This is a Notice Inviting Bids issued by the City of Coronado for door and gate preventative maintenance and as-needed repair services at various municipal facilities. The contract, numbered 27-GS-FAC-1105, requires the successful bidder to provide scheduled preventative maintenance and emergency repair services for doors, gates, and related hardware across eleven City locations, including fire stations, police department, public services buildings, and maintenance facilities. Roll-up doors and gates will be serviced bi-annually or quarterly depending on location, with a total of 40 roll-up doors and 9 gates requiring preventative maintenance. The mandatory pre-bid conference is scheduled for September 2, 2026, at 8:30 a.m. at 101 B Avenue in Coronado, California, with attendance required for proposal eligibility. All bid proposals must be submitted electronically via PlanetBids by 4:00 p.m. on September 23, 2026. Requests for information must be submitted by 12:00 p.m. on September 9, 2026, with responses published by September 17, 2026. Contract award will be made within 60 days of bid opening to the lowest responsible bidder. The contract term is three years with two optional one-year renewal periods.
Bidders must submit a proposal guarantee equal to ten percent of the total bid amount, either as a certified check, cashier's check, or bid bond from an approved surety. The proposal shall include a base bid for annual preventative maintenance services at each location and an additive for as-needed repairs calculated on hourly labor rates during regular working hours (Monday-Friday, 7:00 a.m. to 4:00 p.m.), overtime hours, and holiday hours, plus a guaranteed material markup not to exceed 15 percent. The City makes no guarantee regarding the minimum quantity of as-needed repair work. The successful contractor must possess a California C-61/D-28 contractor license and be registered with the State Department of Industrial Relations per Labor Code Section 1725.5. The contractor must comply with prevailing wage requirements as determined by the Director of Industrial Relations and maintain comprehensive general liability insurance of $2,000,000 per occurrence and $4,000,000 aggregate, as well as automobile liability insurance of $1,000,000 per occurrence. Emergency service calls at fire and police stations must be responded to within two hours, with failure to meet response times subject to progressive corrective action up to contract termination. All work must be performed during normal business hours with prior notification to City staff, and the contractor must submit comprehensive inspection reports within three weeks of contract execution and maintenance reports within five working days of service completion.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SD #4821-4737-7394 v1r
CITY OF CORONADO
NOTICE INVITING BIDS
DOOR AND GATE PREVENTATIVE MAINTENANCE
AND AS-NEEDED REPAIR SERVICES
Contract No. 27-GS-FAC-1105
The City of Coronado invites bids for the performance of maintenance and as-needed repairs services of doors and gates for City facilities in compliance with the manufacturer’s guidelines.
Receipt of Bids: All bid proposals must be received electronically via PlanetBids prior to 4:00 p.m. on Wednesday, September 23, 2026.
Pre-Bid Conference: A mandatory pre-bid conference will be conducted at 8:30 am, September 2, 2026, at 101 B Ave, Coronado, California. The mandatory pre-bid conference will begin promptly at the stated time. All prospective bidders must be present and fully signed in prior to 8:30 am. Any firm or individual arriving after 8:30 am, or failing to sign in before the start time, will not be permitted to participate in the conference and will be deemed non-responsive and ineligible to submit a proposal. No exceptions will be made.
Any requests for information (RFI) or questions related to the project and/or specifications should be made in writing and submitted via PlanetBids by 12 pm on Wednesday, September 9, 2026. Responses will be published on PlanetBids by close of business on Wednesday, September 17, 2026.
Bid Security: Bid Security in the amount of ten percent (10%) of the Lump Sum Base Bid shall accompany the Bid. Bid Bond must be received electronically on Planetbids, and the original received at the Coronado City Clerk’s office PRIOR TO 4:00 pm on September 23, 2026. Deliver to: City Clerk’s Office;1825 Strand Way; Coronado, CA 92118.
Contractor’s License: The successful bidder will be required to possess a current State of California “C- 61/D-28” Contractor’s License at the time the Contract is awarded. Contractors and subcontractors must also be registered with the State of California Department of Industrial Relations per Labor Code Section 1771.1(a) and possess a City business certificate.
Prevailing Wage: In accordance with the California Labor Code, the Contractor must pay not less than prevailing wage rates as determined by the Director of Industrial Relations for all work done under this contract.
Project Documents: The project documents include the Standard Specifications for Public Works Construction (Greenbook), 2024 Edition; the San Diego Regional Standard Drawings for Public Works, 2018 Edition; the Coronado Annotations to the San Diego Regional Standards; and the contract documents.
Bid Documents: Digital files of the plans, specifications, instructions to bidders, and bidder’s proposal forms are available on PlanetBids. Hard copies are available at the Public Services & Engineering Department, 1825 Strand Way, Coronado, California 92118.
CITY OF CORONADO
DATE: _____________________ ________________________________
Jim Newton, City Engineer Public Services & Engineering
8/20/26
SD #4821-4737-7394 v1r 2
DOOR AND GATE PREVENTATIVE MAINTENANCE
AND AS-NEEDED REPAIR SERVICES
Contract No. 27-GS-FAC-1105
CONTENTS
INSTRUCTIONS TO BIDDERS
SPECIAL PROVISIONS
PART 1 – GENERAL PROVISIONS
SECTION 1 – GENERAL
SECTION 2 – SCOPE OF THE WORK
SECTION 3 – CONTROL OF THE WORK
SECTION 5 – LEGAL RELATIONS AND RESPONSIBILITIES
SECTION 7 – MEASUREMENT AND PAYMENT
BIDDER’S PROPOSAL
UNIT PRICE LIST
SUBCONTRACTOR LIST
CERTIFICATE REGARDING CONTRACTOR’S LICENSE
STATEMENT OF EXPERIENCE AND FINANCIAL CONDITION
NON-COLLUSION DECLARATION
ATTACHMENTS
ATTACHMENT A – Sample Agreement
SD #4821-4737-7394 v1r 3
INSTRUCTIONS TO BIDDERS
1. Examination of Site and Contract Documents. The Bidder is required to examine carefully the site of work, proposal forms, plans, specifications, and special provisions for the work contemplated. The submission of a proposal shall be considered conclusive evidence that the Bidder has investigated and is satisfied as to the conditions to be encountered, as to the character, quality and quantities of work to be performed and materials to be furnished, and as to the requirements of all the above documents.
2. Contract Documents. The Notice Inviting Bids, Instructions to Bidders, Bidder’s Proposal (Forms A-1 through A-5), Plans, Standard Specifications, Special Provisions, Standard Drawings, Agreement, and any other documents referenced in the Agreement shall constitute the contract.
Said documents are complementary and intended to yield a complete and finished project.
Anything shown or required of the Bidder, in any one or more of said documents, shall be as binding as if contained in all of said documents. The Bidder will not be allowed to take advantage of any error, discrepancy or omission in any document, but shall promptly report to the City Engineer in writing any such matter discovered. The City Engineer will then decide what corrective action is needed and his decisions shall be final.
3. Addenda. Any addenda issued during the time of bidding, forming a part of the documents, shall be covered in the proposal and shall be made a part of the contract.
4. Contractor's License. No proposal will be accepted from a Bidder who has not been licensed in accordance with the provisions of Chapter 9, Division III, of Business and Professions Code of the State of California. In addition, Bidders must comply with California Labor Code Section 1771.1(a) written as follows:
“A contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal, subject to the requirements of Section 4104 of the Public Contract Code, or engage in the performance of any contract for public work, as defined in this chapter, unless currently registered and qualified to perform public work pursuant to Section 1725.5. It is not a violation of this section for an unregistered contractor to submit a bid that is authorized by Section 7029.1 of the Business and Professions Code or by Section 10164 or 20103.5 of the Public Contract Code, provided the contractor is registered to perform public work pursuant to Section 1725.5 at the time the contract is awarded.”
5. Proposal Forms and Submittal.
a) The proposal shall be submitted on the attached Proposal Forms A-1 through A-5. All blanks on the proposal forms must be filled in.
b) If the proposal is made by an individual, it shall be signed and his full name and post office address shall be given. If made by a co-partnership, it shall be signed with the co-partnership name by one of the partners, who shall sign his/her own name and, in addition, the name and addresses of each partner shall be given. If made by a corporation, it shall
SD #4821-4737-7394 v1r 4 be signed by two officers consisting of the president/CEO, treasurer/CFO or secretary, attested by the corporate seal; the name of the state under the laws of which the corporation was incorporated shall be given; and names, titles, and addresses of all officers of the corporation shall be given. If made by an LLC, it shall be signed by the general manager or managing member, who shall sign his/her own name and, in addition, the names and addresses of each manager and member shall be given.
c) The Bidder’s Proposal (Form A-1) shall be completed and signed by an individual clearly authorized to bind the Bidder. All addenda issued shall be acknowledged on the proposal form. Additionally, Bidders are required to acknowledge all addenda electronically via PlanetBids as a condition of submission.
d) The Unit Price List Form (Form A-2) shall give the unit and total price. In the event the unit price and total amount for any items are not in agreement, the unit price shall govern and the total corrected thereto. In the event of a discrepancy between the total amount submitted in the Unit Price List Form (Form A-2) and the amount entered electronically in PlanetBids via the Line Items module, the total amount in the Unit Price List Form (Form A-2) shall govern. In accordance with Section 6707 of the California Labor Code, for construction of a pipeline, sewer, sewage disposal system, boring and jacking pits, or similar trenches or open excavations, which are five feet or deeper, the Bidder shall specify as specific bid items, adequate sheeting, shoring and bracing or equivalent method, for the protection of life or limb, which shall conform to applicable safety orders. The lowest bid shall be the lowest total of the bid prices on Item I, Base Bid for Preventative Maintenance Services, plus the additive Item II, As-needed Repairs Regular and Overtime Labor Rates.
e) The Subcontractor List (Form A-3) shall be prepared in accordance with Section 4104 of the California Public Contract Code describing the portion of work to be performed and providing the name, the location of the place of business, the California contractor license number, and public works contractor registration number issued pursuant to Section 1725.5 of the Labor Code of each subcontractor who will perform work or labor or render service to the prime contractor in or about the construction of the work or improvement, or a subcontractor licensed by the State of California who, under subcontract to the prime contractor, specially fabricates and installs a portion of the work or improvement according to detailed drawings contained in the plans and specifications, in an amount in excess of one-half of 1 percent of the prime contractor's total bid or, in the case of bids or offers for the construction of streets or highways, including bridges, in excess of one-half of 1 percent of the prime contractor's total bid or ten thousand dollars ($10,000), whichever is greater.
The prime contractor shall list only one subcontractor for each portion as is defined by the prime contractor in his or her bid.
f) The Certificate regarding Contractor’s License (Form A-4) shall be prepared in acknowledgment of Section 7028.15 of the Business and Professions Code.
g) The Statement of Experience and Financial Condition (Form A-5) shall be completed with supporting documentation and signed by an individual clearly authorized to bind the Bidder.
SD #4821-4737-7394 v1r 5
h) The complete proposal including proposal guarantee and surety insurer supporting documentation shall be submitted via PlanetBids.
i) Proposals not received electronically prior to the hour and the date set forth in the
Notice Inviting Bids shall be declared late and not accepted. The Bidder shall have sole responsibility for timely delivery.
6. Proposal Guarantee. All electronic proposals shall included a scanned copy of a certified check, cashier’s check, or bidder’s bond duly executed by an approved surety insurer, made payable to the City of Coronado, for an amount equal to at least ten (10%) percent of the amount of said proposal. Upon identification of the apparent low bidder, City staff will require the original certified check, cashier’s check, or bidder’s bond be submitted in person within a timeframe specified by the City. Failure to submit the original instrument may result in disqualification by the City. Any surety insurer must be authorized to transact surety insurance in California, and have assets that exceed its liabilities in an amount equal to, or in excess of, the amount of the bond.
If a bidder’s bond is submitted with the proposal, the bidder shall also be required to submit the following documentation from the surety insurer:
a) The original, or a certified copy, of the unrevoked appointment, power of attorney, bylaws, or other instrument entitling or authorizing the person who executed the bond to do so.
Before the award of the Contract, the Contractor may also be required to submit the following documentation regarding the surety insurer:
b) A copy of the certificate of authority of the insurer issued by the Insurance Commissioner.
A certified copy may be requested before award of the contract.
c) A certificate from the county clerk of the county in which the court or officer is located attesting that the certificate of authority of the insurer has not been surrendered, revoked, canceled, annulled, or suspended or, in the event that it has, that the renewed authority has been granted.
d) A financial statement of the assets and liabilities of the insurer at the end of the quarter calendar year prior to 30 days next preceding the date of the execution of the bond. The financial statement shall be made by an officer’s certificate as defined in Section 173 of the Corporations Code. In the case of a foreign insurer, the financial statement may, instead of an officer’s certificate, be verified by the oath of the principal officer or manager residing within the United States.
No proposal shall be considered unless such guarantee and supporting documentation is enclosed therewith guaranteeing that the bidder will enter into the proposed contract if awarded.
SD #4821-4737-7394 v1r 6
Withdrawal of Proposals. Any proposal may be withdrawn prior to the hour and date set forth in the Notice Inviting Bids, via PlanetBids. The withdrawal of a proposal shall not prejudice the right of a Bidder to file a new proposal.
7. Rejection of Proposals. Proposals may be rejected if they show any alterations of the forms, additions not called for, conditional or alternative bids uncalled for, incomplete proposals, erasures, or irregularities of any kind; however, the Coronado City Council reserves the right to reject any and all proposals and to waive irregularities.
8. Disqualification of Bidder.
a) More than one proposal from an individual, a firm or partnership, a corporation or an association under the same or different names will not be considered. Reasonable ground for believing that any bidder is interested in more than one proposal for the work contemplated will cause the rejection of all proposals in which such bidder is interested.
b) If there is a reason for believing that collusion exists among the Bidders, none of the participants in such collusion will be considered in awarding of the contract.
c) Proposals in which the prices are obviously unbalanced may be rejected.
d) If the experience or financial background of a Bidder is inadequate or past performance has been unsatisfactory, the proposal may be rejected.
9. Return of Proposal Guarantees. Within 10 days after the award of the Contract, the City Clerk will return all the proposal guarantees accompanying the proposals, which are not to be further considered in making the award. All other proposal guarantees will be held until the contract has been finally executed, after which all proposal guarantees, except those forfeited, will be returned to the respective Bidders.
10. Acceptance or Rejection of Proposals. The Coronado City Council reserves the right to accept or reject any or all proposals, or to waive any irregularities or informalities in the proposals or in the proposal process; and to make an award on the base proposal or on the basis of any combination of proposal schedules to alternates listed in the proposal which, in its opinion, serves the best interest of the City of Coronado.
11. Bid Protest. Any bid protest must be in writing and received electronically by City Clerk at cityclerk@coronado.ca.us before 5:00 p.m. no later than two working days following bid opening (the “Bid Protest Deadline”) and must comply with the following requirements:
a. General. Only a bidder who has actually submitted a Bid Proposal is eligible to submit a bid protest against another bidder. Subcontractors are not eligible to submit bid protests. A bidder may not rely on the bid protest submitted by another bidder, but must timely pursue its own protest.
SD #4821-4737-7394 v1r 7
b. Protest Contents. The bid protest must contain a complete statement of the basis for the protest and all supporting documentation. Material submitted after the Bid Protest Deadline will not be considered. The protest must refer to the specific portion or portions of the Contract Documents upon which the protest is based. The protest must include the name, address, email address, and telephone number of the person representing the protesting bidder if different from the protesting bidder.
c. Copy to Protested Bidder. A copy of the protest and all supporting documents must be concurrently transmitted by fax or by email, by or before the Bid Protest Deadline, to the protested bidder and any other bidder who has a reasonable prospect of receiving an award depending upon the outcome of the protest.
d. Response to Protest. The protested bidder may submit a written response to the protest, provided the response is received by City Clerk electronically via email at cityclerk@coronado.ca.us before 5:00 p.m., within two working days after the Bid Protest Deadline or after actual receipt of the bid protest, whichever is sooner (the “Response Deadline”). The response must include all supporting documentation.
Material submitted after the Response Deadline will not be considered. The response must include the name, address, email address, and telephone number of the person representing the protested bidder if different from the protested bidder.
13. Award of Contract. The proposals will be compared on the basis of the total price of all items. The award of the Contract, if it is awarded, will be to the lowest responsible bidder whose proposal complies with all the requirements prescribed. Such award, if made, will be within sixty
(60) days after the opening of the proposals. With its proposal, Contractor shall submit to the City, a financial statement and resume of previous work of a similar nature.
14. Execution of Contract. The Contract shall be signed by the successful bidder and returned, together with the insurance, within ten (10) days from mailing the Contract to Contractor. No contract shall be binding upon the City until same has been completely executed by Contractor and the City. The City may collect electronic signatures for Contracts and Agreements that do not require notarization.
Failure to execute a contract and file acceptable and insurance as provided herein within the time limit above may be just cause for the annulment of the award and the forfeiture of the proposal guarantee.
15. Americans with Disabilities Act. The contractor acknowledges its obligations under the Americans with Disabilities Act (ADA) in all regulations and practices pertaining thereto, including, but not limited to discrimination against qualified individuals with disabilities in employment, transportation, public accommodation, telecommunications, and in all activities, programs, and services of the contractor.
16. Minority/Women/Disabled Veteran Businesses. The City of Coronado strongly encourages the use of Minority/Women/Disabled Veteran Business Enterprises. The percentages of participation shall be documented and submitted to the City.
SD #4821-4737-7394 v1r 8
17. Labor Code Compliance.
a) In accordance with the California Labor Code, Contractor must pay not less than prevailing wage rates as determined by the Director of Industrial Relations for all work done under this Contract pursuant to the all applicable laws and regulations and as noticed in Attachment B, which obligations include, but are not limited to, the following:
i. This project is subject to compliance monitoring and enforcement by the California Department of Industrial Relations (“DIR”).
ii. Contractor and all subcontractors listed in the bid proposal must be registered with the DIR pursuant to Labor Code Section 1725.5.
iii. Contractor must furnish electronic certified payroll records (online) to the Labor Commissioner.
18. Unfair Business Practice Claims. In entering into a public works contract or a subcontract to supply goods, services, or materials pursuant to a public works contract, the contractor or subcontractor offers and agrees to assign to the awarding body all rights, title, and interest in and to all causes of action it may have under Section 4 of the Clayton Act (15 U.S.C. Section 15) or under the Cartwright Act (Chapter 2 [commencing with Section 16700] of Part 2 of Division 7 of the Business and Professions Code), arising from purchases of goods, services, or materials pursuant to the public works contract or the subcontract. This assignment shall be made and become effective at the time the awarding body tenders final payment to the contractor, without further acknowledgment by the parties.
PROJECT INFORMATION:
Introduction
The City of Coronado seeks to retain a qualified, licenses contractor to perform complete maintenance and as-needed repairs of all doors and gates in compliance with the manufacturer’s guidelines throughout the City of Coronado.
Background
The City requires the services of a qualified contractor to provide regularly schedule door and gate maintenance and as-needed repair services. Without proper maintenance, premature equipment failure and unplanned equipment replacement can lead to downtime and costly repairs.
SCOPE OF SERVICES:
The services are to be provided at various facilities throughout the City of Coronado. Preventative maintenance locations, door/gate quantities are listed below in table one (1).
Scope of Work:
SD #4821-4737-7394 v1r 9
1. Scheduled preventative maintenance service and inspection when requested or as scheduled by the City. Roll up doors and gates will be scheduled bi-annually or quarterly per the Preventative Maintenance Locations of Doors/Gates table below, all other services or repairs are to be as-needed.
2. As-needed repairs of the City’s various pedestrian automatic doors, standard hinged doors, hardware repair, overhead doors and rolling or hinged gates when requested by the City.
3. Emergency, time critical repairs of overhead doors and gates at Fire Stations or Police Station when requested by the City shall be considered a priority.
a. In the event a service call is placed and is deemed an emergency by City Staff, Contractor shall be required to respond in no more than two (2) hours. Note: Two
(2) hours is the maximum acceptable response time, less time from callout to response is preferable.
b. If there is not a response to City facility within two (2) hours after notification, the following actions will be taken, at the City’s discretion:
i. 1st Occurrence: Written Warning.
ii. 2nd Occurrence: Cure Notice.
iii. 3rd Occurrence: Termination for Default.
4. Contractor’s technicians shall have and maintain a thorough knowledge of commercial overhead door systems and automated gates.
5. Contractor shall provide all vehicles, lifts, tools and materials needed for the work.
Scheduled Preventative Maintenance Service and Inspection:
1. Scheduled preventative maintenance services and inspections shall be performed by fully trained or journeyman level personnel.
2. A report listing all items checked, conditions found, and any recommended repairs or action shall be forwarded to the General Services Manager or designee within five (5) working days of the service date.
3. If the Contractor identifies a condition requiring a minor repair or part replacement, the Contractor shall notify the General Services Manager or the City's designee in writing and request authorization to proceed. No repair or part replacement shall be performed until the Contractor receives written authorization from the City.
4. If a condition is found that requires immediate repair or is a safety hazard, Contractor shall notify within one hour and obtain authorization for repairs from the General Services Manager or designee.
5. Within three (3) weeks of executed contract, Contractor shall provide a comprehensive inspection of all equipment, listing the current condition and recommendation of repairs or replacement of equipment in writing to the General Services Manager or designee.
6. Preventative Maintenance service and inspections shall include, but not be limited to the following:
a. Sectional Doors
i. Check all cables, rollers, track, sections, glass stops, hinges, bottom seal, top and bottom fixtures, head plates, and spring brackets.
ii. Check, adjust, and/or lubricate torsion springs, rollers, center shaft couplings, drums, bearings, and all adjustable fixtures.
b. One Piece Counter Weight
SD #4821-4737-7394 v1r 10
i. Check panel condition, rollers, track, stop, cables, and counter weights.
ii. Check, adjust, and/or lubricate rollers, track, stops, and cables.
c. Roll Up Doors
i. Check all slat connectors, bottom bar and seal, guide bolts, connecting slat, springs, head brackets, and hood.
ii. Check, adjust, and/or lubricate torsion barrel assembly, bearings, guides, and curtain stops.
d. Electric Operators
i. Check track, mounts, front and rear hangers, panel covers, exposed low voltage wires, door connector brackets and belts, and remove any accumulated dust, dirt or debris.
ii. Check, adjust, and/or lubricate drive chain, carriage limit switches, limit chain, reversing edge, photo eye, motor, and frame belts.
e. Gates
i. Adjust and lubricate bearings, chains, rollers, hinges, sensors, operator motors and all moving parts.
ii. Ensure electrical connections are tight and in good operating condition.
iii. Clean tracks and operator housing.
7. Extra Work: the terms of the Contract may be used for optional services not specifically identified in the Contract including, but not limited to, modernization, installation, and any repairs not covered specifically by the Contract. The Contractor shall define the scope of any optional work in writing and a cost-not-to-exceed proposal shall be submitted to the General Services Manager.
Note on Material Mark Up: Mark up percentage of supplied material shall not be in excess of 15% for maintenance items or additional requested work.
Table 1- Preventative Maintenance Locations of Doors/Gates to be serviced:
Service Address Rollup
Doors Gates PM
Frequency
Public Services-101 B Ave. X (16) X (2) Bi Annual
Fire Station 36 -1001 6th St. X (3) Quarterly
Fire Station 37- 101 Grand Caribe Causeway
X (2) X (1) Quarterly
Police Dept.-700 Orange Ave. X (8) X (6) Quarterly
1st and Alameda Yard- X (1) Bi Annual
Golf Course Maint. Shed- 635 Glorietta BLVD
X (4) Bi Annual
Beach Maint. Shed – 506 Ocean Blvd.
X (1) Quarterly
Boathouse- 1985 Strand Way X (2) Bi Annual
SD #4821-4737-7394 v1r 11
Golf Course Cart Barn- 2000 Visalia Way
X (4) Bi Annual
Lifeguard HQ- 920 Ocean BLVD X (2) Quarterly
4th and Alameda Yard X (4) Bi Annual
SPECIAL PROVISIONS
The following revisions and additions supplement the Standard Specifications referenced in sub-section 3-7. The numbering and paragraphing follows that of the Standard Specifications, 2018 Edition.
1. On site meeting prior to the start of work being performed.
2. Contractor shall perform work during normal the City business hours, Monday through Friday from 7:00 a.m. to 4:00 p.m.
3. All work performed shall be approved by the City’s authorized representative.
4. At no time may tools, equipment, trucks, or machinery be left unattended and/or unsecured during the work event.
5. Contractor shall at all times enforce strict discipline and good order among the Contractor’s employees, including, but not limited to, appropriate public behavior and decorum, and shall not employ an unfit person or anyone not skilled in the task assigned to them as determined by the City’s authorized representative.
6. Precautions must be taken at all times to ensure public safety by using safety devices i.e.
barricades, caution tape, cones etc.
7. Contractor vehicles shall be clearly marked with the company’s name and logo.
8. Upon job completion, the work zone shall be free of debris and safe for public use.
9. Prior to processing payment for work performed, Contractor shall request a final inspection by the City’s authorized representative.
10. Invoicing and payment for work performed shall be upon completion of all items including punch list.
SD #4821-4737-7394 v1r 12
11. When a service call is deemed an emergency by City staff Contractor shall be required to have a qualified technician respond onsite within two (2) hours of notification unless overtime charges will apply. In the case overtime will be charged it will be at the City’s discretion to approve overtime charges for repairs. In such a case where City opts to avoid overtime charges, next business day service will be accepted during the first three hours of start of business hours.
12. Contractor shall notify City staff of regularly scheduled preventative maintenance service or inspections no less than three (3) business days prior to contractor’s arrival. If contractor arrives onsite without prior notification to City’s staff the City reserves the right to deny and reschedule service at no charge to City.
13. Extra Work - So that the City may monitor extra work, the Service Provider shall provide adequate advanced notice to the General Services Manager or designee prior to commencing any extra work and immediate notification when extra work ceases. Notice shall be given each time an extra work activity starts and stops. Failure to provide such notices shall waive any rights to payment to the Service Provider
14. Within three (3) weeks of executed contract contractor shall provide a comprehensive inspection of all equipment, listing the current condition and recommendations of repairs or replacement of equipment in writing to the General Services Supervisor designee at no cost to the City.
SD #4821-4737-7394 v1r 13
SPECIAL PROVISIONS
PART 1 – GENERAL PROVISIONS
SECTION 1 – GENERAL
1-2 TERMS AND DEFINITIONS
Agency The City of Coronado
Board The City Council of the City of Coronado
Engineer The representative of the City Engineer who is assigned to inspect conformance of the work in accordance with the plans and specifications.
1-7.2 RESERVED.
1-7.3 Award of Contract. The proposals will be compared on the basis of the total price of all items. The award of the Contract, if it is awarded, will be to the lowest responsible bidder whose proposal complies with all the requirements prescribed. Such award, if made, will be within sixty (60) days after the opening of the proposals. All proposals will be compared on the basis of the Engineer’s Estimate. With its proposal, Contractor shall submit to the City, a financial statement and resume of previous work of a similar nature.
1-7.4 Execution of Contract.
a) The Contract shall be signed by the successful bidder and returned, together with insurance, within ten (10) days from mailing the Contract to Contractor. No contract shall be binding upon the City until same has been completely executed by Contractor and the City. The City may collect electronic signatures for Contracts and Agreements that do not require notarization.
b) Failure to execute a contract and file insurance as provided herein within the time limit above may be just cause for the annulment of the award and the forfeiture of the proposal guarantee.
SECTION 2 – SCOPE OF THE WORK
2-2 PERMITS
2-2.1 Licenses. The Contractor shall obtain and pay costs incurred for all licenses necessitated by his operations. Contractor shall obtain a City of Coronado Business License prior to commencing any work on this project.
2-10 DISPUTED WORK
SD #4821-4737-7394 v1r 14
2-10.1 Disputes.
2-10.1.1 If a dispute should arise regarding the performance of this Contract, the following procedures shall be used to address any question of fact or interpretation not otherwise settled by agreement between the parties. Such questions, if they become identified as part of a dispute between persons operating under the provisions of the Contract, shall be reduced to writing by the complaining party.
a) A copy of such documented dispute shall be forwarded to the other party involved, along with recommended methods of resolution that would be of benefit to both parties.
b) The party receiving the letter shall reply to the letter along with a recommended method of resolution within ten (10) days of receipt of the letter.
c) If the dispute is not resolved, the aggrieved party shall send a letter outlining the dispute to the City Engineer, who will recommend a resolution in writing within ten (10) business days of receipt of such letter.
d) If the dispute remains unresolved and the parties have exhausted the procedures of this section, the parties may then seek remedies available to them at law or in equity.
2-10.1.4 Pursuant to Public Contracts Code (“PCC”) section 20104, a claim by the Contractor for a time extension; payment of money or damages arising from work done by or on behalf of the Contractor pursuant to the Contract which is not otherwise expressly provided for or the claimant is not otherwise entitled to; or an amount the payment of which is disputed by the City, shall be dealt with as follows:
a) The claim shall be in writing and include the documents necessary to substantiate the claim. Claims must be filed on or before the date of final payment. Nothing in this subdivision is intended to extend the time limit or supersede notice requirements otherwise provided by the Contract for the filing of claims.
b) Claim of less than fifty thousand dollars ($50,000):
1) For claims of less than fifty thousand dollars ($50,000), the City shall respond in writing to any written claim within forty-five (45) days of receipt of the claim, or may request, in writing, within thirty (30) days of receipt of the claim, any additional documentation supporting the claim or relating to defenses or claims the City may have against the claimant.
2) If additional information is thereafter required, it shall be requested and provided pursuant to this subdivision, upon mutual agreement of the City and the claimant.
SD #4821-4737-7394 v1r 15
3) The City’s written response to the claim, as further documented, shall be submitted to the claimant within fifteen (15) days after receipt of the further documentation or within a period of time no greater than that taken by the claimant in producing the additional information, whichever is greater.
c) Claim of fifty thousand dollars ($50,000) or more:
1) For claims of fifty thousand dollars ($50,000) or more, the City shall respond in sixty (60) days of receipt of the claim, or may request, in writing, within thirty
(30) days of receipt of the claim, any additional documentation supporting the claim or relating to defenses or claims the City may have against the claimant.
2) If additional information is thereafter required, it shall be requested and provided pursuant to this subdivision, upon mutual agreement of the local agency and the claimant.
3) The City’s written response to the claim, as further documented, shall be submitted to the claimant within thirty (30) days after receipt of the further documentation, or within a period of time no greater than that taken by the claimant in producing the additional information or requested documentation, whichever is greater.
d) If the claimant disputes the City’s written response, or the City fails to respond within the time prescribed, the claimant may so notify the City, in writing, either within fifteen (15) days of receipt of the local agency’s response or within fifteen
(15) days of the City’s failure to respond within the time prescribed, respectively, and demand an informal conference to meet and confer for settlement of the issues in dispute. Upon a demand, the City shall schedule a meet and confer conference within thirty (30) days for settlement of the dispute.
e) If following the meet and confer conference, the claim or any portion remains in dispute, the claimant may file a claim pursuant to Chapter 1 (commencing with Section 900) and Chapter 2 (commencing with Section 910) of Part 3 of Division
3.6 of Title 1 of the Government Code. For purposes of those provisions, the running of the period of time within which a claim must be filed shall be tolled from the time the claimant submits his or her written claim pursuant to Subsection
(a) until the time the claim is denied, including any period of time utilized by the meet and confer conference.
f) A civil action filed to resolve a claim subject to Section 10-4 of this Contract shall be subject to the provisions of PCC Sections 20104.4 and 20104.6.
SECTION 3 – CONTROL OF THE WORK
3-1 ASSIGNMENT.
SD #4821-4737-7394 v1r 16
3-1.1 Contractor Indebtedness. Indebtedness incurred for any cause in connection with this work must be paid by Contractor and the City is hereby relieved at all times from any indebtedness or claim other than payments under terms of the Contract and Contractor will indemnify and hold harmless the City and its officers and employees from any loss, demand, damages, claims or actions arising from or in connection with said indebtedness.
3-7 CONTRACT DOCUMENTS
3-7.1 General. Except as otherwise noted or specified, the work shall be done in accordance with the following referenced specifications and drawings, which are on file and available from the Public Services & Engineering Department, 1825 Strand Way, Coronado, California 92118:
Document Date Adopted
Standard Specifications for Public Works May 21, 2019 Construction, 2018 Edition
San Diego Regional Standard Drawings May 21, 2019 (SDRSD), 2018 Edition
San Diego Regional Standard Drawings May 21, 2019 (SDRSD), 2018 Edition, City-Annotated
Caltrans Standard Specifications - 2018
3-8 SUBMITTALS
3-8.1 General. When submittals are required by Plans or Specifications, or as directed by the City Engineer, they may be shop drawings, product data, samples or documents to ensure that the Work is in accordance with the Contract documents. Contractor shall provide the submittals within fifteen (15) calendar days from the date requested in writing by the City.
Contractor is responsible for coordinating, scheduling, sequencing and preparing submittals so that work will not be delayed.
Initial submittals requiring approval will be reviewed at no cost to the Contractor. The cost of reviewing resubmittals, for reason of failure to meet Contract requirements, shall be at the expense of Contractor.
Contractor shall furnish five (5) copies (unless otherwise specified herein) of the required submittals to the City Engineer or submit electronically as “pdf” files if authorized by the Engineer.
Contractor shall ensure no work has begun until submittals for that item of work have been returned approved.
SD #4821-4737-7394 v1r 17
3-8.1.1 Submittals Required. The following submittals shall include, but not be limited to:
a) Contractor shall provide an Annual Preventative Maintenance Schedule indicating exact dates all maintenance activity is expected to be completed at each location in conformance with Table 1. Contractor shall confirm scheduled date with City a minimum of 3 days in advance and coordinate anticipated arrival time.
3-8.3 Shop Drawings. Contractor agrees that Shop Drawing Submittals processed by the City Engineer are not Change Orders; that the purpose of Shop Drawing Submittals by the Contractor is to demonstrate to the Engineer that the Contractor understands the design concept, that Contractor demonstrates his/her/its understanding by indicating which equipment and material Contractor intends to furnish and install, and by detailing the fabrication and installation methods that he/she/it intends to use. Contractor further agrees that if deviations, discrepancies or conflicts between Shop Drawing Submittals and the contract documents in the form of design drawings and specifications are discovered either prior to or after Shop Drawing Submittals are processed by the Engineer, the design drawings and specifications shall control and shall be followed. Shop drawings shall include complete fabrication, assembly, and installation drawings for the complete assembly of the system with all components, equipment, and parts, each with an assigned number corresponding to the system manufacturer’s parts list. Shop drawings shall also show construction details for each component and piece of equipment. All samples and shop drawings are to be submitted to City within thirty (30) calendar days of the Notice to Proceed. Contractor shall submit shop drawings for the items indicated in the specifications.
3-8.3.1 Record Drawings. Accurate and legible records shall be kept on a set of contract drawings of all changes of work that occur during construction. Contractor shall record the exact location by dimension, and exact depth, by elevation, of all installed material, etc. All information necessary to maintain and/or service any concealed work shall be noted on these record drawings.
Such records shall be kept up to date with all entries checked by the City Engineer before the work is buried or covered up. Prior to field acceptance, Contractor shall deliver this information to the Engineer.
3-12 WORK SITE MAINTENANCE
3-12.3 Noise Control. Contractor shall adhere to the applicable provisions of Title 41 of the Coronado Municipal Code, Noise Abatement and Control Ordinance; and, in particular, shall observe the construction noise curfew between 7:00 p.m. and 7:00 a.m. of any weekday and at all times on Sundays and holidays (Sections 41.10.040 and 41.10.050) as described below:
41.10.040 Construction Noise Curfew.
A. It shall be unlawful for any person, between the hours of 7:00 p.m. and 7:00 a.m.
of any day or on legal holidays and Sundays to erect, construct, demolish, excavate for, alter or repair any building or structure in such a manner as to create a disturbing, excessive or offensive noise unless a noise control permit has been applied for and granted beforehand by the Noise Control Officer. In granting such a permit, the Noise Control Officer should consider whether the construction noise
SD #4821-4737-7394 v1r 18 in the vicinity of the proposed work site would be less objectionable at night than during the daytime; whether obstruction and interference with traffic, particularly on streets of major importance, would be less objectionable at night than during the daytime; whether the type of work to be performed emits noises at such a low level as to not cause significant disturbances in the vicinity of the work site; the character and nature of the neighborhood of the proposed work site; whether great economic hardship would occur; if the work is in the general public interest; and he shall prescribe such conditions, working time, types of construction equipment to be used and permissible noise levels as he deems to be required in the public interest.
B. The provisions of Subsection A of this Section shall not apply to emergency work as defined herein, provided that the Noise Control Officer shall be notified in writing of such emergency work no later than forty-eight (48) hours after work commences.
41.10.050 Construction Noise Limits.
Except as provided in Section 41.10.040(B) above, it shall be unlawful for any person, including the City of Coronado, to conduct any construction activity so as to cause, at or within the property lines of any property zoned residential, an average sound level greater than seventy-five (75) decibels during a one-hour period any time between the hours of 7:00 a.m. and 7:00 p.m. unless a variance has been applied for and granted by the Noise Control Officer.
3-12.4.2 Storage in Public Streets. Area available within the City of Coronado for storage of materials is limited. Contractor shall store all materials off-site and delivered to the job site as required for construction. Storage in public streets is not permitted. If an area within the City is allowed to be used as a storage area, the site shall be kept in a clean condition to the satisfaction of the City and shall conform with Best Management Practices to avoid run-off contamination.
3-13 COMPLETION, ACCEPTANCE, AND WARRANTY
3-13.3.1 Guarantee. All work shall be guaranteed by Contractor for a period of one (1) year from the date of acceptance of the work against defective workmanship and materials furnished by Contractor. Contractor shall promptly replace or repair, in a manner satisfactory to the City Engineer, any such defective work after notice to do so from the Engineer. Upon Contractor’s failure to make such replacement or repairs promptly, the City may perform this work and the Contractor and his/her/its surety shall be liable for the cost thereof.
SECTION 4 – CONTROL OF MATERIALS
4-2 PROTECTION
4-2.1 Storage of Materials. Area available within the City of Coronado for storage of materials is limited. Contractor shall store all materials off-site and deliver to the job site as required for construction. If an area within the City is allowed to be used as a storage area, it will
SD #4821-4737-7394 v1r 19 be specified in Section 3-12.4.2. The site shall be kept in a clean condition to the satisfaction of the City and shall conform with Best Management Practices to avoid run-off contamination.
4-2.1 Property Rights in Material. Nothing in the Contract documents shall be construed as vesting in Contractor any right of property in the materials used after they have been attached or affixed to the work or the soil. All such materials shall become the property of the City upon being so attached or affixed.
SECTION 5 – LEGAL RELATIONS AND RESPONSIBILITIES
5-3 LABOR
5-3.1.1 Laws. Pursuant to Sections 1720 et seq. and 1770 et seq. of the California Labor Code, Contractor shall pay not less than the prevailing rate of per diem wages as determined by the Director of the California Department of Industrial Relations. Copies of such prevailing rate or per diem wages are on file in the City Engineer’s office, which copies shall be made available to any interested party on request at the posted reproduction charge. Contractor shall post a copy of such wage determinations at each job site.
5-3.3 Payroll Records. Contractor shall furnish the City certified payroll records for all persons employed by the Contractor and subcontractors in connection with work on the Project.
Failure to do so will delay payments to the Contractor until such certified payrolls are received by the City. Contractor shall furnish electronic certified payroll records (online) to the Labor Commissioner in addition to submitting records to the City, as applicable.
5-4 INSURANCE
5-4.2 General Liability Insurance. Contractor shall obtain and, during the term of the Agreement, shall maintain a commercial general liability (CGL) insurance policy that shall cover liability arising from any and all for bodily injury, personal injury, and property damage in an amount of not less than two million dollars ($2,000,000) per occurrence and four million dollars ($4,000,000) aggregate and shall contain the following coverage:
1. Manufacturers’ and Contractor’s liability.
2. Broad form property damage.
3. Owner’s and Contractor’s protective liability.
4. Broad form contractual liability.
5. Products and completed operations coverage.
6. Coverage for explosion, collapse, or underground property damage (X, C, U
Hazards).
The CGL insurance policy shall be written on an ISO Occurrence form or equivalent providing coverage at least as broad as CG 00 01. If limits apply separately to this Project (CG 25 03 or 25 04), the general aggregate limit shall not apply. There shall be no endorsement or modification of the CGL limiting the scope of coverage for either insured vs. insured claims or contractual liability.
All defense costs shall be outside the limits of the policy. If the Contractor or subcontractor
SD #4821-4737-7394 v1r 20 maintains higher limits than the limits shown above, the City shall be entitled to coverage for the higher limits maintained by the Contractor and/or its subcontractor. Any available insurance proceeds in excess of the specified minimum limits of insurance and coverage shall be available to the City. Any excess or umbrella policies being used to meet the required limits of insurance will be evaluated separately and must meet the same qualifications as the Contractor’s primary policy.
Contractor shall likewise obtain and, during the term of the Agreement, shall maintain an automobile liability insurance policy for all of the Contractor’s automobiles, including owned, hired, and non-owned automobiles, written on an ISO form CA 00 01 12 90 or a later version of this form or an equivalent form providing coverage at least as broad for bodily injury, personal injury and property damage in an amount of not less than one million dollars ($1,000,000) per occurrence and two million dollars ($2,000,000) aggregate. The insurance certificate shall reflect coverage for any automobile (any auto).
The City of Coronado shall be listed as additionally insured on the required CGL and automobile general liability policies. The Additional Insured Endorsement shall be an ISO Form 20 10 11 85 or an ISO Form 20 10 10 01 and 20 37 10 01, or their equivalent, including coverage for the City with respect to liability arising out of the completed operations of the Contractor. Completed operations coverage shall be maintained in effect for the benefit of the City for a period of two (2) years following the completion of the Work specified in the Contract.
All policies shall contain a provision stating that the Contractor’s policies are primary insurance and that insurance (including self-retention) of the City or any named insured shall not be called upon to contribute to any loss, as reflected in an endorsement at least as broad as CG 20 01 04 13 which shall be submitted to the City. This provision shall apply regardless of any language of the general liability or automobile liability policy maintained by the Contractor during the term of this Contract.
The City of Coronado shall accept no endorsement or modification to the CGL limiting the scope of coverage required in this Section.
The insurance policies must provide that they remain in force for not less than thirty (30) days after a notice is given to the City of the policy’s expiration or cancellation. Contractor’s insurance will not be accepted if these requirements are not met and evidenced in the submitted documents.
Contractor shall furnish certificates of said insurance and policy endorsements to the Contract Officer prior to commencement of Work under the Contract.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .