECTION FOR 24-INCH EQUIVALENT DIAMETER ARCH OR ELLIPTICAL PIPE CULVERT
McCullough Construction Inc. $700.00 $1,400.00 Hat Creek Construction & Materials, Inc. $700.00 $1,400.00 Engineer's Estimate 2 EACH $1,000.00 $2,000.00
A0550 60403-0000 INLET (PIPE RISER WITH DEBRIS RACK CAGE)
McCullough Construction Inc. $3,500.00 $7,000.00 Hat Creek Construction & Materials, Inc. $6,000.00 $12,000.00 Engineer's Estimate 2 EACH $3,750.00 $7,500.00
A0560 60403-0700 INLET, CALTRANS (TYPE GO WITH TYPE 24-12X METAL GRATE)
McCullough Construction Inc. $3,000.00 $9,000.00 Hat Creek Construction & Materials, Inc. $2,500.00 $7,500.00 Engineer's Estimate 3 EACH $3,700.00 $11,100.00
A0570 60403-0700 INLET, CALTRANS (MODIFIED TYPE G2 WITH TYPE 24-12X METAL GRATE)
McCullough Construction Inc. $3,200.00 $3,200.00 Hat Creek Construction & Materials, Inc. $2,500.00 $2,500.00 Engineer's Estimate 1 EACH $6,500.00 $6,500.00
A0580 60403-0700 INLET, CALTRANS (TYPE G2 WITH TYPE 24-12X METAL GRATE)
McCullough Construction Inc. $3,200.00 $6,400.00 Hat Creek Construction & Materials, Inc. $2,500.00 $5,000.00 Engineer's Estimate 2 EACH $5,100.00 $10,200.00
10 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: CA FLAP CR4F009(1)
Project Name: J F Kennedy Memorial Drive
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0590 60412-2000 REMOVE AND RESET MANHOLE FRAME AND COVER
McCullough Construction Inc. $1,500.00 $1,500.00 Hat Creek Construction & Materials, Inc. $2,000.00 $2,000.00 Engineer's Estimate 1 EACH $1,600.00 $1,600.00
A0600 60501-0000 STANDARD UNDERDRAIN SYSTEM
McCullough Construction Inc. $175.00 $32,375.00 Hat Creek Construction & Materials, Inc. $75.00 $13,875.00 Engineer's Estimate 185 LNFT $70.00 $12,950.00
A0610 60704-0000 CLEANING CULVERT IN PLACE
McCullough Construction Inc. $3,500.00 $28,000.00 Hat Creek Construction & Materials, Inc. $3,200.00 $25,600.00 Engineer's Estimate 8 EACH $1,000.00 $8,000.00
A0620 60705-0000 RECONDITIONING DRAINAGE STRUCTURE
McCullough Construction Inc. $2,500.00 $10,000.00 Hat Creek Construction & Materials, Inc. $1,500.00 $6,000.00 Engineer's Estimate 4 EACH $2,800.00 $11,200.00
A0630 60901-2300 CURB, ASPHALT, 6-INCH DEPTH
McCullough Construction Inc. $4.00 $64,000.00 Hat Creek Construction & Materials, Inc. $5.50 $88,000.00 Engineer's Estimate 16,000 LNFT $4.50 $72,000.00
A0640 60902-1000 CURB AND GUTTER, CONCRETE, 12-INCH DEPTH (SPILL PAN)
McCullough Construction Inc. $45.00 $16,650.00 Hat Creek Construction & Materials, Inc. $30.00 $11,100.00 Engineer's Estimate 370 LNFT $35.00 $12,950.00
A0650 60902-1000 CURB AND GUTTER, CONCRETE, 12-INCH DEPTH
McCullough Construction Inc. $35.00 $6,650.00 Hat Creek Construction & Materials, Inc. $30.00 $5,700.00 Engineer's Estimate 190 LNFT $35.00 $6,650.00
11 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: CA FLAP CR4F009(1)
Project Name: J F Kennedy Memorial Drive
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0660 60905-1000 GUTTER, CONCRETE
McCullough Construction Inc. $45.00 $4,050.00 Hat Creek Construction & Materials, Inc. $36.00 $3,240.00 Engineer's Estimate 90 LNFT $30.00 $2,700.00
A0670 61108-1000 ADJUST WATER VALVE
McCullough Construction Inc. $250.00 $250.00 Hat Creek Construction & Materials, Inc. $1,500.00 $1,500.00 Engineer's Estimate 1 EACH $780.00 $780.00
A0680 61501-0300 SIDEWALK, FIBER REINFORCED COLORED CONCRETE
McCullough Construction Inc. $100.00 $6,000.00 Hat Creek Construction & Materials, Inc. $87.00 $5,220.00 Engineer's Estimate 60 SQYD $75.00 $4,500.00
A0690 61503-1000 MEDIAN, CONCRETE
McCullough Construction Inc. $110.00 $35,200.00 Hat Creek Construction & Materials, Inc. $87.00 $27,840.00 Engineer's Estimate 320 SQYD $65.00 $20,800.00
A0700 61505-1000 ACCESSIBILITY RAMP, CONCRETE (CALTRANS CASE C)
McCullough Construction Inc. $2,500.00 $2,500.00 Hat Creek Construction & Materials, Inc. $1,450.00 $1,450.00 Engineer's Estimate 1 EACH $3,000.00 $3,000.00
A0710 61701-4500 GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A STEEL POSTS (STAINED)
McCullough Construction Inc. $35.00 $262,500.00 Hat Creek Construction & Materials, Inc. $33.50 $251,250.00 Engineer's Estimate 7,500 LNFT $40.00 $300,000.00
A0720 61702-1500 TERMINAL SECTION, TYPE MGS TANGENT (STAINED)
McCullough Construction Inc. $3,500.00 $3,500.00 Hat Creek Construction & Materials, Inc. $3,500.00 $3,500.00 Engineer's Estimate 1 EACH $2,500.00 $2,500.00
12 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: CA FLAP CR4F009(1)
Project Name: J F Kennedy Memorial Drive
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0730 61702-1600 TERMINAL SECTION, TYPE MGS FLARED (STAINED)
McCullough Construction Inc. $2,500.00 $17,500.00 Hat Creek Construction & Materials, Inc. $2,500.00 $17,500.00 Engineer's Estimate 7 EACH $2,500.00 $17,500.00
A0740 61702-1700 TERMINAL SECTION, TYPE MGS-BAT (STAINED)
McCullough Construction Inc. $1,700.00 $5,100.00 Hat Creek Construction & Materials, Inc. $1,500.00 $4,500.00 Engineer's Estimate 3 EACH $3,500.00 $10,500.00
A0750 62201-0250 DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY
McCullough Construction Inc. $110.00 $4,400.00 Hat Creek Construction & Materials, Inc. $100.00 $4,000.00 Engineer's Estimate 40 HOUR $110.00 $4,400.00
A0760 62201-0900 WHEEL LOADER, 2 CUBIC YARD MINIMUM RATED CAPACITY
McCullough Construction Inc. $170.00 $6,800.00 Hat Creek Construction & Materials, Inc. $157.00 $6,280.00 Engineer's Estimate 40 HOUR $155.00 $6,200.00
A0770 62201-2050 ROLLER
McCullough Construction Inc. $150.00 $4,500.00 Hat Creek Construction & Materials, Inc. $135.00 $4,050.00 Engineer's Estimate 30 HOUR $125.00 $3,750.00
A0780 62201-2850 MOTOR GRADER, 12 FOOT MINIMUM BLADE
McCullough Construction Inc. $175.00 $5,250.00 Hat Creek Construction & Materials, Inc. $150.00 $4,500.00 Engineer's Estimate 30 HOUR $180.00 $5,400.00
A0790 62201-3200 HYDRAULIC EXCAVATOR, CRAWLER MOUNTED, 1.5 CUBIC YARD MINIMUM CAPACITY
McCullough Construction Inc. $170.00 $13,600.00 Hat Creek Construction & Materials, Inc. $150.00 $12,000.00 Engineer's Estimate 80 HOUR $70.00 $5,600.00
13 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: CA FLAP CR4F009(1)
Project Name: J F Kennedy Memorial Drive
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0800 62301-0000 GENERAL LABOR
McCullough Construction Inc. $60.00 $4,800.00 Hat Creek Construction & Materials, Inc. $65.00 $5,200.00 Engineer's Estimate 80 HOUR $70.00 $5,600.00
A0810 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES
McCullough Construction Inc. $125.00 $5,000.00 Hat Creek Construction & Materials, Inc. $110.00 $4,400.00 Engineer's Estimate 40 HOUR $130.00 $5,200.00
A0820 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES
McCullough Construction Inc. $140.00 $5,600.00 Hat Creek Construction & Materials, Inc. $177.00 $7,080.00 Engineer's Estimate 40 HOUR $170.00 $6,800.00
A0830 62401-0200 FURNISHING AND PLACING TOPSOIL, 3-INCH DEPTH
McCullough Construction Inc. $25.00 $32,500.00 Hat Creek Construction & Materials, Inc. $12.00 $15,600.00 Engineer's Estimate 1,300 SQYD $7.80 $10,140.00
A0840 62407-0000 PLACING CONSERVED TOPSOIL
McCullough Construction Inc. $12.00 $1,440.00 Hat Creek Construction & Materials, Inc. $70.00 $8,400.00 Engineer's Estimate 120 CUYD $35.00 $4,200.00
A0850 62901-1000 ROLLED EROSION CONTROL PRODUCT, TYPE 3.B
McCullough Construction Inc. $7.00 $2,100.00 Hat Creek Construction & Materials, Inc. $8.00 $2,400.00 Engineer's Estimate 300 SQYD $7.50 $2,250.00
A0860 63301-0000 SIGN SYSTEM
McCullough Construction Inc. $325.00 $19,500.00 Hat Creek Construction & Materials, Inc. $320.00 $19,200.00 Engineer's Estimate 60 EACH $500.00 $30,000.00
14 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: CA FLAP CR4F009(1)
Project Name: J F Kennedy Memorial Drive
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0870 63308-4000 OBJECT MARKER, TYPE CALTRANS TYPE L (TYPE L-2)
McCullough Construction Inc. $55.00 $4,565.00 Hat Creek Construction & Materials, Inc. $45.00 $3,735.00 Engineer's Estimate 83 EACH $75.00 $6,225.00
A0880 63315-0000 RUMBLE STRIP
McCullough Construction Inc. $110.00 $6,600.00 Hat Creek Construction & Materials, Inc. $76.00 $4,560.00 Engineer's Estimate 60 SQYD $300.00 $18,000.00
A0890 63316-1000 REMOVE AND RESET SIGN
McCullough Construction Inc. $325.00 $4,875.00 Hat Creek Construction & Materials, Inc. $300.00 $4,500.00 Engineer's Estimate 15 EACH $250.00 $3,750.00
A0900 63401-1500 PAVEMENT MARKINGS, TYPE H, SOLID
McCullough Construction Inc. $0.50 $50,750.00 Hat Creek Construction & Materials, Inc. $0.45 $45,675.00 Engineer's Estimate 101,500 LNFT $1.15 $116,725.00
A0910 63403-0800 PAVEMENT MARKINGS, TYPE H
McCullough Construction Inc. $20.00 $440.00 Hat Creek Construction & Materials, Inc. $10.00 $220.00 Engineer's Estimate 22 SQFT $5.00 $110.00
A0920 63405-2950 PAVEMENT MARKINGS, TYPE H, STRAIGHT ARROW
McCullough Construction Inc. $260.00 $260.00 Hat Creek Construction & Materials, Inc. $260.00 $260.00 Engineer's Estimate 1 EACH $220.00 $220.00
A0930 63405-3100 PAVEMENT MARKINGS, TYPE H, "STOP" WORD MESSAGE
McCullough Construction Inc. $250.00 $2,000.00 Hat Creek Construction & Materials, Inc. $250.00 $2,000.00 Engineer's Estimate 8 EACH $425.00 $3,400.00
15 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: CA FLAP CR4F009(1)
Project Name: J F Kennedy Memorial Drive
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0940 63405-3250 PAVEMENT MARKINGS, TYPE H, ACCESSIBILITY SYMBOL
McCullough Construction Inc. $280.00 $840.00 Hat Creek Construction & Materials, Inc. $280.00 $840.00 Engineer's Estimate 3 EACH $300.00 $900.00
A0950 63407-0400 RECESSED PAVEMENT MARKER TYPE D
McCullough Construction Inc. $8.00 $16,000.00 Hat Creek Construction & Materials, Inc. $7.80 $15,600.00 Engineer's Estimate 2,000 EACH $20.00 $40,000.00
A0960 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
McCullough Construction Inc. $130.00 $260.00 Hat Creek Construction & Materials, Inc. $170.00 $340.00 Engineer's Estimate 2 EACH $140.00 $280.00
A0970 63502-0700 TEMPORARY TRAFFIC CONTROL, CONE
McCullough Construction Inc. $30.00 $1,500.00 Hat Creek Construction & Materials, Inc. $30.00 $1,500.00 Engineer's Estimate 50 EACH $22.00 $1,100.00
A0980 63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM
McCullough Construction Inc. $75.00 $3,750.00 Hat Creek Construction & Materials, Inc. $100.00 $5,000.00 Engineer's Estimate 50 EACH $50.00 $2,500.00
A0990 63502-1500 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE A
McCullough Construction Inc. $15.00 $60.00 Hat Creek Construction & Materials, Inc. $110.00 $440.00 Engineer's Estimate 4 EACH $60.00 $240.00
A1000 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B
McCullough Construction Inc. $160.00 $640.00 Hat Creek Construction & Materials, Inc. $110.00 $440.00 Engineer's Estimate 4 EACH $135.00 $540.00
16 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: CA FLAP CR4F009(1)
Project Name: J F Kennedy Memorial Drive
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1010 63502-1700 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE C
McCullough Construction Inc. $15.00 $120.00 Hat Creek Construction & Materials, Inc. $110.00 $880.00 Engineer's Estimate 8 EACH $50.00 $400.00
A1020 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN
McCullough Construction Inc. $5,000.00 $5,000.00 Hat Creek Construction & Materials, Inc. $5,000.00 $5,000.00 Engineer's Estimate 1 EACH $8,300.00 $8,300.00
A1030 63503-0400 TEMPORARY TRAFFIC CONTROL, CONCRETE BARRIER
McCullough Construction Inc. $25.00 $5,000.00 Hat Creek Construction & Materials, Inc. $45.00 $9,000.00 Engineer's Estimate 200 LNFT $63.00 $12,600.00
A1040 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
McCullough Construction Inc. $20.00 $8,000.00 Hat Creek Construction & Materials, Inc. $20.00 $8,000.00 Engineer's Estimate 400 SQFT $22.00 $8,800.00
A1050 63505-1000 TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS
McCullough Construction Inc. $1,200.00 $10,800.00 Hat Creek Construction & Materials, Inc. $1,400.00 $12,600.00 Engineer's Estimate 9.0 MILE $1,250.00 $11,250.00
A1060 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER
McCullough Construction Inc. $60.00 $120,000.00 Hat Creek Construction & Materials, Inc. $65.00 $130,000.00 Engineer's Estimate 2,000 HOUR $65.00 $130,000.00
A1070 63506-0600 TEMPORARY TRAFFIC CONTROL, PILOT CAR
McCullough Construction Inc. $90.00 $45,000.00 Hat Creek Construction & Materials, Inc. $110.00 $55,000.00 Engineer's Estimate 500 HOUR $85.00 $42,500.00
17 out of 17Source Selection Information - See FAR 2.101 & 3.104
Project No: CA FLAP CR4F009(1)
Project Name: J F Kennedy Memorial Drive
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1080 63601-7000 SYSTEM INSTALLATION, SPEED FEEDBACK SIGN (SPECIAL SOLAR VMS WITH RADAR)
McCullough Construction Inc. Lump Sum $5,000.00 Hat Creek Construction & Materials, Inc. Lump Sum $24,000.00 Engineer's Estimate ALL LPSM Lump Sum $12,000.00
A1090 63602-6020 SYSTEM INSTALLATION, TRAFFIC DETECTOR WIRE LOOP
McCullough Construction Inc. $4,500.00 $9,000.00 Hat Creek Construction & Materials, Inc. $7,000.00 $14,000.00 Engineer's Estimate 2 EACH $5,500.00 $11,000.00
A1100 63610-2800 CONDUIT, 4-INCH, PVC (SCHEDULE 40)
McCullough Construction Inc. $50.00 $2,500.00 Hat Creek Construction & Materials, Inc. $50.00 $2,500.00 Engineer's Estimate 50 LNFT $35.00 $1,750.00
A1110 63621-1000 UTILITY BOX, PULLBOX
McCullough Construction Inc. $500.00 $500.00 Hat Creek Construction & Materials, Inc. $500.00 $500.00 Engineer's Estimate 1 EACH $1,500.00 $1,500.00
Total Schedule - All Items
McCullough Construction Inc. $3,563,455.00 Hat Creek Construction & Materials, Inc. $3,692,398.00 Engineer's Estimate $4,094,730.00