This document describes a data item description for a program management plan. The program management plan is required to provide technical, management, schedule, and cost data using a contract work breakdown structure. It must include an introduction, relationship to the CWBS describing each element and associated costs, a milestone chart covering major program activities by CWBS and timeline, a government furnished equipment chart, a cost chart depicting estimated annual program spending, a purchase chart outlining subcontractors and purchases, and organization charts depicting the program and functional structures. The related federal contract opportunity is a sole source solicitation for Northrop Grumman for attitude motion sensor set engineering services due on July 19, 2021 issued by the Department of the Air Force Materiel Command Air Force Sustainment Center.

View the file

Other files

File Type Posted
DID81874.pdf PDF
DID81249B.pdf PDF
DID80508B.pdf PDF
PWS.docx DOCX document
DID80809B.pdf PDF
DID80447A.pdf PDF
DID81928.pdf PDF
DID80067C.pdf PDF
3130548_CDRL1_REPORT.pdf PDF
DID81000F.pdf PDF
DID80639E.pdf PDF
DID81250B.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DATA ITEM DESCRIPTION

Title: PROGRAM MANAGEMENT PLAN

Number: DI-MGMT-81797 Approval Date: 20091208 AMSC Number: F9115 Limitation: N/A DTIC Applicable: No GIDEP Applicable: No Office of Primary Responsibility: 70 (OO-ALC/526 ICBM) Applicable Forms:

Use/Relationship: The Program Management Plan provides technical, management, schedule, and cost data. It provides current information which is used to describe the approach, resources and needs of the contractor to perform the effort. This data item description (DID) contains the format and content instructions for the data product to be generated.

Requirements:

1. Reference documents: None

2. Format. The Program Management Plan shall be in contractor format and shall be unclassified.

3. Content. The Program Management Plan shall be an integrated document showing technical, cost and schedule data to a common base, the contract work breakdown structure (CWBS) or it’s planning equivalent. It shall also provide information on the contractor’s organization, practices and techniques to be used in managing the program and, if applicable, subcontractors. The plan shall specifically contain the following:

a. Introduction to the plan.

b. Indication of the relationship of the plan to the CWBS: This shall include a description of each element and the cost associated with each element.

c. Milestone chart: A detailed program milestone chart covering the major activities of the program (system deliveries, tests, etc,) by CWBS, if applicable, and in linear time phasing.

d. Equipment/facilities chart: A chart depicting major government furnished equipment (GFE) and the date and duration that such GFE and facilities are required.

e. Cost chart: A cost chart depicting by month the estimated program spend forecast per fiscal year (October thru September).

Source: https://assist.dla.mil -- Downloaded: 2014-05-20T17:54Z Check the source to verify that this is the current version before use.

DI-MGMT-81797

f. Purchase Chart: A chart depicting subcontractors and equipment or material purchases, the date and approximate amount of each.

g. Organization data including:

(1) Program organization chart: A chart showing the structure of the program organization by title and name. Identify the program office, support contractors, and major subcontractors.

(2) Program/functional organization relationship chart: A chart showing the relationship of the program functions to the functional organizations indicating lines of authority and communications.

4. End of DI-MGMT-81797

Source: https://assist.dla.mil -- Downloaded: 2014-05-20T17:54Z Check the source to verify that this is the current version before use.

Use/Relationship: The Program Management Plan provides technical, management, schedule, and cost data. It provides current information which is used to describe the approach, resources and needs of the contractor to perform the effort. This data item description (DID) contains the format and content instructions for the data product to be generated.