Amend_002_Project_Drawings.pdf

PDF 36 MB Posted

Attached to
Construct VT Hanlon Substation, Stage 01, in South Dakota Federal contract opportunity
Solicitation number
DE-SOL-0007930
Issued by
Department of Energy Western Area Power Administration

About this file

Revised and additional drawings

View the file

Other files for this federal contract opportunity

Other files attached to Construct VT Hanlon Substation, Stage 01, in South Dakota, newest first.
File Type Posted
Amendment_003.pdf PDF
VH_Contractor_and_internal_questions_and_answers.docx DOCX document
Amend_002_Bidding_Schedule.pdf PDF
Amend_002_Project_Specifications.pdf PDF
Amend_002_SF30.pdf PDF
21._Amendment_0001.pdf PDF
21._Prospective_Bidders_Letter.pdf PDF
Project_Drawings.pdf PDF
Contract_Clauses_and_Bid_Schedule.pdf PDF
Project_Specifications.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT 002

VT HANLON SUBSTATION, STAGE 01

PROJECT DRAWINGS

A. GENERAL:

CONSTRUCTION STANDARD DRAWINGS: A complete set of standard drawings are available at:

https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspxm Construction drawings are the specification drawings and any additional drawings required for use in construction.

The construction drawings will be issued after contract award and may include amendment changes and other details, which make the drawings suitable to use for construction purposes.

PROJECT DRAWINGS: Project drawings included herein are reduced reproductions and are not to scale. Some project drawings show details of fabrication and other information not a part of the work. Disregard information and details, which are not applicable.

STANDARD DRAWINGS: Where details shown on standard drawings included herein differ from project drawings or text, the details of project drawings or text shall govern.

INFORMATIONAL DRAWINGS: Some project drawings have the words “FOR INFORMATION ONLY” appearing above the title block. These drawings show some information, which may be required for bidding purposes.

These drawings do not show items to be furnished or work to be performed.

EXISTING INSTALLATION DRAWINGS: Some project drawings have the words “EXISTING INSTALLATION” appearing above the title block. These drawings show the existing installations prior to modifications and may show some new work to be performed.

REFERENCE DRAWINGS: Reference drawings referred to on project drawings and not included herein, are not necessary for bidding purposes.

CONTRACTOR'S RESPONSIBILITY: Check all drawings and advise Western of any errors or omissions.

B. LIST OF DRAWINGS:

LOCATION MAP:

1. VH 0015 – Location and Vicinity Map

ELECTRICAL:

2. VH 0001-1 Rev. A– Switching Diagram (Sheet 1 of 2)

3. VH 0001-2 Rev. A – Switching Diagram (Sheet 2 of 2)

4. VH 1000 Rev. A – General Arrangement Plan

5. VH 1010 – 230KV Area East Bus Plan

6. VH 1011 Rev. A – 230KV Area West Bus Plan

7. VH 1025 – 230/115KV XFMR Area Plan

8. VH 1030 – 115KV & 69KV Areas Plan

9. VH 1040 Rev. A – 230/69KV XFMR Area Plan

10. VH 1050 Rev. B – 69KV Area Plan

11. VH 1100 – Equipment and Material Index

12. VH 1110 – 230KV Area Bay V1 Sections

13. VH 1111 – 230KV Area Bay V2 Sections

14. VH 1112 – 230KV Area Bay V3 Sections

15. VH 1113 – 230KV Area Bay V4 Sections

16. VH 1114 – 230KV Area Bay V5 Sections

17. VH 1115 – 230KV Area Bay V6 Sections

18. VH 1116 – 230KV Area Bay V7 Sections

19. VH 1117 – 230KV Area Bay V8 Sections

20. VH 1118 – 230KV Area Sections J1-J1 and K1-K1

21. VH 1119 – 230KV Area Sections J2-J2 and K2-K2

22. VH 1120 – 230KV Area Section M1-M1

23. VH 1121 – 230KV Area Section M2-M2

24. VH 1125 – KV7A XFMR Area Sections A-A, B-B, and C-C

25. VH 1127 – KV3A XFMR Area Section F-F

26. VH 1130 – 115KV & 69KV Areas Bays Y1 and Y2

27. VH 1131 – 115KV & 69KV Areas Bays Y3 and Y4

28. VH 1132 – 115KV & 69KV Areas Bays Z5 and Z6

29. VH 1133 – 115KV & 69KV Areas Bays Z7 and Z8

30. VH 1140 – KV2A XFMR Area Section A-A

31. VH 1145 – KV6A XFMR Area Section B-B

32. VH 1150 – 69KV Area Bays Z9 and Z10

33. VH 1151 – 69KV Area Bays Z11 and Z12

34. VH 1152 – 69KV Area Bays Z13 and Z14

35. VH 1153 – 69KV Area Bays Z15 and Z16

36. VH 1154 Rev. A – 69KV Area Bays Z17 and Z18

37. VH 1155 – 69KV Area Section F-F

38. VH 1160 – 12.47KV Area Sections D-D and E-E

39. VH 1164 – 12.47KV Area Reactor Dampening Structure

40. VH 1165 – 12.47KV Area Station Service Feed https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspxm

PROJECT DRAWINGS

41. VH 1180 – 230KV Area Instrument Transformer Details

42. VH 1181 – 115KV Area Instrument Transformer Details

43. VH 1182 – 69KV Area Instrument Transformer Details

44. VH 1185 – A-Frame Details

45. VH 1500 Rev. A – General Grounding Plan

46. VH 1510 – 230KV Area East Bus Grounding Plan

47. VH 1511 – 230KV Area West Bus Grounding Plan

48. VH 1525 – 230/115KV XFMR Area Grounding Plan

49. VH 1530 – 115KV & 69KV Areas Grounding Plan

50. VH 1540 – 230/69KV XFMR Area Grounding Plan

51. VH 1550 Rev. A – 69KV Area Grounding Plan

52. VH 1600 Rev. A – Station Service DWA Wiring Diagram

53. VH 1602 – Service Panel DWB Wiring Diagram

54. VH 1604 – Service Panel DWC Wiring Diagram

55A. VH 1612 – 230KV Area 120/240V Wiring Diagram

55B. VH 1614 – 115KV & 69KV Areas 120/240V Wiring Diagram

55C. VH 1616 – 69KV Area 120/240V Wiring Diagram

55. VH 1606 – Service Panel DWD Wiring Diagram

56. VH 1700 Rev. A – General Conduit Plan

57. VH 1710 – 230KV Area East Bus Conduit Plan

58. VH 1711 Rev. A – 230KV Area West Bus Conduit Plan

59. VH 1725 Rev. A – 230/115KV XFMR Area Conduit Plan

60. VH 1730 – 115KV & 69KV Areas Conduit Plan

61. VH 1740 – 230/69KV XFMR Area Conduit Plan

62. VH 1750 Rev. A – 69KV Area Conduit Plan

63. VH 1780 FIO – Fiber Optic Cable Mounting Details (For Information Only)

CIVIL & SITE DRAWINGS:

64. VH 0016 – Topography

65. VH 2050 Rev. B – Site Plan

65A. VH T017 – Existing Tile Lines

66. VH 2051 Rev. A – Grading Plan

67. VH 2052 Rev. A – Sections & Details (Sheet 1 of 2)

68. VH 2053 – Sections & Details (Sheet 2 of 2)

69. VH 2054 – 12” HDPE Pipe & Outlet Headwall Plan & Profile, Detail & Sections

FOUNDATION AND STRUCTURAL DRAWING INDEX:

70. VH 2000 Rev. A – Foundation/Structural Data and Drawing Index

CONCRETE:

71. VH 2150 Rev. A – Foundation General Plan

72. VH 2200 – 230KV Area East Bus Foundation Plan

73. VH 2201 – 230KV Area West Bus Foundation Plan

74. VH 2202 – 230/115KV XFMR Area Foundation Plan

75. VH 2203 – 230/69KV XFMR Area Foundation Plan

76. VH 2204 – 115KV & 69KV Area Foundation Plan

77. VH 2205 Rev. A – 69KV Area Foundation Plan

78. VH 2300-1 – Foundations Outline and Reinforcement (Sheet 1 of 2)

79. VH 2300-2 – Foundations Outline and Reinforcement (Sheet 2 of 2)

80. VH 2301-1 – Foundations Outline and Reinforcement (Sheet 1 of 2)

81. VH 2301-2 – Foundations Outline and Reinforcement (Sheet 2 of 2)

82. VH 2302-1 – Foundations Outline and Reinforcement (Sheet 1 of 2)

83. VH 2302-2 – Foundations Outline and Reinforcement (Sheet 2 of 2)

84. VH 2303 – Foundations Outline and Reinforcement

85. VH 2304 – Foundations Outline and Reinforcement

86. VH 2305 – Foundations Outline and Reinforcement

87. VH 2306 Rev. A – Foundations Outline and Reinforcement

88. VH 2307 Rev. A – Foundations Outline and Reinforcement

89. VH 2308 Rev. A – Foundations Outline and Reinforcement

90. VH 2309 Rev. A – Foundations Outline and Reinforcement

91. VH 2310 Rev. A – Foundations Outline and Reinforcement

PROJECT DRAWINGS

92. VH 2311 Rev. A – Foundations Outline and Reinforcement

93. VH 2312 Rev. A – Foundations Outline and Reinforcement

94. VH 2313 – Foundations Outline and Reinforcement

94A. VH 2314 Rev. A – Foundations Outline and Reinforcement

94B. VH 2315 Rev. A – Foundations Outline and Reinforcement

94C.VH 2316 Rev. A – Foundations Outline and Reinforcement

CABLE TRENCH:

95. VH 2500 – Cable Trench Plan and Details

96. VH 2501 – Cable Trench Sections

ANCHOR BOLTS & EMBEDDED MATERIALS:

97. VH 2550 – Anchor Bolts

STEEL & ALUMINUM STRUCTURES:

98. VH 2600 – 230KV Take-Off Structure Type IV Elevation

99. VH 2601-1 – 230KV Take-Off Structure Type IV - Assemblies and Connections (Sheet 1 of 2)

100. VH 2601-2 – 230KV Take-Off Structure Type IV Assemblies and Connections (Sheet 2 of 2)

101. VH 2602 – 230KV Take-Off Structure Type V Elevation

102. VH 2603-1 – 230KV Take-Off Structure Type V - Assemblies and Connections (Sheet 1 of 2)

103. VH 2603-2 – 230KV Take-Off Structure Type V - Assemblies and Connections (Sheet 2 of 2)

104. VH 2604 – 115KV Take-Off Structure Type I & II Elevation

105. VH 2605 – 115KV Take-Off Structure Type I & II Assemblies and Connections

106. VH 2606 – 115KV Take-Off Structure Type III Elevation

107. VH 2607 – 115KV Take-Off Structure Type III Assemblies and Connections

108. VH 2608 – 230KV Bus Tower Type I Elevation

109. VH 2609 – 230KV Bus Tower Type I Assemblies and Connections

110. VH 2610 – 45 Ft. Ground Mast Type I

111. VH 2611 – 65 Ft. Ground Mast Type II

112. VH 2612 – Bus Poles Aluminum Design and Details

113. VH 2613 – Bus Poles Steel Design and Details

114. VH 2614 – Bus Tee Poles (2 Phase) Aluminum Design and Details

115. VH 2615 – Bus Tee Poles (2 Phase) Steel Design and Details

116. VH 2616 – Bus Tee Poles (3 Phase) Steel Design and Details

117. VH 2617 – Bus Frames Steel Design and Details

118. VH 2618 – Disconnect Switch Supports Steel Design and Details

119. VH 2619 – Equipment Supports Steel Design and Details

120. VH 2620 – Reactor Dampening Support Type I Elevation

121. VH 2621 – Reactor Dampening Support Type I Sections & Details

122. VH 2622 – Station Service Feed Support Type I Elevation

123. VH 2623 – Station Service Feed Support Type I Sections & Details

124. VH 2624 – 69KV Fuse Disconnect Switch Support Type I Steel Design and Details

125. VH 2925 – Equipment Cabinet Platforms Steel Design and Details

126. VH 2926 – Switch Operating Platforms Steel Design and Details

STRINGING REQUIREMENTS:

127. VH 2900 – Stringing Requirements

CONTROL BUILDING:

128. VH 3200 – General Structural Notes, Abbreviations & Reference Drawings

129. VH 3201 Rev. A – Structural Foundation Plan

130. VH 3202 Rev. A – Structural Roof Framing Plan

131. VH 3203 – Structural Foundation Sections & Details

132. VH 3204 – Structural Foundation/Cable Entry Details (Sh 1 of 2)

133. VH 3205 – Structural Foundation/Cable Entry Details (Sh 2 of 2)

134. VH 3206 – Structural Typical Wood-Framed Wall

135. VH 3207 – Structural Equipment Mounting Details

136. VH 3208 – Building Entry Platforms Steel Design and Details

137A. VH 3000-1 – Architectural Floor Plan

137B. VH 3000-2 – Architectural Reflected Ceiling Plan

138. VH 3001 Rev A – Architectural Exterior Elevations

139. VH 3002 – Architectural Building Sections

140. VH 3003 – Architectural Detailed Sections

141. VH 3004 – Architectural Detailed Sections

PROJECT DRAWINGS

142. VH 3005 Rev. A – Architectural Mechanical Mounting Details

143. VH 3006 – Architectural Door & Window Details

144. VH 3300 Rev. A – Mechanical HVAC Floor Plan

145. VH 3301 Rev. A – Mechanical HVAC Upper Plan.

146. VH 3302 Rev. A – Mechanical Control Room Schedules

147. VH 3303 Rev. A – Mechanical Battery Room Schedules

148. VH 3304 Rev. A – Mechanical HVAC Details

149. VH 3400 Rev . A – Electrical Power Plan

150. VH 3401 Rev. A – Electrical Luminaire & Egress Marking Plan

151. VH 3402 Rev. A – Electrical Door Alarms

152. VH 3403 Rev. A – Electrical Panelboards DHA, DHA1

153. VH 3404 Rev. A – Electrical Wiring Devices Schematic

154. VH 3405 Rev. A – Electrical Luminaire & Equipment Schedules

CONTROLS:

155. VH 4000 Rev. A – Service Building – Arrangement, Conduit & Grounding

156. VH T600-1 Rev. A - Control Cable List (Sh 1 of 2)

157. VH T600-2 Rev. A - Control Cable List (Sh 2 of 2)

158A. VH 6000-1 - DC Distribution Panel BHA1 Wiring Diagram

158B. VH 6000-2 – DC Distribution Panel BHA2 Wiring Diagram

EXISTING TRANSMISSION LINE STRUCTURES:

159. 43-26S 2200 FIO – 26S Tower 55 and 70FT Bodies (For Information Only)

160. 43-26S 2201 Rev A FIO – 26S Tower Leg Extensions to 55 FT Body and Stub Angle (For Information Only)

161. 43-212N 2200 Rev B FIO – Double Circuit Steel Towers 212N & N1 Tower 50’ Body – 10’ Leg Extension & Stub

(For Information Only)

161A. FT-SF D 2005 Rev. A – Fort Thompson – Sioux Falls Double Circuit Steel Towers Footing Data and Selection Criteria (For Information Only)

161B. FT-SF D 2006 Rev. A – Fort Thompson – Sioux Falls Double Circuit Steel Towers Footing Data and Selection Criteria (For Information Only)

161C. FT-SF D 2007 Rev. A – Fort Thompson – Sioux Falls Double Circuit Steel Towers DSH Tower Footings – Types A, B, C, and D (For Information Only)

161D. FT-SF D 2008 Rev. A – Fort Thompson – Sioux Falls Double Circuit Steel Towers DSH Tower Footings – Types DF and DFH (For Information Only)

161E. FT-SF D 2009 Rev. A – Fort Thompson – Sioux Falls Double Circuit Steel Towers DSH Tower Footings – Types PT and PTH (For Information Only)

PLAN AND PROFILES:

162. FT-SF D 4082 Rev. A EI – Fort Thompson – Sioux Falls 230KV Transmission Line Station 1448+00 to 1502+00

(Existing Installation)

163. FT-SF D 4083 Rev. A EI – Fort Thompson – Sioux Falls 230KV Transmission Line Station 1394+00 to 1448+00 (Existing Installation)

GEOLOGY:

164. VH 8000 – Geotechnical Boring Location Plan

165. VH 8001 – Soil Boring Diagram – VT Hanlon Substation Expansion

166. VH 8002 – Boring Number SB-01 and SB-02

167. VH 8003 – Boring Number SB-03 and SB-04

168. VH 8004 – Boring Number SB-05 and SB-06

169. VH 8005 – Boring Number SB-07 and SB-08

170. VH 8006 – Boring Number SB-09

171. VH 8007 – Subsurface Exploration – Penetration Resistance and Log – Hole No. PR14-1 and PR14-2

172. VH 8008 – Subsurface Exploration – Penetration Resistance and Log – Hole No. PR14-3 and PR14-4

173. VH 8009 – Subsurface Exploration – Penetration Resistance and Log – Hole No. PR14-5 and PR14-6

174. VH 8010 – Subsurface Exploration – Penetration Resistance and Log – Hole No. PR14-7 and PR14-8

175. VH 8011 – Subsurface Exploration – Penetration Resistance and Log – Hole No. PR14-9

176. VH 8012 – Geotechnical Subsurface Diagram – SB-01, SB-03, SB-04, SB-05 and SB-06

177. VH 8013 – Geotechnical Subsurface Diagram – SB-07, SB-08 and SB-09

178. VH 8014 – Geotechnical Subsurface Diagram – SB-02, SB-04, SB-07 and SB-08

2Amendment 002

3Amendment 002

4Amendment 002

6Amendment 002

9Amendment 002

10Amendment 002

45Amendment 002

51Amendment 002

52Amendment 002

55AAmendment 002

55BAmendment 002

55CAmendment 002

56Amendment 002

58Amendment 002

59Amendment 002

62Amendment 002

65Amendment 002

65AAmendment 002

67Amendment 002

70Amendment 002

71Amendment 002

77Amendment 002

87Amendment 002

88Amendment 002

89Amendment 002

90Amendment 002

91Amendment 002

92Amendment 002

93Amendment 002

94AAmendment 002

94BAmendment 002

94CAmendment 002

129Amendment 002

130Amendment 002

137AAmendment 002

137BAmendment 002

138Amendment 002

142Amendment 002

144Amendment 002

145Amendment 002

146Amendment 002

147Amendment 002

148Amendment 002

149Amendment 002

150Amendment 002

151Amendment 002

152Amendment 002

153Amendment 002

154Amendment 002

155Amendment 002

156Amendment 002

157Amendment 002

158AAmendment 002

158BAmendment 002

161AAmendment 002

161BAmendment 002

161CAmendment 002

161DAmendment 002

161EAmendment 002

Amend 002 Drawing Index.pdf
A. GENERAL:
B. LIST OF DRAWINGS:

File details come from the government source that posted it. Updated .