Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE

PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

3. EFFECTIVE DATE 5. PROJECT NO. (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

2. AMENDMENT/MODIFICATION NO.

Linda Hennequant, Contracting Officer

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Remove and Install Three (3) Antenna Towers, at the Remote Transmitter Receiver (RTR) Facility, 14510 Airport Pkwy, Clearwater FL 33762.

Amendment is issued to answer vendor questions. See attached.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

Federal Aviation Administration Eastern Acquisitions Southern Region, AAQ-510 1701 Columbia Avenue College Park, GA 30337

Federal Aviation Administration Eastern Acquisitions Southern Region, AAQ-510 1701 Columbia Avenue College Park, GA 30337

4. REQUISITION/PURCHASE REQ. NO.

See Schedule

9A. AMENDMENT OF SOLICITATION

NO.

DTFAEN-16-R-00143

1 2

08/29/2016

9B. DATED (SEE ITEM 11)

08/09/2016

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, X

AMENDMENT 0002

Solicitation DTFAEN-16-R-00143

Remove and Install Antenna Towers 14510 Airport Pkwy, Clearwater FL

THIS AMENDMENT IS BEING ISSUED TO INCORPORATE THE FOLLOWING

INFORMATION INTO THE REFERENCED SOLICITATION

Offerors must acknowledge receipt of this amendment in Block 15, on the SF30, AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT.

QUESTIONS AND ANSWERS

1. QUESTION: In price breakdown it has three CLIN numbers 0001, through 0003 they all in reference to Replace Antenna Tower. But project also requires regrading and raising existing ground Elevation 1.75 feet, regrade with slope and 3” gravel followed compaction and testing. There should be another line item (CLIN 0004) with established quantity measurement that your engineer needs to provide. There is no way for us to calculate and come up with a fair estimate.

FAA ANSWER: Note 6, on sheet C002 shows an approximate amount of 1750 CY of fill dirt will be required for this site.

2. QUESTION: Do the new towers need to be painted white and orange as existing ones? Or no need to paint?

FAA ANSWER: The towers do not need to be painted.

3. QUESTION: In the existing southeast tower there is a bird’s nest. Do you know what type of bird pertains there? Is this can be an obstacle to demolish the tower?

FAA ANSWER: The bird is an osprey. The tower cannot be removed while the osprey is in the tower. The bird does not live in the nest year round, and the contractor will be able to remove the tower once the bird leaves.

4. QUESTION: Do OB Lights and GFI outlets on the towers are part of the scope of work?

FAA ANSWER: OB lights and GFI outlets are not part of the scope of work. The contractor will need to install the conduit for the OB light as shown in detail 3, on sheet S001.

5. QUESTION: Does the note #8 on page E-001 in the drawings refer to the grounding in the junction box at the building?

FAA ANSWER: Note 8, refers to junction boxes at the bottom of the tower. Since there are no junction boxes at the bottom of the tower, this note does not apply.

6. QUESTION: Are there any permits required for this project? If so, what will be these?

FAA ANSWER: No permits are required.

END OF AMENDMENT 0002