Division 1 - DEN WQ Improvements.pdf
PDF 925 KB Posted
- Attached to
- Water Quality Infrastructure Improvements
- Solicitation number
- 202578378
- Issued by
- Denver County, Denver City, Colorado
About this file
This is a technical specification document for an Invitation for Bid (IFB) procurement by the City and County of Denver, specifically Denver International Airport (DEN), for Annual Water Quality Infrastructure Improvements. The project encompasses two distinct sites requiring water quality and detention infrastructure construction: one located at 7491 N Gun Club Road and another at 24735 E 75th Avenue. The primary objectives include constructing regional water quality and detention ponds, installing storm drainage lines, performing earthwork and grading, replacing existing water quality ponds, and implementing erosion and sediment control measures. The first site involves creating a regional water quality and detention pond for a 140-acre tributary area, which will eliminate three existing water quality ponds. The second site will consolidate water quality and detention for the WorldPort development, replacing two existing ponds with a new consolidated pond.
The project is funded through DEN's annual erosion control Capital Improvement Plan (CIP) program, driven by compliance requirements under the Denver Revised Municipal Code. The procurement is structured as a competitive bid process, with technical specifications provided in extensive detail across multiple document sections covering everything from project management and coordination to environmental controls, quality assurance, and contract closeout procedures. The technical specifications indicate a comprehensive approach to infrastructure development, with rigorous requirements for contractor qualifications, safety protocols, environmental management, and documentation. While specific budget amounts are not explicitly stated in the provided document, the project appears to be a significant municipal infrastructure investment aimed at improving stormwater management and environmental compliance at Denver International Airport.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| IFB 202578378 Final v2.pdf | ||
| Division 2 - DEN WQ Improvements IFB.pdf | ||
| Summary of Quantities IFB - Water Quality Infrastructure Improvements.xlsx | XLSX spreadsheet | |
| 20220237-WQ InfrastructureCompleteSetSealed-R2-2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Annual Water Quality Infrastructure
Improvements
DIVISION 01 GENERAL REQUIREMENTS
CITY AND COUNTY OF DENVER
DENVER INTERNATIONAL AIRPORT
IFC DOCUMENTS: 07-03-2024
DEN DESIGN CONTRACT NO. 202265738
DEN CONSTRUCTION CONTRACT NO. XXXXXXXXX
Design Engineer’s Seal is applicable to design direction, and construction requirements associated with project specific design elements.
All other requirements herein are provided by DEN.
TECHNICAL SPECIFICATIONS DENVER INTERNATIONAL AIRPORT
DIVISION 01 – GENERAL REQUIREMENTS ANNUAL WATER QUALITY INFRASTRUCTURE IMPROVEMENTS
DESIGN CONTRACT NO. 202265738
CONTRACT NO. XXXXXXXXX
ISSUED FOR Construction: X/X/XXXX Shrewsberry & Associates Revision No. X
ANNUAL WATER QUALITY INFRASTRUCTURE IMPROVEMENTS
DIVISION 01 – GENERAL REQUIREMENTS
TABLE OF CONTENTS
011100 – SUMMARY OF WORK
011400 – WORK SEQUENCE AND CONSTRAINTS
011810 – UTILITIES INTERFACE
012510 – SUBSTITUTIONS
012600 – CONTRACT MODIFICATION PROCEDURES
012910 – SCHEDULE OF VALUES
012976 – PROGRESS PAYMENT PROCEDURES
013100 – PROJECT MANAGEMENT AND COORDINATION
013119 – PROJECT MEETINGS
013210 – SCHEDULE
013223.11 – CONSTRUCTION LAYOUT AND AS-BUILT SURVEYS
013223.15 – SURVEY INFORMATION
013223.19 – QUANTITY SURVEYS
013233 – PHOTOGRAPHIC DOCUMENTATION
013300 – SUBMITTAL PROCEDURES
013325 – SHOP AND WORKING DRAWINGS, PRODUCT DATA, AND SAMPLES
013510 – CONSTRUCTION SAFETY
014100 – REGULATORY REQUIREMENTS
014210 – REFERENCED MATERIAL
014225 – REFERENCE STANDARDS
014230 – DEFINITIONS AND CONVENTIONS
014510 – CONTRACTOR QUALITY CONTROL
014525 – MATERIAL TESTING AGENCY
015050 - MOBILIZATION
015210 – TEMPORARY FACILITIES
015525 – TRAFFIC CONTROL
015719 – TEMPORARY ENVIRONMENTAL CONTROLS
015810 – TEMPORARY SIGNS
016000 – PRODUCT REQUIREMENTS
016610 – STORAGE AND PROTECTION
017419 – CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
017420 - CLEANING
017720 – CONRACT CLOSEOUT
017845 – WARRANTIES AND BONDS
017840 – CONTRACT RECORD DOCUMENTS
DESIGN CONTRACT NO. 202265738
SECTION 011100
SUMMARY OF WORK
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Special Conditions and other Division 01 Specification Sections, apply to this Section.
1.02 SUMMARY AND DESCRIPTION
A. The Work specified in this contract consists of furnishing all management, supervision, labor, materials, tools, equipment, services, testing and incidentals for the construction of the Work indicated in the contract documents including lump sum items and unit price items.
B. The Work in this Contract may affect operations at DEN. The Contractor shall bid, plan and execute the Work to minimize disruption of operations and inconvenience to the public.
C. Change Notice:
1. The Contractor will be required to submit a proposal for each Change Notice
2. The Contractor shall submit a proposal for the complete scope of the Work within the specified duration identified by the Notice. Where there is no time requirement identified by the notice documents, the Contractor shall submit a proposal within 20 days of receiving the notice or as allowed in Title 11 - Changes in the Work, Contract Price, or Contract Time of the General Contract Conditions, 2011 Edition.
3. The proposal could contain both competitive bid and estimated costs and shall adhere to the requirements of Title 11 of the General Contract Conditions.
4. The Contractor shall not proceed on any change notice work until a change order is issued.
D. Change Directives:
1. The DEN Project Manager may issue Change Directive(s) for a Scope of Work. The Contractor shall keep all Time and Material record for any Change Directive(s) issued until a final settlement for the task is settled and finalized in a Change Order.
2. The Contractor shall keep records and approvals for all Time and Material impacts of a Change Directive until a final settlement is reached and fully executed by the DEN Project Manager.
3. The Contractor may invoice for a Change Directive in accordance with Title 11 of the General Contract Conditions, 2011 Edition.
E. Guaranteed Maximum Price (GMP): For Contracts assigned as GMP the Contractor shall follow the Special Conditions issued for the Contract.
F. This Project will be administered using the current Project Management Information System (PMIS). The application will be supplied by DEN at no cost to the Contractor. DEN will provide PMIS training for up to two (2) of the contractor’s personnel.
DESIGN CONTRACT NO. 202265738
G. DEN utilizes several programs as part of the Asset Management System. Keeping accurate as-built record and operation and maintenance data are essential in the integrity and the validity of the airport operation. The Contractor is required to make every effort to keep the airport data informed, updated and accurate in the format required by DEN Project Manager:
1. The Contractor shall provide and implement BIM Project Execution Plan based on the DEN BIM Project Execution Plan. The Contractor shall employ or contract a consultant to provide all the requirements to produce the Project model in the latest edition of the currently approved DEN format.
2. The Contractor shall comply with all the requirements of DEN BIM Project Execution Plan and provide the data to DEN to produce the complete record of the BIM model of the Project.
H. Inspection Requirements:
1. Special Inspection and Testing required by the building official or the Engineer of Record in the Contract Documents or in the Statement of Special Inspections will be performed by DEN contracted Agencies.
2. Contractor shall subcontract Qualified Material Testing Agency(s) to perform all necessary Quality Control, processing control and any additional Testing required by the Contract Documents.
3. DEN Quality Assurance Manager may audit all material tests performed by the Contractor Quality Control at any time. Testing and Inspections for structural elements (reinforced concrete, steel, masonry caissons, fire protection, precast and post tension concrete) not identified as special inspection will be performed by the Contractor Quality Control Program and Contractor Material Testing Agency and audited and confirmed by DEN Quality Assurance Manager. DEN will perform 100% visual inspection on all weldments. DEN will perform Quality Assurance testing at a frequency of approximately 10% of the Quality Control test and inspection frequencies. The testing frequencies by DEN may escalate to higher percentages and the Contractor will be responsible for all costs associated with failing tests of the same pay item elements. The Contractor may not hire the DEN contracted or testing agency in any capacity on this Project.
I. DEN Quality Assurance will perform all quality assurance pull and adhesion tests on all airfield joint sealants. Contractor shall perform all quality control tests for the same items.
J. DEN Quality Assurance is required to submit a letter indicating that all Work performed on the project complies with all applicable codes. The Contractor shall make sure that all required test frequencies and all deficiencies has been corrected to comply with all applicable codes and standards and the requirements of the Contract Documents.
1.03 WORK BY OTHERS AND FUTURE WORK
A. Refer to Title 7 – Cooperation, Coordination and Rate of Progress of the General Contract Conditions, 2011 Edition
1.04 SITE CONDITIONS
A. Refer to Title 14 – Site Conditions of the General Contract Conditions, 2011 Edition
PART 2 - PRODUCTS (NOT USED)
DESIGN CONTRACT NO. 202265738
PART 3 - EXECUTION
3.01 CONTRACTOR'S DUTIES
A. Refer to Title 3 – Contractor Performance and Services of the General Contract Conditions, 2011 Edition
B. Execute the Work as specified and in a timely manner. Submit a schedule of Work that will be performed at times other than during the eight-hour working day of Monday through Friday, daylight hours. Submit this schedule five (5) working days prior to the beginning of Work to the DEN Project Manager for review and acceptance. Approval to work at night may be obtained after Contractor presents a written program outlining special precautions to be taken to control the extraordinary hazards presented by night work. That program shall include, but not be limited to, supplementary lighting of work areas, availability of medical facilities, security precautions, and noise limitations.
3.02 COORDINATION
A. Coordinate execution of the Work with those public utilities, governmental bodies, private utilities and other contractors performing work on and adjacent to the worksites. Eliminate or minimize delays in the Work and conflicts with those utilities, bodies, and contractors.
Schedule governmental, private utility and public utility work that relies upon survey points, lines and grades established by the Contractor to occur immediately after those points, lines and grades have been established. Confirm coordination measures for each individual case with the DEN Project Manager in writing.
B. In the coordination effort of work by others, the Contractor shall obtain and refer to equipment locations and other layouts, as available, to avoid interface problems.
C. The City reserves the right to permit access to the site of the Work for the performance of work by other contractors and persons at such times that the City deems proper. The exercise of such reserved right shall in no way or to any extent relieve the Contractor from liability for loss and damage to the Work due to or resulting from its operations or from responsibility for complete execution of the Contract. The Contractor shall cooperate with other contractors and persons in all matters requiring common effort.
3.03 CONTRACTOR USE OF WORK SITE
A. Confine work site operations to areas permitted by law, ordinances, permits, and the Contract.
B. Consider the safety of the Work and that of the people and property on and adjacent to the work site when determining amount, location, movement, and use of materials and equipment on work site.
C. Do not load work site with equipment and products that would interfere with the Work. Only equipment, tools, or materials required for this Work may be stored at the work site.
D. Protect products, equipment, and materials stored on work site.
E. Relocate stored products, equipment, and materials that interfere with operations of City, government bodies, public, and private utilities, and other contractors.
PART 4 - MEASUREMENT
DESIGN CONTRACT NO. 202265738
4.01 METHOD OF MEASUREMENT
A. No separate measurement shall be made for work under this Section.
PART 5 - PAYMENT
5.01 METHOD OF PAYMENT
A. No separate payment will be made for work under this section. The cost of the work described in this section shall be included in the applicable unit price item, work order or lump sum bid item.
END OF SECTION 011100
DESIGN CONTRACT NO. 202265738
SECTION 011400
WORK SEQUENCE AND CONSTRAINTS
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Special Conditions and other Division 01 Specification Sections, apply to this Section.
1.02 OTHER WORK
A. Other concurrent construction contracts with which the Contractor must interface are described elsewhere in the Contract Documents. Refer to Section 013210 "Schedule" and the Special Conditions for specific work constraints and milestones.
1.03 WORK SEQUENCE
A. The work sequence shall comply with Phasing, Sequencing, and Milestones as indicated in the Contract Documents and in accordance with the approved Construction Schedule developed by the Contractor. The schedule shall comply with requirements indicated in the Special Conditions and Section 011400 "Work Sequence and Constraints". The Construction Schedule is described in Section 013210 "Schedule".
1.04 WORK CONSTRAINTS
A. Site Constraints:
1. Access to the Project shall be generally as indicated in the Contract Documents.
Access shall be organized and planned by the Contractor to ensure no disruption of airline or DEN operations.
2. Access to work sites will be strictly monitored and must comply with DEN Airport Operations and FAA Regulations. The Contractor shall provide monitoring and escorts as required by DEN Operations in the area of the Work.
3. The Contractor's staging area will be as indicated in the Construction Documents.
4. Contractor employee parking will not be allowed within the existing revenue control system. Parking facilities will be as indicated in the Construction Documents.
5. Material for work in the Terminal may be brought in through the Terminal Loading Dock accessed via Gate 1. Employee and material access to the Concourses will be via Gate 5.
6. The Contractor shall use the haul routes specified in the Construction Documents.
7. If required, the Contractor shall provide a bus and driver to transport the Contractor’s employees between the designated employee parking area and the work sites. No separate payment will be made for this bus and driver. The cost shall be included in the bid item “Mobilization”. The bus driver shall be provided at all times when Contractor employees are working on the Project.
B. System Interruptions:
DESIGN CONTRACT NO. 202265738
1. DEN is a 24/7/365 facility. Construction activity that requires any system shutdown must be coordinated with the project manager and DEN AIM MCC.
2. The Shutdown cannot proceed unless all approver groups have approved the request.
If any of the groups rejects the request, you may not proceed with the Shutdown. If a Shutdown is determined to be an emergency due to pending health issues or the risk of additional damage, this process may be bypassed. If the Shutdown is an emergency, proceed with the shutdown without the approvals. Approvals must be obtained as follows
a. Airfield Shutdowns must be submitted at least 72 hours prior to the shutdown start date.
b. All other Shutdowns must be submitted at least five (5) business days prior to the shutdown start date.
c. All Shutdown Requests must be submitted using the Shutdown Request form, which can be accessed via the Home page of the DEN intranet.
C. Airfield Operations at Denver International Airport:
1. Full airport and aircraft operations are underway adjacent to this Project. Contractors are required to obtain a Contractor Participant Manual from the Security Manager and must follow the guidelines in the manual. Copies of the Contractor section of the manual are available for review at the Denver International Airport Access Services Office.
a. If any Work contains requirements for Work activities or access through or in the restricted area, reference Section 011420 "Security Requirements & Sensitive Security Information (SSI)" for requirements.
b. If not in a restricted area, the Contractor personnel still must be badged;
reference Section 011420 "Security Requirements & Sensitive Security Information (SSI).
D. Conduct of persons using the Denver Municipal Airport system:
1. Contractor activities shall comply with Airport Operations and Regulation 130 "TRAFFIC" and Regulation 20 "CONDUCT OF PERSONS USING THE DENVER MUNICIPAL AIRPORT SYSTEM" shall be followed at all times. These regulations are available from Airport Operations at Denver International Airport.
E. Operational safety on airports during construction:
1. All Work shall be accomplished in accordance with FAA Advisory Circular AC150/5370-2C, "Operational Safety on Airports during Construction", FAR Part 139 and FAR Part 107 except as herein modified.
F. Welding Equipment, Procedures and Constraints:
1. Natural gas-powered portable welders or inverter single- and three-phase electric portable welders are the only acceptable welding equipment to be used inside the building basement or tunnel areas. Acceptability of equipment other than the equipment noted above shall be at the sole discretion of the DEN Project Manager.
2. Welding activities inside buildings require submittal of a System Interruption Request (See paragraph “System Interruptions” above). Prior to welding in any area, the Contractor shall locate smoke detectors and shall request interruption of the fire alarm system. Subsequent to the interruption of the fire alarm system and prior to welding activities, the Contractor shall cover and protect smoke detectors until work is complete. Prior to expiration of each interruption of the system, the Contractor shall uncover the smoke detectors.
DESIGN CONTRACT NO. 202265738
3. Electrical Service: The Contractor shall be responsible for verifying with the. DEN Project Manager or representatives locations acceptable for accessing electrical power for welders and other electrical equipment feeders. The Contractor shall be responsible for all work and equipment required to install temporary or permanent electrical modifications for construction power and lighting.
a. Temporary Hook-up: In addition to the requirements of paragraph “Temporary Power and Lighting for Construction” below, comply with the following:
1) Provide wiring sized to accommodate full load of welding equipment, accounting for voltage drop.
2) Provide appropriate NEMA twist-lock or ANSI receptacle for welder hook-up.
3) 480V, 3 phase, 3 pole, 4-wire twist lock ground line.
4) NEMA L16-20 or ANSI C73.87.
b. The Contractor may not begin operation of the equipment prior to request for inspection by DEN representatives and acceptance of the installation.
c. Permanent installation of electrical branch circuiting for welding equipment shall be made in accordance with all Division 26 Specification Sections
4. Welding Practices: All standard safe welding practices must be followed, including but not limited to the following:
a. Flash protection for surrounding areas.
b. Contractor fire extinguisher in area.
c. One person in each welding area solely designated as fire watch for each welder.
d. Protect all equipment, cable trays and contents, etc., in area.
e. Use fire blankets and other appropriate materials to confine sparks and molten metal from the welding, cutting, and/or grinding activities.
f. All welders shall have been qualified through welding tests in accordance with applicable welding code, such as but not limited to AWS, ASME, API, within one year prior to welding taking place. Evidence of qualification shall be through Welding Performance Qualification Records (WPQR).
g. All welder qualifications test shall be or shall have been administered and witnessed by an Independent Testing Agency (ITA), AWS Certified Welding Inspector (CWI).
h. If recertification of welders is required, delay costs and retesting costs shall be borne by the Contractor.
5. Grounding: Review with DEN representative’s area of work prior to beginning work to ensure ground procedures do not induce undesirable charges in steel building system or other systems. This review should take place subsequent to the pre-work meeting.
Do not ground to adjacent building systems, baggage system, hangers, or devices that support mechanical or electrical equipment.
G. Temporary Power and Lighting for Construction:
1. The Contractor shall be responsible for all work and equipment required to install temporary or permanent electrical modifications for construction power and lighting.
2. The Contractor shall be responsible for all work and equipment required to install temporary or permanent electrical modifications for construction power and lighting.
a. Comply with all requirements of NEC Article 590.
b. Flexible cords used for temporary power shall be listed in accordance with NEC Article 400, and rated for ‘extra-hard’ usage.
c. Provide an equipment grounding conductor with all temporary power circuits.
d. All temporary power distribution devices and equipment shall be listed and rated for the application.
e. Provide ground fault protection for personnel.
DESIGN CONTRACT NO. 202265738
f. Temporary lighting fixtures shall be protected from physical damage.
H. Cleaning Equipment and Spoils:
1. Discharge of water, liquids, or chemicals into a building sanitary sewer system or storm drainage systems is prohibited. The Contractor shall comply with all Federal, State, and Local requirements for disposal of chemicals and equipment wash water.
The Contractor shall maintain and service all equipment in work areas and collect all wash water, spoils and water from excavations in containers for discharge or removal off site.
I. Vehicle Permitting for Tunnel and Basement Use:
1. Electric carts require permitting. The Contractor shall provide at least one (1) electric cart for Contractor use during the work in the tunnel and basements of the buildings.
Only electric or CNG powered trucks are allowed in the tunnel and basements of the buildings. Only electric or CNG trucks may be used and shall not be parked overnight or for long terms within the tunnel or basements. All vehicles require permitting.
Permits may be acquired at the DEN Airport Security Office.
J. Radio and Cell Phone Use:
1. The Contractor shall have wireless communications in place prior to initiation of work in the tunnel or basements by use of cell phone and/or radio. Radio and cell phone coverage in the tunnels and basements varies in signal strength throughout the campus. An RF Application must be submitted for the Radio equipment intended for use at least 14 days prior to intended use. Include the following radio information:
a. Make
b. Model
c. Frequency
d. Effective Radiated Power (ERP)
2. Contractors must receive an approval letter from the RF Systems Manager prior to use of the radio equipment on the DEN campus.
K. Keys:
1. The Contractor shall be required to contact DEN Maintenance Control to procure keys for access to all rooms having locks in order to gain access. Keys may be checked out at the beginning of each work shift by the Contractor and shall be returned to DEN Maintenance Control at the end of each work shift
1.05 COORDINATION
A. The Contractor will designate a contact person for coordination with the DEN Project Manager and airline tenants. The contact person shall have the authority to make decisions for the Contractor firm and shall have binding signatory power for changes in work. The contact person shall be on site at all times during work activity.
B. No additional costs shall be considered for coordination activities throughout this project.
The Contractor shall include in the Contractor's bid costs for coordination of all activities.
DESIGN CONTRACT NO. 202265738
3.01 DUST/PROTECTION BARRIERS
A. HVAC system containment. The Contractor shall submit to DEN Maintenance HVAC and Fire Alarm shutdown requests prior to modifications to the area of work for dust containment. The HVAC system shall be interrupted, re-routed, or blocked off to prevent dust from entering return or supply ducts.
B. Debris and Protection Barriers:. The Contractor shall construct code-approved and DEN-approved dust and debris barriers on both sides of walls and doors that are to be modified.
Barriers shall be constructed to allow emergency ingress and egress to and from equipment and spaces. Barriers shall be constructed to allow continual uninterrupted function of building equipment and spaces.
1. Return all removed door hardware to DEN. Label each hardware set correlating the door number of the original hardware set. Coordinate with the DEN Project Manager for storage and return of hardware.
3.02 EQUIPMENT
A. Equipment: CNG-powered equipment is allowed within the buildings. No other fossil fuel equipment may be used within the buildings unless the equipment is directly vented to the building exterior.
B. Electric: Electric powered equipment is acceptable in the Work area.
PART 4 - MEASUREMENT
4.01 METHOD OF MEASUREMENT
A. No separate measurement shall be made for work under this Section.
PART 5 - PAYMENT
5.01 METHOD OF PAYMENT
A. No separate payment will be made for work under this section. The cost of the work described in this section shall be included in the applicable unit price item, work order or
END OF SECTION 011400
DESIGN CONTRACT NO. 202265738
SECTION 011810
UTILITIES INTERFACE
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Special Conditions and other Division 01 Specification Sections, apply to this Section.
1.02 SUMMARY
A. Various utilities may be located within the limits of work in the Project area. The owners of these utilities may require that the Contractor work around their existing facilities until alterations, relocation, or abandonment have been completed. The Contractor shall verify and satisfy itself that there are no other existing utilities that may not be shown.
B. The owners of utilities within the project area may include, but are not limited to:
1. Century Link Telephone
2. DEN Telephone
3. Xcel Energy Natural Gas
4. Xcel Energy Elec. Services
5. DEN Storm Water
6. DEN Sanitary Sewer
7. DEN Deicing Waste
8. Denver Water Department
9. DEN Deicing Supply operated by Inland Technologies
10. Fuel System (ASI)
11. Premise Wiring System- DEN Business Technologies
12. FAA Duct Bank
13. Oil/Gas Wells
14. DEN Electrical Department
15. Fire Alarm System
16. Paging System
C. The location and establishment of each construction vehicle crossing shall be at sites mutually agreed upon in writing by the Contractor and the owner of the utility.
D. At the locations where the Contractor needs to establish a construction vehicle crossing over any of the operating pipelines, the furnishing and placing of a crossing shall be by the Contractor. The crossing shall allow the normal operation of the pipeline at all times unless specifically approved by DEN or the owner of the pipeline. Each crossing shall be adequately marked and signed for safe passage of vehicles over the crossing. Construction
DESIGN CONTRACT NO. 202265738
vehicles shall not be allowed to cross over operating pipelines at any place other than an established crossing.
E. These utility locations are based upon information provided by the utility companies or previous construction contractors that were the basis for determining utility coordinates. The Contractor is responsible for confirming the accuracy of the provided coordinates with the utility owner.
F. The Contractor shall control the Contractor's operations in order to avoid creating any obstacles for the utility owner’s access for maintaining or operating their equipment.
1.03 REFERENCE DOCUMENTS
A. Section 312323.33 "Flowable Backfill (Controlled Low-Strength Material)"
1.04 REGULATORY REQUIREMENTS
A. The Contractor shall obtain and pay for all utility company permits, fees, and licenses necessary for the execution of this work. The Contractor shall give all notices and shall comply with all laws, ordinances, rules, and regulations of all authorities having jurisdiction.
1.05 QUALITY CONTROL
A. When the Contractor performs any operations that will affect a utility owner, the Contractor shall give timely notice to the utility owner and the DEN Project Manager so that the Contractor's operations may be observed by the utility owner or their representative.
1.06 WORK INCLUDED
A. The Work of this Section includes furnishing all materials, equipment, and labor necessary to provide utility crossings as required and as specified herein and subject to approval by the associated utility owner.
B. North American Resources has a line passing through airport property. The Contractor shall contact the utility prior to beginning earthwork operations to ascertain any special requirements or conditions required to maintain and protect this service during construction activities.
C. FAA Underground Duct lines: The FAA has duct lines passing under the site. The Contractor shall contact the FAA prior to beginning earthwork operations to ascertain any special requirements or conditions required to maintain this service during construction activities.
PART 2 - PRODUCTS
2.01 MATERIALS
A. Suitable cover material shall be in accordance with Colorado Department of Transportation Standard Specifications. Wet, soft, or frozen material, asphalt chunks, or other deleterious substances shall not be used for cover.
B. Aggregate for road base material shall consist of clean, sound and durable particles of crushed stone, crushed gravel or crushed slag, shall be free from coatings of clay, silt and organic matter, and shall contain no clay balls. Material shall conform to the State of
DESIGN CONTRACT NO. 202265738
Colorado Standard Specifications for Road and Bridge Construction Class 6 aggregate base unless otherwise specified.
C. The materials for the load distribution system on top of the cover shall conform to the specification of the American Institute of Steel Construction, the American Institute of Timber Construction, or the American Concrete Institute, as applicable, depending upon the system agreed upon between the Contractor and utility owner.
D. Materials for the sleeving of the pipelines shall be purchased by the utility owner at the Contractor’s expense.
E. Comply with utility backfill requirements for the use of flowable backfill in Section 312323.33 "Flowable Backfill (Controlled Low-Strength Material)" and Division 26 and Division 33 requirements.
PART 3 - EXECUTION
3.01 NOTIFICATION OF UTILITIES FOR LOCATING AND POTHOLING
A. The Contractor shall verify the location of all utilities prior to any operations including physically uncovering the utility to verify location as required by the utility owner.
B. The Contractor shall notify the Utility Notification Center of Colorado at (303) 534-6700 or 811, as a minimum for location of utilities.
PART 4 - MEASUREMENT
4.01 METHOD OF MEASUREMENT
A. No separate measurement shall be made for work under this Section.
PART 5 - PAYMENT
5.01 METHOD OF PAYMENT
A. No separate payment will be made for work under this section. The cost of the work described in this section shall be included in the applicable unit price item, work order or
END OF SECTION 011810
DESIGN CONTRACT NO. 202265738
SECTION 012510
SUBSTITUTIONS
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Special Conditions and other Division 01 Specification Sections, apply to this Section.
1.02 SUMMARY
A. All material and equipment substitutions must comply with Title 4, Article 406: Substitution of Materials and Equipment in the General Contract Conditions, 2011 Edition.
B. The Work specified in this Section consists of submitting form CM-09, Request for Substitution for the approval of a different material, equipment, or process than is described in the Contract Documents.
C. If the substitution changes to the Scope of Work, Maximum Contract Cost, cost of the Work (if less than the Maximum Contract Cost), or Contract time, a Change Order is required.
D. As-built drawings and specifications must include all substitutions even if a Change Order is not issued.
1.03 REFERENCE DOCUMENTS
A. Form CM-09, Request for Substitution
B. Section 013300 "Submittal Procedures"
C. Section 013325 "Shop and Working Drawings, Product Data and Samples"
1.04 QUALITY CONTROL
A. The substitution shall provide as a minimum, the same performance as specified.
1.05 SUBMITTALS
A. Refer to Section 013300 "Submittal Procedures" and Section 013325 "Shop and Working Drawings, Product Data and Samples" for submittal procedures.
B. A completed Form CM-09 shall be submitted at least 60 days prior to when an order needs to be placed or a method needs to be changed.
C. The submittal shall contain all the data required to be submitted for acceptance of the originally specified item or process, including, as appropriate:
1. Detailed product data sheets for the specified items and the substitution.
2. Samples and shop drawings of the substitution.
DESIGN CONTRACT NO. 202265738
3.01 SUBSTITUTION PROCESS
A. Provide the information as required on Form CM-09.
3.02 SUBSTITUTION REQUEST
A. The formal Request for Substitution will be evaluated by the DEN Project Manager and the Designer of Record based on the following criteria:
1. Compatibility with the rest of the project.
2. Reliability, ease of use and maintenance.
3. Both initial and long term cost.
4. Schedule impact.
5. The willingness of the Contractor to share equally in any cost savings.
6. The ability of the item or process to meet all applicable governing regulations, rules, and laws along with funding agency requirements.
7. The cost of evaluating the substitution.
B. Based upon the above evaluation, the Senior Director of AIM Development will make a final determination of what is in the best interest of the City and either approve, disapprove or approve as noted the requested substitution.
3.03 CONDITIONS
A. As a condition for submitting a Request for Substitution, the Contractor waives all rights to claim for extra costs or changes in the costs, schedule, Contract time or Scope of Work, other than those outlined in the request and approved by the Senior Director of AIM Development. The Contractor, by submitting a Request for Substitution, also accepts all liability for cost and scheduling impact on other contractors or the City due to the substitution.
B. Included with the Request for Substitution shall be the following statement:
1. "The substitution being submitted is equal to or superior in all respects to the Contract-required item or process. All differences between the substitution and the Contract-required item or process are described in this request along with all required information, cost, and scheduling data."
C. The statement shall be signed and dated by the Contractor's Superintendent.
D. Replacement of Substitution Found to be Not Equal:. The Contractor shall be responsible for all aspects and conditions of the substitution that are not clearly identified in the substitution submittal, and shall be liable for the appearance, function, performance or other aspects of the substitution that are found not to be equal to the originally specified item.
1. The Contractor shall incur all labor and costs associated with replacement of any substitution that is found to be not equal to the originally specified item or process and rejected by the DEN Project Manager.
2. The replacement of any rejected substitution shall either be with the originally
DESIGN CONTRACT NO. 202265738
specified item or process, or a substitution approved by the DEN Project Manager.
3.04
PART 4 - MEASUREMENT
4.01 METHOD OF MEASUREMENT
A. No separate measurement shall be made for work under this Section.
PART 5 - PAYMENT
5.01 METHOD OF PAYMENT
A. No separate payment will be made for work under this section. The cost of the work described in this section shall be included in the applicable unit price item, work order or
END OF SECTION 012510
DESIGN CONTRACT NO. 202265738
SECTION 012600
CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Special Conditions other Division 01 Specification Sections, and Related Requirements apply to this Section.
3.01 CHANGE MANAGEMENT PROCEDURES
A. General Process Requirements
1. Refer to Project Management for Software Requirements Section 013100 Project Management and Coordination.
2. Refer to the City and County of Denver Standard Specifications for Construction General Contract Conditions Title 11 requirements
3. Process
a. Change Mechanism Types
1) Change Directive
a) DEN directed change/scope changes that are necessary for safety or operations – scope addition is not optional. DEN provides a budget via CD, and the contractor responds via CDR with costs (either actual or negotiated). Once the CDR is approved, a change order may be issued for the difference between the CD and the CDR.
2) Change Notice
a) When to use: DEN directed changes/scope for which the contractor can propose costs to do the work. A CN does not mean the work will take place; project impacts, including cost and schedule, must be negotiated and agreed upon before the work takes place. Once the change notice is negotiated, a change order may be issued.
3) Contractor Change Request
a) Adverse or changed conditions encountered by the contractor that were not the result of DEN direction; RFI responses that differ from spec that may result in additional cost or schedule. Once the CCR is approved, a change order may be created.
b. Non-Standard Contract Changes
1) Suspension
a) Suspensions should be recorded through a change notice. The contractor may respond with any associated costs.
2) Termination
a) Terminations should be recorded through a change notice. The contractor may respond with any associated costs.
DESIGN CONTRACT NO. 202265738
3) Minor Contract Language Change
a) Changes to contract language should be recorded through a change notice. In addition to the normal Unifier approval process, Airport Legal Services (ALS) should also review and approve of changes in the contract. Common situations where this may occur:
(1) Project Milestone Changes
(2) Submittal Requirements
(3) Insurance Requirements
(4) Other
(5) Other
4) Specification Change
a) Changes to spec should be recorded through an RFI if possible. If not, then a CN may be issued for spec changes. In addition to the normal Unifier approval process, the spec owner/SME should review and approve of the change.
5) Major Contract Language Change
a) Major Contract Language Changes require the involvement of Airport
Legal Services (ALS) and may require additional approval, up to and including City Council. Situations where this may be necessary would include
(1) Removal of special conditions, exhibits, or attachments to the contract
(2) Increase in contract capacity over a designated value
(3) Any other contract change that has not been covered by this section.
c. Change orders
1) Change Directives, Change Notices and Contractor Change Requests will be executed and incorporated into a contract via a Change order only.
B. Submission Requirements
1. Refer to Section 013100 Project Management and Coordination.
3.02 TIMELINE
A. The Contract General Conditions (Standard Specifications for Construction General Contract Conditions) Title 11 provides timelines and deadlines for approval. The contractor shall refer to this section of the contract for specific requirements, in addition to any special conditions within the contract.
B. The deadlines specified in Title 11 should be applied to the initial submission package for a change. Any requests for revision, including negotiations, will be subject to the following deadlines.
1. If a contractor is asked to revise a final proposal, the revision will be completed and submitted through the designated system within seven (7) calendar days.
2. DEN will have fourteen (14) calendar days to review any revised proposal and provide a recommendation back to the contractor. This includes any reviews of the proposal on behalf of DEN, including third parties, subject matter experts, and Project Manager reviews.
DESIGN CONTRACT NO. 202265738
A. No separate measurement shall be made for work under this Section.
PART 5 - PAYMENT
5.01 METHOD OF PAYMENT
A. No separate payment will be made for work under this section. The cost of the work described in this section shall be included in the applicable unit price item, work order or
END OF SECTION 012600
DESIGN CONTRACT NO. 202265738
SECTION 012910
SCHEDULE OF VALUES
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Special Conditions other Division 01 Specification Sections, and Related Requirements apply to this Section.
1.02 RELATED REQUIREMENTS
A. The Work specified in this Section consists of preparing and submitting the Schedule of Values (“Schedule”) as referenced in the General Conditions. Use the Project Specifications Table of Contents or Schedule of Prices and Quantities (Bid Tabs), if applicable, as a guide to establish line items for the Schedule of Values. Provide at least one line item for each Specification Section. The Work also includes the preparing and submitting of updated copies of the Schedule if the Schedule is affected by change orders.
B. A Schedule of Stored Material is a detailed cost breakdown for permanent materials that will be temporarily stored prior to their being installed and for which the Contractor seeks partial payments. The Schedule of Stored Material will be incorporated as a part of the Schedule of Values.
C. Within 14 calendar days of issuance of the Notice to Proceed (NTP), the Contractor shall submit the Schedule of Values including the Schedule of Stored Material if applicable. The Schedule of Values and Schedule of Stored Material used to prepare the work/cost breakdown for the Schedule will be used for the Contractor's billings.
D. Any Contract allowances shall be included in the Schedule. Expenditure of allowances shall be done using the Allowance Authorization form. Use of this form does not increase or decrease the Contract value.
1.03 RELATED DOCUMENTS
A. Title 9 – Compensation of the General Contract Conditions, 2011 Edition
B. Section 013300 "Submittal Procedures"
C. Section 013325 “Shop and Working Drawings, Product Data and Samples".
D. Form CM-89, Schedule of Values
E. Form CM-91, Schedule of Values for Unit Price Contracts
1.04 SUBMITTALS
A. The Schedule of Values shall be formally approved by the DEN Project Manager.
B. The Schedule shall identify each item of work. Work items in the Schedule shall represent all Work and shall be referenced with the Technical Specifications section numbers, DESIGN CONTRACT NO. 202265738 specification subparagraph, specification section title and the bid item number used for the Schedule of Prices and Quantities when applicable.
C. Upon request by the City, the Contractor shall support values given with the data that will substantiate the correctness of the values.
D. The Schedule will be utilized only as a basis for review of the Contractor's application for progress payment.
1.05 REVIEW AND RESUBMITTAL
A. If review by the DEN Project Manager indicates that changes to the Schedule are required, the Contractor shall revise and resubmit the Schedule.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
3.01 PREPARING SCHEDULE OF VALUES
A. Provide a breakdown of the Contract Price in enough detail to facilitate continued evaluation of Applications for Payment and progress reports.
B. Breakdown of the items used in the Schedule shall include the following item costs. Ensure each item is complete:
1. Delivered cost of product with applicable taxes paid.
2. Total installation cost with overhead and profit.
3. Breakdown costs of each lump sum item with a list of products and major operations for which the Contractor seeks to receive progress payments to recover the Contractor's costs for that bid Item.
4. Each unit price item as listed in the bid Schedule of Prices and Quantities shall list products and major operations for which the Contractor seeks to receive progress payments for that bid item.
3.02 PREPARING SCHEDULE OF STORED MATERIAL
A. The Contractor shall submit with the Schedule an indication of whether products will be stored on or off the work site. The Schedule of Stored Material shall show all quantities and types of products that will be stored.
B. Material allowances consist of only the net cost of the product, the cost of delivery and unloading at the storage site, the cost of applicable sales taxes, and all discounts.
C. In no case will the cost paid for a permanent material be greater than 90 percent of the Contract price for the Work in which they are included.
3.03 PAYMENT FOR STORED MATERIALS
A. Only materials that are described in the specifications and on the drawings will be considered permanent materials. Permanent materials are materials that will be left in the Work after the Contract is completed.
DESIGN CONTRACT NO. 202265738
B. Nothing in these specifications shall be interpreted as requiring the City to pay for stored materials. The DEN Project Manager shall decide on a case-by-case basis whether stored materials shall be paid for. No payment will be made for stored materials that have not been submitted and accepted.
C. The Contractor must, at all times, store permanent materials in accordance with manufacturer's recommendations. Any material not properly stored will not be paid for.
Amounts will be deducted from payments for any stored permanent material previously paid for and subsequently found to be improperly stored or not present, based upon a physical inventory of stored permanent material.
D. Only the neat line quantity of material needed for the finished product may be paid for.
E. All requests for stored permanent material payment must be accompanied by paid invoices clearly showing the quantity of permanent material, the type of permanent material and discounts or rebates and the net amount paid to the supplier along with a certificate stating that the permanent material is free of any liens or judgments preventing its use by the City.
F. If the permanent material is stored outside the Denver area the Contractor must pay for the City representative's transportation and lodging to see the stored material as needed.
Acceptable lodgings must, as a minimum, have a Mobil Travel Guide Rating Criteria® rating of Two-Star or the American Automobile Association Lodging Listing Requirements & Diamond Rating Guidelines® rating of Two Diamonds. The minimum transportation shall be by regularly scheduled commercial air carrier at coach rates. The DEN Project Manager will determine if an overnight stay is required.
G. All permanent material stored off site, for which payment is being requested, must be insured and stored in bonded, insured warehouses. The Contractor shall provide proof of insurance for all material stored off site, and specific address and storage conditions of storage location.
H. Any permanent material on which payment is requested must be in such a form that it cannot be used on work other than this Contract, or stored in a manner acceptable to the DEN Project Manager to ensure that the permanent material cannot be used on work other than this Contract.
3.04 ALLOWANCE AUTHORIZATION AND PAYMENT
A. Contractor shall request written approval for expenditure of any Contract allowances PRIOR TO performing the Work involved. List work to be performed and estimated cost in the requesting correspondence.
B. Original copies of all invoices and receipts must be submitted with the Allowance Authorization as part of the request for payment.
C. Using the format provided by the City, the Contractor’s request for payment of all Contract allowances shall be included in the Schedule of Values.
PART 4 - MEASUREMENT
A. No separate measurement shall be made for work under this Section.
DESIGN CONTRACT NO. 202265738
PART 5 - PAYMENT
5.01 METHOD OF PAYMENT
A. No separate payment will be made for work under this section. The cost of the work described in this section shall be included in the applicable unit price item, work order or
END OF SECTION 012910
DESIGN CONTRACT NO. 202265738
SECTION 012976
PROGRESS PAYMENT PROCEDURES
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Special Conditions other Division 01 Specification Sections, and Related Requirements apply to this Section.
1.02 SUMMARY
A. Section includes requirements for the following:
1. Section 011100 “Summary of Work”
2. Section 013100 “Project Management and Coordination”
3. Section 013300 “Submittal Procedures”
A. General Process Requirements
1. Payment application need to be submitted as per the Agreement.
2. Comply with the PM Guide for invoicing.
B. Progress Payment Package
1. Subcontractor Payment Verification
a. The Contractor shall submit with the Schedule, a report of all work performed by subcontracted parties of all tiers, and current payment status.
b. The report shall include the following minimum fields:
1) Project name
2) Project number
3) Date
4) Name of Contractor
5) Name of all subcontractors, of all tiers, as listed in the bid as well as any subsequently submitted CM-02 forms, including the following information for each subcontracted firm:
a) Total value of work performed
b) Total amount paid to date
c) Date of last payment
d) Balance due
e) Payment Terms
f) Remaining balance to be paid
g) Planned payment date
c. Failure to provide this information may result in withholding of progress
DESIGN CONTRACT NO. 202265738
payments, pursuant to Article 909.1 of the General Contract Conditions
C. Submission Requirements
1. Refer to the PM Guide for invoicing.
3.02 TIMELINE
A. Prompt Pay Requirements
1. Refer to the Prompt Pay Ordinance
B. Penalties for Late Payments
1. A Key Performance Indicator (KPI) is a way of measuring specific performance of the Contractor for which a target is stated in the KPI Schedule contained in Exhibit / Table (X). The KPIs for this section relate to the Contractor's performance with submitting documentation related to invoice submissions and proof of subcontractor / vendor payment, see Exhibit / Table (X).
2. An assessment of the Contractor’s performance against the KPIs is made monthly at the time of the Contractor's invoice submittal and request for payment. Reporting of performance and assessments are carried out in accordance with the provisions of this Article.
3. As used in this clause and specification, the Moderated Amount represents the amount of Contractor’s fee contained in each payment application.
4. If the Contractor achieves a target stated for a Key Performance Indicator in respect of any assessment interval, they are entitled to be paid the allocated weighting set out in the KPI Schedule of the Moderated Amount, in respect of that monthly assessment interval ("Due Moderated Amount").
5. The Moderated Amount and each Due Moderated Amount in respect of the first two assessment intervals following the Contract Date shall be paid as submitted and reviewed in order to allow the Contractor to become acquainted with the invoice submission process.
6. Where the Contractor does not become entitled to be paid Due Moderated Amounts which in total equal the full amount of the Moderated Amount in respect of the relevant assessment interval, the Contractor still has the opportunity to earn the amount of the Moderated Amount to which they did not become entitled in respect of the…