One Agency, One Team, One Direction

Elements of an Adequate Proposal

The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations

Page | 1

Further information is available in the Information for Contractors Manual under Enclosure 3

Today’s Discussion

Price Proposal Price Proposal Adequacy Common Proposal Deficiencies

Adequate Cost or Pricing Data

On-line Resources

Page | 2

Proposal Adequacy The Contractor is responsible for providing adequate supporting data.

The contractor bears the burden of proof in establishing reasonableness of proposed costs.

The basis and rationale for all proposed costs should be provided as part of the proposal so that the government can place reliance on the information as current, accurate, and complete.

Page | 3

FAR Part 15, Table 15-2 – Instructions for submitting cost/price proposals when certified cost or pricing data are required.

DFARS 252.215-7009 Proposal Adequacy Checklist - New Requirement - Provides location of requested information or an explanation of why the requested information is not provided.

How is proposal adequacy determined?

Price Proposal Adequacy

Page | 4

Proposal Cost Elements

Direct Labor

Material

Subcontracts

Other Direct Costs (ODCs)

Indirect Rates

Page | 5

Direct Labor An adequate proposal should include:

A time -phased (e.g., monthly, quarterly, etc.) breakdown of labor hours, rates, and cost by appropriate category The basis of proposed labor rates and classifications including any escalation factors:

DCAA will determine how proposed labor rates were estimated and will need to audit any data that supports these estimates.

DCAA will evaluate the basis of labor categories (labor grades) proposed and the hours assigned to each labor category.

The basis of proposed labor hours, comparisons of proposed hours to experienced hours for the production of similar items; and any learning curve applications.

Page | 6

Material An adequate proposal should include a consolidated priced summary of individual material quantities included in the various tasks, orders, or contract line items. In addition, the consolidated bill of material should provide:

The basis for pricing (vendor quotes, invoice prices, competitive bids, etc.)

Include raw materials, parts, components, assemblies, and services to be produced or performed by others.

Identify the item and show the source, quantity, and price.

Page | 7

Price Competition DCAA has found contractors inappropriately claiming there is adequate price competition.

Contracting officers directed to no longer limit their analysis to the FAR 15.403-1(c)(1)(ii) and (iii) to determine that the offered price is based on adequate competition when only one offer is received.

Contracting officers may require cost or pricing data, or other than cost or pricing data when only one offer is received.

Page | 8

Subcontracts An adequate proposal includes the basis of proposed subcontract costs including the prime contractor’s cost or price analyses of all subcontractor proposals.

Submit the subcontractor’s cost or pricing data as part of your own cost or pricing data, as well as your analyses of the subcontractor’s cost or pricing data per FAR 15.403-4 and FAR 15.403-1(b)

Include data showing the degree of competition and the basis for establishing the source and price reasonableness

Include support for commercial item determinations and the basis for establishing the commerciality and price reasonableness

The prime contractor is responsible for managing its subcontracts per FAR 42.202(e)(2)

Page | 9

Examples of Inadequate Subcontract Analysis Procedures

No cost or price analysis completed/documented Failure to support the degree of competition or basis for establishing the source selection or price reasonableness Failure to perform commercial item determination or price reasonableness No documentation on attempts to perform analysis and seek Government assistance when denied access to subcontractor’s records

Page | 10

Subcontract Analysis Adequate Analysis:

Reduced audit time Cost savings in reduced audit support Timely audit report

Inadequate Analysis:

Unsupported costs

Adverse audit opinion Increased audit time and support costs

Negotiation delays

Page | 11

Adequate or Inadequate

Subcontractor’s proposed labor rate is an average of 100 manufacturing employees.

The prime contractor’s cost analysis states:

“We recalculated the average labor rate and considered the labor rate reasonable.”

Page | 12

Adequate or Inadequate?

Answer

INADEQUATE

Page | 13

Improvements to Consider Subcontractor’s proposed labor rate is an average of 100 manufacturing employees.

In addition to a recalculation consider the following:

When averaging ensure representative of function being bid Validate labor rates by employee to labor records Compare labor rates to market labor rates Document the scope of the labor rate evaluation

Page | 14

Other Direct Costs Other Direct Costs vary but could include items such as:

Special tooling

Packaging

Travel

The basis for pricing should be included in the proposal (vendor quotes, invoice prices, competitive bids, etc.)

Page | 15

Indirect Costs An adequate proposal includes the basis of the proposed indirect expense rates.

Required support is at least the current year detailed operating budget and a long range forecast/strategic plan covering all the periods of performance.

The operating budget should be at the department/pool level with expense item detail supporting anticipated contract performance.

The budget should detail indirect expenses and show the relationship of direct labor (or other indirect expense allocation bases) to sales projections.

Support also includes comparisons by year of projected overhead expenses by account to prior years’ incurred amounts. Out-year projections should be supported by the contractor’s analysis of the impact on its rates based on its long range forecast/strategic plan.

Page | 16

Requirements FAR 15.408 – Table 15-2 II C.

Show trends and budgetary data to provide a basis for evaluating the reasonableness of proposed rates.

Page | 17

Budgetary Data Straight-lining out-year rates for future periods with no explanation is not adequate.

Support for out-year pools and bases should be made based on reasonable sales forecasts and contractor’s assumptions for changes, if any, to major cost groupings (e.g., variable, semi-variable, and fixed).

Small firms with limited budgetary data can use historical costs to estimate out-year rates. However, the contractor should provide trend data with appropriate explanations to support that the historical costs are the most reasonable estimate.

Page | 18

Examples of Inadequate Budgetary Data

“Flat-lined” indirect rates with no support for using the same rate each year of the period of performance

No detailed budgetary data provided

Projections provided for only the first year of proposal’s period of performance

Page | 19

Budgetary Data Adequate Data:

Better planning Efficient and timely audits More accurate cost estimates

Inadequate Data:

More lengthy audits

Adverse audit opinion Delay in negotiation

Page | 20

Page | 21

Explanation Adequate or Inadequate?

Page | 22

Straight lining out-years rates for lack of budgetary data is not acceptable.

Consider the following:

Explain differences in trended rates Explain why the rate will not change Consider an analysis of fixed, variable, and semi-variable costs Any upcoming changes

Page | 23

Adequate Cost or Pricing

Factual and verifiable

Includes data in forming a basis for judgment

All facts that can be reasonably expected to contribute to the soundness of estimates of future costs and to the validity of determination of costs already incurred

Page | 24

Definition/Requirements FAR 2.101 – Cost or Pricing Data All facts existing up to the time of agreement on price which prudent buyers and sellers would reasonably expect to affect price negotiations significantly.

FAR 15.406-2

Requires certification that data is current, accurate, and complete.

Truth in Negotiations (TINA) (10 U.S.C. 2306(a)) Requires contractors to submit accurate, complete, and current cost or pricing data when negotiating contracts with the Government. It also provides the Government with a price reduction remedy if a contractor fails to comply and provides provisions for interest and penalties.

Page | 25

Examples of Cost or Pricing

Vendor quotations Purchase orders Make-or-buy decision Accounting records Information on production methods Data supporting projections of business prospects

Page | 26

A few examples of cost or pricing data:

Cost or Pricing Data Adequate Cost or Pricing Data:

Better estimating More timely and effective audits Accurate follow-on pricing

Inadequate Cost or Pricing Data:

Potential for defective pricing

Longer audits Poor estimating

Inaccurate follow-on pricing

Page | 27

In price proposal dated July 2018, unit 1X52 is estimated at $2,000/per unit based on:

Purchase order number 124 dated July 6, 2012

Page | 28

Adequate or Inadequate?

Page | 29

While the purchase order is verifiable, it is not current.

Consider the following:

Current competitive quote Market pricing Adjust estimated prices for cost trends and quantity Ensure non-recurring costs are not included in unit-price Make or buy analysis Inventory on hand Cost or pricing data if over threshold

Page | 30

Cost or Pricing Data Considerations Labor:

Historical data - its use or nonuse Basis for escalation factors Turnover Compensation issues Changes in compensation policy Market rates to demonstrate reasonableness Historical skill mix to demonstrate basis of estimate Improvement curves

Page | 31

Cost or Pricing Data Considerations Indirect Rates:

Internal budgets Basis of escalation factors Changes in headcount Sales forecast Historical rates/accuracy of previous forecasts Ongoing issues (e.g., CAS) Any known accounting issues that may impact rates

Page | 32

Historical Data

Estimates based on historical data should consider:

Learning efficiencies Prior non-recurring costs Escalating/diminishing costs Representative/Non-representative aspects of historical cost used to estimate

Page | 33

Unallowable Costs Ensure proposed rates/costs exclude unallowable costs

FAR 31.201-2

Generally Accepted Accounting Principles ( GAAP) Allowable per FAR 31.205 Reasonable Terms of the contract Allocable Cost Accounting Standards (CAS), if applicable

Page | 34

Common Deficiencies Inadequate cost or pricing data

Lack of/inadequate budgetary data

Failure to perform subcontract analysis

Wrap Up Pricing proposals should include the following:

Cost or Pricing Data which supports all proposed costs

Budgetary Data (or support for proposed indirect rates) for the entire period of performance

Subcontract Analysis, if applicable

Page | 36

Resources

DFARS

http://farsite.hill.af.mil/vmdfara.htm http://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html DoD Proposal Adequacy Checklist

FAR

http://farsite.hill.af.mil/vmfara.htm https://www.acquisition.gov/browsefar

DCAA

www.dcaa.mil Information for Contractors Manual

Page | 37

Questions/Comments

Page | 38

File details come from the government source that posted it. Updated .