CW_RO1_Chemical_Storage_-_Bid_Set_-_Drawings_SS.pdf
PDF 17 MB Posted
- Solicitation number
- 23-0051-UT
- Issued by
- Pinellas County, Florida
About this file
This file is a bid set drawing document for Pinellas County's RO1 Chemical Storage and Feed System Improvements project. The project encompasses comprehensive improvements to the reverse osmosis facility's chemical handling infrastructure, including preparation and protective coating of containment areas for hydrofluorosilicic acid, antiscalant, sodium bisulfite, and caustic; installation of leak detection sensors with conduit and wiring throughout chemical feed and storage areas; demolition and replacement of ammonium hydroxide storage infrastructure with temporary ammonia dosing facilities; furnishing and installation of new storage tanks, day tanks, chemical piping, tubing, valves, fittings, supports, and transfer pumps; installation of a new level switch with accessories and grating in the sump area; furnishing and installation of a new dosing SCADA system; and demolition and replacement of the caustic dosing line with new containment, insulation, injection quill, and injection quill housing in the RO process room. Bids are due July 22, 2026, with contract documents posted June 10, 2026. The Contractor must provide fixed project signs as described in the contract documents, with the final quantity determined at project mobilization based on schedule-related cost impacts.
Contractors must hold a current Florida state Contractor License/Registration and Pinellas County registration if applicable, submitting copies with their bid response. The project drawings and specifications provide detailed technical requirements for all work scope items. No specific pricing information, set-asides, incumbent contractor details, or funding amounts are detailed in this drawing document, as it serves as a technical reference for bid preparation rather than a comprehensive contract solicitation document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RO1_Chemical_Storage_and_Feed_System_Improvements_(Addendum_#2_Revision).pdf | ||
| IMG_0109.MOV | MOV file | |
| IMG_0108.MOV | MOV file | |
| IMG_0107.MOV | MOV file | |
| IMG_0106.MOV | MOV file | |
| IMG_0105.MOV | MOV file | |
| Photos.pdf | ||
| CW_RO1_Chemical_Storage_Supplemental_Specifications.pdf | ||
| CW_RO1_Chemical_Storage_-_Bid_Set_-_Drawings_SS.pdf | ||
| RO1_Chemical_Storage_and_Feed_System_Improvements.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID SET
City Project No. 23-0051-UT City Plan Set No. 2026010
Tara L. Kivett, P.E.
City Engineer
Approved For Construction
Date Approved
CITY ENGINEER Tara L. Kivett, P.E. #86611
RO1 CHEMICAL STORAGE AND
FEED SYSTEM IMPROVEMENTS
SHEET INDEX
Project Location
N
S
EW
Sheet 1 of 21
CITY OFFICIALS
Bruce Rector Mayor Ryan Cotton Councilmember Mike Mannino Councilmember David Allbritton Councilmember Lina Teixeira Councilmember Jennifer Poirrier City Manager
G-002
2 21
GENERAL NOTES
1. All work performed shall comply with the regulations and ordinances of the various governmental agencies having jurisdiction over the work.
2. All workmanship and materials used in the construction of this project shall conform to the latest City of Clearwater standards, contract documents and specifications unless otherwise noted.
3. Specific requirements of the Florida Department of Transportation (FDOT) “Design Standards” and “Standard Specifications for Road and Bridge Construction”, most current editions, are incorporated into the contract documents by reference.
4. The Contractor shall obtain all required permits prior to construction.
5. The Contractor shall notify all utility companies at least forty eight (48) hours prior to start of construction, demolition and/or excavation in accordance with Florida Statutes.
6. The Contractor shall call Sunshine 811, previously known as Sunshine State One Call of Florida, at 1-800-432-4770 or 811, a minimum of two (2) days and a maximum of five (5) days prior to start of construction.
7. Locations, elevations and dimensions of existing utilities, structures and other features are shown according to the best information available at the time of the preparation of these plans, but do not purport to be absolutely correct. The Contractor shall verify the location, elevations and dimensions of all existing utilities, structures and other features affecting the work prior to construction.
8. The Contractor shall be responsible to review the site to determine existing conditions. Anything not shown on these plans shall be brought to the attention of the City's Engineering Representative and shall not constitute additional scope of work unless approved by the Engineer.
9. The Contractor shall contact the City's Engineering Representative immediately concerning any conflicts arising during construction.
10. All construction activities must conform to the local noise ordinance.
11. Hours of work shall be in accordance with the local governmental agency.
12. These drawings do not include necessary components for construction safety. The Contractor is solely responsible for construction safety. Special precautions may be required in the vicinity of power lines and other utilities.
13. The Contractor shall furnish, erect and maintain all necessary traffic control and safety devices in accordance with the U.S. Department of Transportation, “Manual on Uniform Traffic Control Devices” and the latest Florida Department of Transportation “Design Standards”.
14. The Contractor shall provide, erect and maintain effective barricades, danger signals, signs and pedestrian detours in all areas where required for the protection of the work and the safety of the public.
15. Maintenance of Traffic (MOT): if it becomes necessary for the Contractor to close any street to through traffic within the limits of construction, access for local traffic with destination within the project limits of construction shall be maintained. If during construction, access for local traffic is changed, the property owners affected shall be given at least three (3) days advance notice. The Contractor shall submit to the City's Engineering Representative the Traffic Control Plan for approval prior to implementation.
16. A registered Land Surveyor, at the Contractor's expense, shall reset all section corners or property corners dislocated or disturbed by any construction related activities.
17. Any National Geodetic Survey (NGS) Monument within the limits of construction is to be protected. If in danger of damage, contractor shall notify the city's field representative immediately and contact the National Geodetic Survey information center.
18. Unless noted on the plans, final grade is to generally be the same as existing grade. Restore uniformly and for proper yard drainage grade toward roadway.
19. All new utilities shall be installed with the minimum thirty six (36) inches of cover.
20. Where utilities cross the lowest pipe shall be installed first.
21. The Contractor shall be responsible for testing of all newly constructed utilities in accordance with current standards of local jurisdiction. The Contractor shall notify the local jurisdiction and the Owner or an authorized representative at least forty eight (48) hours in advance of performing tests.
22. The Contractor shall provide all sheeting, shoring and bracing required to protect adjacent structures or to minimize trench width. Where a separate pay item is not provided, the cost of all sheeting and bracing required shall be included in the contract price for the item of work for which sheeting, shoring and bracing is anticipated to be required in accordance with local, state, or federal regulations for construction.
23. All concrete shall have a minimum compressive strength of 3,000 psi (28-day strength), unless otherwise noted on drawings.
24. No surfacing material is to be applied to any manhole covers, frames, valve boxes, gas drops, etc. All existing and proposed utility and storm sewer structures whose tops will be exposed within any paved area shall be adjusted so that the top surface of covers or frames shall be flush with the pavement surface.
25. Materials interfering with construction shall be disposed of as directed by the City's Engineering Representative, unless otherwise noted on plans.
26. All excess soil resulting from construction activities that is not claimed by the Owner shall become the property of the Contractor and disposed of by the Contractor.
27. All disturbed landscaped and/or grassed areas shall be restored uniformly and be generally at the same elevation as existing grades.
28. All disturbed areas shall be replaced within fifteen (15) days to a condition equal to or better than existing conditions.
29. All voids after placement of sod shall be filled with prepared soil mix. The sod shall be rolled to meet the proposed grades. Sod placed on slopes 3:1 or steeper shall be pegged.
30. Areas of exposed earth resulting from construction shall be sodded in kind as directed by the City's Engineering Representative unless otherwise noted on plans.
31. The Contractor shall maintain an accurate set of marked-up drawings (As-Builts) at the construction site.
32. A CCTV inspection of the new sewer system in digital format utilizing the industry standard Pipeline Assessment and Certification Program (PACP) coding system shall be provided to the City. The video shall be taken prior to placing the new sewer system into service. Data will be collected utilizing CUES Granite software.
33. Installation of gravity sewer pipe shall be in conformance with recommended practices contained in Standard Practice for Underground Installation of Thermoplastic Pipe for Sewers and Other Gravity-Flow Applications ASTM D2321. Connections to manholes with sanitary pipe shall use a joint two (2) feet in length and shall use an approved water stop around pipe joint entry.
34. The bottom trench width in an unsupported trench shall be limited to the minimum practicable width allowing working space to place and compact the hunching material. The use of trench boxes and movable sheeting shall be performed in such a manner that removal, backfill and compaction will not disturb compacted haunching material or pipe alignment. Dewatering of the trench bottom shall be accomplished using adequate means to allow preparation of bedding, placement of the haunching material and pipe in the trench without standing water. Dewatering shall continue until sufficient backfill is placed above the pipe to prevent flotation or misalignment.
35. The Contractor shall dispose of all unsuitable materials, construction debris, and other waste materials offsite in accordance with applicable regulatory agency requirements at the Contractor's expense. All backfill shall be free of unsuitable materials.
36. The Contractor shall be responsible for providing a Hurricane Preparation Plan to the City's Engineering Representative for review and approval prior to commencing construction activities.
37. Any damage to city, county, or state roads caused by the Contractor shall be repaired by the Contractor in a timely manner and to the satisfaction of the City's Engineering Representative. Payment shall not be made for this work.
38. The Contractor shall protect private property.
SURVEY NOTES
1. The City of Clearwater Control Network's Horizontal Datum is: North American Datum (N.A.D.), Florida State Plane Coordinates, Florida West Zone 83(1999).
2. The City of Clearwater Control Network's Vertical Datum is: North American Vertical Datum (N.A.V.D.) 1988.
3. The survey was provided by the City of Clearwater Land Survey Division. The last date of field survey is January 2016.
TREE PROTECTION
1. The Contractor will be responsible for adhering to all Tree Protection measures required by the City of Clearwater codes, ordinances and Standard Specifications. This will include all tree barricades, root pruning and tree trimming/pruning activities. These requirements will apply within the specified “limits of work” and will also be applicable in all areas where the Contractor and/or his subcontractors stage, store or park vehicles, equipment, materials and debris.
2. All tree pruning and/or root pruning on existing trees to be preserved will only be performed by or under the direct supervision of an International Society of Arboriculture (ISA) Certified Arborist. Furthermore, all tree work shall conform to the American National Standards Institute (ANSI) 2001, American National Standard for Tree Care Operations - Tree, Shrub and Other Woody Plant Maintenance - Standard Practices (Pruning) ANSI A-300.
3. Where called for on the plans, install tree barricades, erosion control/silt fencing or other approved protective barriers around all trees to be preserved, per City Standard Detail. Where applicable, and specifically approved by the City's Engineering Representative protective barriers may be placed in root prune trenches.
4. Prior to any field changes taking place, it will be the Contractor's responsibility to review the potential impacts to existing trees with his Certified Arborist, and include any and all recommended tree protection measures in his proposal to modify the approved design. The City's Engineering Representative must approve, in writing, any changes to the approved design prior to implementation of said change.
5. The Contractor will avoid any open excavations, fill or other construction activities whenever possible within the “critical root zone” of any existing tree (i.e., under the drip line/canopy).
6. No vehicles, equipment or materials shall be parked or stored under/within the drip line/protective barrier area of any tree.
7. Where construction activities are anticipated to last for an extended period of time near existing trees, the Contractor shall install and maintain City approved tree barricades as shown in the Standard Details and as approved by the City's Engineering Representative.
8. Woodchips, mulch or another cushioning surface material approved by the City's Engineering Representative shall be placed to a minimum depth of ten (10) inches over areas where roots are present and construction traffic occurs.
9. All tree protection measures shall remain in place at all times during construction until the City's Engineering Representative authorizes removal.
10. The Contractor will coordinate with the City's Engineering Representative, Tim Kurtz, at (727) 562-4737, to obtain approval in advance of any and all work within the critical root zone of any existing tree.
SEDIMENT & EROSION CONTROL
1. It is the responsibility of the Contractor to control and prevent erosion and the transportation of sediment to surface drains and outfalls.
2. The Contractor shall prepare and submit a Stormwater Pollution Prevention Plan (SWPPP) in accordance with Florida Department of Environmental Protection (FDEP) Criteria for a National Pollution Discharge Elimination System (NPDES) Activities Permit.
3. The Contractor must obtain a FDEP Generic Permit for The Discharge of Produced Ground Water, if dewatering with offsite discharge will be required. The Contractor is responsible for all required preliminary water samples to satisfy the FDEP Generic Permit for the Discharge of Produced Ground Water. Sampling shall occur thirty (30) days prior to the start of dewatering.
4. Construction operations shall be carried out in such a manner that erosion and pollution shall be minimized.
The submitted SWPPP shall be complied with. All applicable federal, state, and local laws shall be complied with at all times. Please note that no hay bales are allowed on City of Clearwater projects.
ROOT PRUNING
1. Root pruning shall only be performed by or under the direct supervision of an International Society of Arboriculture (ISA) Certified Arborist.
2. Any proposed root pruning trenches shall be identified (i.e., staked or painted) on site, inspected and approved by the City's Engineering Representative prior to actual root pruning.
3. Root pruning shall be performed as far in advance of other construction activities as is feasible, but at a minimum shall be performed prior to any impacts to the soil. Associated tree protection measures should be implemented upon completion of said root pruning.
4. If there is a likelihood of excessive wind and/or rain, an exceptional care shall be taken on any root pruning activities.
5. Root pruning shall be limited to a minimum of twelve inches per one inch trunk diameter from the tree base.
Any exception must be approved by the City's Engineering Representative prior to said root pruning.
6. Roots shall be cut cleanly, as far from the trunk of the tree as possible. Root pruning shall be done to a minimum depth of eighteen (18) inches from existing grade, or to the depth of the disturbance if less than eighteen (18) inches.
7. Root pruning shall be performed using a root cutting machine designed specifically for this purpose. Alternate equipment or techniques must be approved by the City's Engineering Representative, prior to any work adjacent to trees to be preserved.
8. Root pruning shall be completed, inspected and accepted prior to the commencement of any excavation or other impacts to the critical root zones of trees to be protected.
9. Excavations in an area where root are present shall not cause the tearing or ripping of tree roots. Roots must first be cleanly severed prior to continuing with the excavation, or tunneled around to prevent damage to the root.
10. Tree roots shall not be exposed to drying out. Root ends shall be covered with native soil or burlap and kept moist until final backfill or final grades have been established.
11. When deemed appropriate (e.g. during periods of drought) the city representative may require a temporary irrigation system be utilized in the remaining critical root zones of root pruned trees.
UTILITY OWNERS
Spectrum Attention: Mr. Ted Bingham 700 Carillon Parkway, Suite 6 St. Petersburg, Florida 33716-1123 Phone: (727) 329-2847
Frontier Communications, Inc.
Attention: Mr. Chris Blauvelt
MC: FLCW5033
1280 Cleveland Street Clearwater, Florida 33782 Phone: (727) 562-1130
Wide Open West (WOW!)
FLSP2144
Attention: Mr. James Sandman - Construction Project Coordinator 3001 Gandy Boulevard North Pinellas Park, Florida 33782 Phone: (727) 239-0224 Office
Duke Energy Attention: Mr. Rico Ashley 2166 Palmetto Street, Bldg. F Clearwater, Florida 33765 Phone: (727) 562-5767 City of Clearwater
Clearwater Gas System Attention: Mr. Robert Malick 401 North Myrtle Avenue Clearwater, Florida 33755 Phone: (727) 444-8924
City of Clearwater Engineering Department - Traffic Division Attention: Annabella C. Hullen, P.E.
100 South Myrtle Avenue, Clearwater, Florida 33756-4748 Phone: (727) 383-0932
City of Clearwater Engineering Department - Survey Division Attention: Mr. Daniel Dieter 100 South Myrtle Avenue Clearwater, Florida 33756-4748 Phone: (727) 444-8183
City of Clearwater Engineering Department - Public Utilities Attention: Mr. Michael Flanigan 1650 North Arcturas Avenue Clearwater, Florida 33755 Office: (727) 444-8878 Mobile: (727) 224-7043
City of Clearwater Engineering Department - Construction Management Attention: Mr. Steve Wasilefsky 100 South Myrtle Avenue Clearwater, Florida 33756 Phone: (727) 444-7231
GENERAL NOTES
RECORD DRAWINGS
SURVEYED BY:
APPROVED BY:
REVIEWED BY:
PROJECT ENGINEER
DRAWN BY:
DATE
DATE
REVISION BY DATE
CALL 811
SHEET NO.:
CONTRACT NO.: DATE DRAWN:
DESIGNED BY:
SURVEYED BY:
APPROVED BY
HORIZ.
DRAWN BY:
VERT.
SCALE:DWG NAME: FIELD BOOK:
CHECKED BY:
DATE
JOB NO.:
INVESTIGATE BEFORE YOU EXCAVATE
SUNSHINE STATE
ONE CALL
OF FLORIDA
www.callsunshine.com
(800) 432-4770
MIN. 48 HOURS
BEFORE YOU EXCAVATE
CITY OF CLEARWATER, FLORIDA
PUBLIC UTILITIES
100 S. MYRTLE AVE.
CLEARWATER, FL 33756
OF
RO1 CHEMICAL STORAGE AND FEED
SYSTEM IMPROVEMENTS
23-0051-UT
NA NA
04/2026 DBT
RRF SM
N/A
N/A
Mead and Hunt, Inc.
mailto:Theodore.bingham@mybrighthouse.com
DUAL-MEDIA FILTERS
F.F. EL.= 72.00
#4
CONCRETE PAD
#3 #2 #1
BAYOXIDE
FILTERS
FUTURE
BUILDING
EXTENSION
20,000GAL.
BLENDING
TANK
COVERED
ENTRANCE
CHEMICAL
STORAGE AND FEED
BLENDED
WATER
PUMPSFERRIC
CHLORIDE
STORAGE
AND FEED
(ABANDONED)
SODIUM
HYPOCHLORITE
ROOM
MAINTENANCE
OFFICE
AMMONIA
BUILDING
PUMP STATION
BUILDING
FFE=70.05
WATER STORAGE TANK
VENTURI
FLOW
METER
BOOSTER
PUMP
STATION
20,00GAL
BACKWSH
HOLDING
TANK
4'-6"x2'-3" SAMPLE SHED ON 5'-6"x3'-3" CONCRETE PAD
8' ORNAMENTAL
PICKET FENCE
WELLFIELD COMMUNICATION TOWER
CONCRETE PAD
GENERATOR
ENCLOSURE
(8'-6"x25'-0")
FU
EL
T
AN
K (9
'-8 "x
'-8
DRYWELL
COMPRESSOR
REVERSE OSMOSIS
BUILDING
F.F. EL. 70.50
COMPRESSOR
ON CONC. PAD
TRANSFORMER
CANTILEVER
SLIDE GATE
STORMWATER
POND
WOOD
BRIDGE
SWALE
1 STORY MASS BUILDING
1 STORY MASS BUILDING
1 STORY MASS BUILDING
1 STORY MASS BUILDING
1 STORY MASS BUILDING
1 STORY MASS BUILDING
POOL AND DECK
STORM INLET
TOP EL = 67.45'
N THROAT EL=66.65'
S THROAT EL=66.71'
INV EL 12" CMP (W) = 64.40'
INV EL 12" PVC (S) = 65.58'
PA
LM
ET
TO
S
TR
EE
T
AS
PA
LT
P
AV
EM
EN
T
563.25’(F) 541.32(F)
1104.57’ O/A(C,F) S0010‘16"W O/A(C,F) HORIZONTAL SURVEY CONTROL LINES (TYP) SIR 5/8”
FDC LB 6707
GPS PT.
PUMP
STATION
ARSENIC TREATMENT
SYSTEM FACILITY
WATER STORAGE
TANK
FUTURE LAS
DOSING LINE
CONTRACTOR
LAYDOWN
AREA
CONTRACTOR PARKING AREA
C-001
3 21
EXISTING SITE PLAN
RECORD DRAWINGS
SURVEYED BY:
APPROVED BY:
REVIEWED BY:
PROJECT ENGINEER
DRAWN BY:
DATE
DATE
REVISION BY DATE
CALL 811
SHEET NO.:
CONTRACT NO.: DATE DRAWN:
DESIGNED BY:
SURVEYED BY:
APPROVED BY
HORIZ.
DRAWN BY:
VERT.
SCALE:DWG NAME: FIELD BOOK:
CHECKED BY:
DATE
JOB NO.:
INVESTIGATE BEFORE YOU EXCAVATE
SUNSHINE STATE
ONE CALL
OF FLORIDA
www.callsunshine.com
(800) 432-4770
MIN. 48 HOURS
BEFORE YOU EXCAVATE
CITY OF CLEARWATER, FLORIDA
PUBLIC UTILITIES
100 S. MYRTLE AVE.
CLEARWATER, FL 33756
OF
RO1 CHEMICAL STORAGE AND FEED
SYSTEM IMPROVEMENTS
23-0051-UT
NA NA
04/2026 DBT
RRF SM
N/A
N/A
Mead and Hunt, Inc.
LEGEND:
1. CHEMICAL STORAGE FEED AREA (ANTISCALANT,
HYDROFLUOROSILICIC ACID, SODIUM BISULFITE,
SODIUM HYDROXIDE)
2. CHEMICAL STORAGE AND FEED BUILDING
(AMMONIUM HYDROXIDE)
3. SODIUM HYDROXIDE FEED LINE AND INJECTION
POINT
4. CONTRACTOR LAYDOWN AREA
5. CONTRACTOR PARKING AREA
D-001
4 21
EXISTING AND DEMOLITION AMMONIUM
HYDROXIDE STORAGE AND FEED
RECORD DRAWINGS
SURVEYED BY:
APPROVED BY:
REVIEWED BY:
PROJECT ENGINEER
DRAWN BY:
DATE
DATE
REVISION BY DATE
CALL 811
SHEET NO.:
CONTRACT NO.: DATE DRAWN:
DESIGNED BY:
SURVEYED BY:
APPROVED BY
HORIZ.
DRAWN BY:
VERT.
SCALE:DWG NAME: FIELD BOOK:
CHECKED BY:
DATE
JOB NO.:
INVESTIGATE BEFORE YOU EXCAVATE
SUNSHINE STATE
ONE CALL
OF FLORIDA
www.callsunshine.com
(800) 432-4770
MIN. 48 HOURS
BEFORE YOU EXCAVATE
CITY OF CLEARWATER, FLORIDA
PUBLIC UTILITIES
100 S. MYRTLE AVE.
CLEARWATER, FL 33756
OF
RO1 CHEMICAL STORAGE AND FEED
SYSTEM IMPROVEMENTS
23-0051-UT
NA NA
04/2026 DBT
RRF SM
N/A
N/A
Mead and Hunt, Inc.
REMOVE AND DISPOSE TWO (2)
AMMONIUM HYDROXIDE TANKS
EXISTING AMMONIUM
HYDROXIDE TANKS
SALVAGE TWO (2) CHEMICAL
TRANSFER PUMPS AND VALVE BODIES
AND RETURN TO CITY. PVC PIPING
AND FITTINGS TO BE REMOVED AND
DISPOSED.
REMOVE AND DISPOSE
TWO (2) AMMONIUM
HYDROXIDE STORAGE TANKS
REMOVE AND DISPOSE
TWO (2) AMMONIA ODOR
CONTROL TANKS AND PIPING
SALVAGE TWO (2)
TRANSFER PUMPS AND
RETURN TO CITY
SALVAGE CHEMICAL SKID
AND RETURN TO CITY SALVAGE PUMP AND
RETURN TO CITY
REMOVE AND DISPOSE
AMMONIUM HYDROXIDE
DAY TANK
EXISTING AMMONIUM HYDROXIDE
AREA DEMOLITION PLAN
EXISTING AMMONIUM
HYDROXIDE TRANSFER PUMPS
NOTES:
1. CONTRACTOR TO COORDINATE WITH CITY OPERATIONS
STAFF 28 DAYS MINIMUM BEFORE STARTING DEMOLITION
2. CONTRACTOR TO INSTALL TEMPORARY LAS DOSING
SYSTEM, INCLUDING TOTES, PIPING, TUBING, ETC.;
CONNECT TO EXISTING DOSING LINE, AND COORDINATE
WITH THE CITY ON PLACING INTO SERVICE PRIOR TO
BEGINNING DEMOLITION.
3. CONTRACTOR TO PROTECT AND REUSE EXISTING CONDUIT,
LEVEL SENSORS AND TRANSMITTERS, AND SS316
UNISTRUT SUPPORTS.
4. ALL CHEMICAL PIPING, FITTINGS, AND TANKS ARE TO BE
REMOVED FROM SITE AND PROPERLY DISPOSED.
5. TRANSFER PUMPS, EXISTING DOSING PUMP SKID, AND
DOSING PUMPS TO BE CAREFULLY DISCONNECTED,
REMOVED, AND DELIVERED TO A LOCATION IDENTIFIED BY
THE CITY.
6. ALL VALVE BODIES TO BE SALVAGED AND DELIVERED TO
THE CITY UNLESS OTHERWISE DIRECTED BY THE
ENGINEER OR CITY REPRESENTATIVE.
REMOVE AND DISPOSE ONE
(1) AMMONIUM HYDROXIDE
DAY TANK
SALVAGE METERING PUMP
SALVAGE DOSING PUMP SKID AND AND
RETURN TO THE CITY. OFF-SKID PIPING
TO BE DISPOSED OF. ALL VALVE BODIES
TO BE SALVAGED AND RETURNED TO THE
CITY.EXISTING AMMONIUM HYDROXIDE
DAY TANK & PUMP SKID
FUTURE
BUILDING
EXTENSION
COVERED
ENTRANCE
GENERATOR
ENCLOSURE
(8'-6"x25'-0")
REVERSE OSMOSIS
BUILDING
F.E. EL. 70.50
D-002
5 21
SODIUM HYDROXIDE DEMOLITION PLAN
RECORD DRAWINGS
SURVEYED BY:
APPROVED BY:
REVIEWED BY:
PROJECT ENGINEER
DRAWN BY:
DATE
DATE
REVISION BY DATE
CALL 811
SHEET NO.:
CONTRACT NO.: DATE DRAWN:
DESIGNED BY:
SURVEYED BY:
APPROVED BY
HORIZ.
DRAWN BY:
VERT.
SCALE:DWG NAME: FIELD BOOK:
CHECKED BY:
DATE
JOB NO.:
INVESTIGATE BEFORE YOU EXCAVATE
SUNSHINE STATE
ONE CALL
OF FLORIDA
www.callsunshine.com
(800) 432-4770
MIN. 48 HOURS
BEFORE YOU EXCAVATE
CITY OF CLEARWATER, FLORIDA
PUBLIC UTILITIES
100 S. MYRTLE AVE.
CLEARWATER, FL 33756
OF
RO1 CHEMICAL STORAGE AND FEED
SYSTEM IMPROVEMENTS
23-0051-UT
NA NA
04/2026 DBT
RRF SM
N/A
N/A
Mead and Hunt, Inc.
NOTES:
1. CONTRACTOR SHALL COORDINATE ALL CONSTRUCTION AND DEMOLITION WITH CITY
OPERATIONS STAFF A MINIMUM OF 2 WEEKS BEFORE COMMENCING WORK.
2. CONTRACTOR TO TAKE ALL NECESSARY PRECAUTIONARY SAFETY MEASURES AND
FLUSH EXISTING LINE PRIOR TO DEMOLITION.
3. CONTRACTOR SHALL INSTALL NEW SODIUM HYDROXIDE INJECTION LINE AND QUILL OR
A TEMPORARY DOSING LINE PRIOR TO DEMOLISHING EXISTING SODIUM HYDROXIDE
INJECTION POINT.
4. CONTRACTOR TO SUBMIT AND RECEIVE APPROVAL OF SEQUENCE CONSTRUCTION TO
ENSURE SODIUM HYDROXIDE INJECTION IS BEING DOSED AT ALL TIMES PRIOR TO
STARTING WORK
5. CONTRACTOR TO REMOVE FLUSH AND DISPOSE OF EXISTING SODIUM HYDROXIDE
INJECTION LINE ONCE NEW LINE IS IN SERVICE.
6. CONTRACTOR MAY REUSE EXISTING SADDLE FOR ABANDONED INJECTION POINT AND
PERMANENTLY SEAL CONNECTION USING PLUG, WELDED CAP, OR OTHER CONNECTION
ACCEPTABLE TO THE CITY. THREADED CONNECTIONS WILL NOT BE ACCEPTED.
7. CONTRACTOR TO REMOVE AND DISPOSED OF EXISTING SODIUM HYDROXIDE VALVES
UNLESS OTHERWISE DIRECTED BY THE CITY OR ENGINEER.
8. CONTRACTOR MAY REUSE PIPE SUPPORT HANGERS UPON INSPECTION AND
APPROVAL BY THE ENGINEER
EXISTING SODIUM
HYDROXIDE
INJECTION POINT
EXISTING SODIUM HYDROXIDE
INJECTION POINT AND
CONTAINMENT
APPROXIMATE LOCATION
OF INJECTION POINT
EXISTING SODIUM HYDROXIDE
DOSING LINE TO BE REMOVED
REMOVE EXISTING SODIUM
HYDROXIDE DOSING LINE,
INSULATION, AND CONTAINMENT.
REMOVE EXISTING SODIUM HYDROXIDE PIPING
AND INSULATION. STRUT SUPPORTS TO BE
REPLACED TO ACCOMMODATE NEW PIPING.
REMOVE EXISTING SODIUM
HYDROXIDE PIPING AND
INSULATION. STRUT
SUPPORTS TO BE REPLACED
TO ACCOMMODATE NEW
PIPING.
EXISTING SODIUM HYDROXIDE
DOSING LINE PLAN VIEW
EXISTING SODIUM HYDROXIDE
DOSING LINE ROUTING
M-001
6 22
PROPOSED LIQUID AMMONIUM SULFATE (LAS) LAYOUT
RECORD DRAWINGS
SURVEYED BY:
APPROVED BY:
REVIEWED BY:
PROJECT ENGINEER
DRAWN BY:
DATE
DATE
REVISION BY DATE
CALL 811
SHEET NO.:
CONTRACT NO.: DATE DRAWN:
DESIGNED BY:
SURVEYED BY:
APPROVED BY
HORIZ.
DRAWN BY:
VERT.
SCALE:DWG NAME: FIELD BOOK:
CHECKED BY:
DATE
JOB NO.:
INVESTIGATE BEFORE YOU EXCAVATE
SUNSHINE STATE
ONE CALL
OF FLORIDA
www.callsunshine.com
(800) 432-4770
MIN. 48 HOURS
BEFORE YOU EXCAVATE
CITY OF CLEARWATER, FLORIDA
PUBLIC UTILITIES
100 S. MYRTLE AVE.
CLEARWATER, FL 33756
OF
RO1 CHEMICAL STORAGE AND FEED
SYSTEM IMPROVEMENTS
23-0051-UT
NA NA
04/2026 DBT
RRF SM
N/A
N/A
Mead and Hunt, Inc.
CONTROL
PANEL
FENCE GATE
OPENING
SAFETY
SHOWER
ALL CONCRETE FLOOR AND
CONTAINMENT WALL SURFACES
TO BE PREPPED AND COATED
ACCORDING TO SPECIFICATION
09 96 00
PROPOSED SEQUENCE OF CONSTRUCTION:
1. CONTRACTOR TO FURNISH AND INSTALL A TEMPORARY LAS
DOSING SYSTEM IN EXISTING FERRIC CHLORIDE STORAGE
AND FEED AREA.
2. CONTRACTOR TO COORDINATE WITH CITY OPERATIONAL
STAFF AND PLACE TEMPORARY SYSTEM ON-LINE PRIOR TO
COMMENCING WORK IN EXISTING AMMONIA AREA
3. CONTRACTOR TO REMOVE EXISTING STORAGE TANKS,
TRANSFER PUMPS, DOSING PUMP SKID, AND
INTERCONNECTING PIPING
4. CONTRACTOR TO SALVAGE AND PROTECT LEVEL
INSTRUMENTATION AND CONTROL PANEL
5. ALL FLOOR AND CONTAINMENT WALL SURFACES TO BE
CLEANED, PREPPED, AND COATED ACCORDING TO
SPECIFICATION 09 96 00. TOPCOAT COLORS TO BE
SUBMITTED TO THE ENGINEER FOR SELECTION.
6. NEW LAS STORAGE AND DAY TANKS TO BE INSTALLED IN
ACCORDANCE WITH THE SPECIFICATIONS AND
MANUFACTURER'S REQUIREMENTS. REFER TO SHEETS
M-003 & M-004 FOR NOZZLE ORIENTATIONS.
7. NEW LAS DOSING SKID AND CHEMICAL TRANSFER PUMPS TO
BE INSTALLED IN ACCORDANCE WITH THE SPECIFICATIONS
AND MANUFACTURER'S REQUIREMENTS
8. NEW LOADING, VENT, AND INTERCONNECTING PIPING AND
TUBING, AND CONDUIT TO BE INSTALLED IN ACCORDANCE
WITH THE SPECIFICATIONS AND MANUFACTURER'S
REQUIREMENTS
9. LEVEL INSTRUMENTATION TO BE REINSTALLED AND
CALIBRATED TO NEW TANKS
10.NEW LEVEL SWITCH TO BE INSTALLED IN CHEMICAL SUMP.
SUMP TO BE COVERED WITH NEW FRP GRATING
11.NEW ALARM BEACON TO BE INSTALLED AND INTEGRATED
WITH PLANT SCADA ALARM SYSTEM
12.SUCTION LINE TO BE SLOPED DOWN TO PUMPS. SLOPE TO
BE 0.5%.
13.OVERHEAD PIPING NOT SHOWN FOR CLARITY. CONTRACTOR
MAY REUSE OVERHEAD ANCHORS AND SUPPORTS IF THEY
ARE IN GOOD CONDITION AS DEEMED BY THE ENGINEER.
14.TANK TIE-DOWNS TO BE SUPPLIED BY THE TANK
MANUFACTURER AND INSTALLED PER MANUFACTURER'S
RECOMMENDATIONS.
15.STRAINER ASSEMBLY TO BE ADDED TO COMBINED SUCTION
LINE TO TRANSFER PUMPS. SEE DETAIL C ON SHEET M-002
FOR STRAINER DETAIL.
ONE (1) DUPLEX
PUMP SKID
SUCTION LINE TO
DOSING PUMP SKID
ONE (1) 65 GAL DAY TANK
(SEE SHEET M-004 FOR
DETAILS)
TWO (2) 405 GAL STORAGE
TANKS (SEE M-003 FOR TANK
DETAILS)
TWO (2)
TRANSFER
PUMPS
4" SCH80 PVC TANK VENT
W/ SS316 INSECT SCREEN
4" SCH80 PVC TANK VENT
W/ SS316 INSECT SCREEN
EXISTING LEVEL
INDICATOR PANEL
EXISTING LEVEL
INDICATOR PANEL
1-1/2" BALL
VALVE
2" BALL VALVE
2" TYPE 57 BUTTERFLY
VALVE
2" TYPE 57
BUTTERFLY
VALVE
SUCTION LINE TO
TRANSFER PUMPS
A M-002
FLEXIBLE PIPE OR
BELLOWS
FLEXIBLE PIPE
OR BELLOWS
LAS CHEMICAL AREA
3/4 = 1'-0"
BAR SCALE
0 6" 1' 2'
PIPE TO TUBING
TRANSITION BOX
2" SCH80 PVC TANK VENT
ROUTED TO OUTSIDE
CONTAINMENT AREA
W/ SS316 INSECT SCREEN
10" x 10" x 40"
CONCRETE
PEDESTAL
REVERSE FLOAT
SS316 PIPE
SUPPORT
SS316 PIPE
SUPPORTS
REVERSE FLOAT
STRAINER
ASSEMBLY
CONNECTION FOR
FUTURE DOSING SKID
24" x 24" CONTAINMENT WITH 4" x 4" WALL.
CONTAINMENT FLOOR AND WALLS TO BE
COATED PER 09 96 00
2" CAMLOCK QUICK
CONNECT HOSE FITTING
SS316 PIPE CLAMP AND
EXPANSION BOLTS
B M-002
M-002
7 22
PROPOSED LAS SECTIONS
RECORD DRAWINGS
SURVEYED BY:
APPROVED BY:
REVIEWED BY:
PROJECT ENGINEER
DRAWN BY:
DATE
DATE
REVISION BY DATE
CALL 811
SHEET NO.:
CONTRACT NO.: DATE DRAWN:
DESIGNED BY:
SURVEYED BY:
APPROVED BY
HORIZ.
DRAWN BY:
VERT.
SCALE:DWG NAME: FIELD BOOK:
CHECKED BY:
DATE
JOB NO.:
INVESTIGATE BEFORE YOU EXCAVATE
SUNSHINE STATE
ONE CALL
OF FLORIDA
www.callsunshine.com
(800) 432-4770
MIN. 48 HOURS
BEFORE YOU EXCAVATE
CITY OF CLEARWATER, FLORIDA
PUBLIC UTILITIES
100 S. MYRTLE AVE.
CLEARWATER, FL 33756
OF
RO1 CHEMICAL STORAGE AND FEED
SYSTEM IMPROVEMENTS
23-0051-UT
NA NA
04/2026 DBT
RRF SM
N/A
N/A
Mead and Hunt, Inc.
CONNECT TO
TANK
RETURN LINE
TO TK-01
RECONNECT LEVEL
SENSOR ONCE TANK IS
INSTALLED
405 GAL STORAGE
TANK (SEE M-003
FOR TANK DETAILS)
TWO (2) TRANSFER
PUMPS
EXISTING LEVEL
INDICATOR PANEL
1" BALL CHECK
1" BALL VALVE
2" SCH80 PIPE
TO DAY TANK
2" BALL VALVE
CONNECT VENT LINE AND ROUTE TO
OUTSIDE CHEMICAL AREA
FILL LINE FROM TANKER
TRUCK
RETURN LINE FROM
TRANSFER PUMPS
LAS TANK
TK-02
2" TEE ROTATED UP AT
~45° ANGLE
SS316 SUPPORT
STRUT
2" SCH80
PVC PIPE
1" BACK
PRESSURE
VALVE
SS316 SUPPORT CLAMP
TANK FILL PIPING DETAIL
NTS
SECTION A - CHEMICAL TANK AND
TRANSFER PUMP FACE PIPING
NTS
PRESSURE GAUGE
WITH DIAPHRAGM
SEAL
Y-STRAINER CONFIGURATION DETAIL
NTS
SS316 PIPE SUPPORT
(SEE NOTE 12)
2" BALL VALVE
SECTION B - TANK FILL CONNECTION
NTS
4" CHAMFER ALL
AROUND TOP OF
PEDISTAL
#3 TIES @ 12" OC(4) #4 ADHESIVE DOWELS,
EQ SPACED, EMBED 3-1/2"
6" CONCRETE BASE
WITH WELDED WIRE
MESH 2" FROM BOTTOM
90° ELBOW
NOTES:
1. Y STRAINER TO BE MOUNTED IN CONFIGURATION SHOWN
2. CONTRACTOR TO MOUNT Y STRAINER WITH MINIMUM 6"
CLEARANCE FROM FLOOR OR OTHER OBSTRUCTIONS
3. VALVES, FITTINGS, AND STRAINER MATERIAL TO MATCH
PIPING MATERIAL UNLESS OTHERWISE NOTED
BALL VALVE
Y-STRAINER
M-003
8 21
PROPOSED LIQUID AMMONIUM SULFATE (LAS)
RECORD DRAWINGS
SURVEYED BY:
APPROVED BY:
REVIEWED BY:
PROJECT ENGINEER
DRAWN BY:
DATE
DATE
REVISION BY DATE
CALL 811
SHEET NO.:
CONTRACT NO.: DATE DRAWN:
DESIGNED BY:
SURVEYED BY:
APPROVED BY
HORIZ.
DRAWN BY:
VERT.
SCALE:DWG NAME: FIELD BOOK:
CHECKED BY:
DATE
JOB NO.:
INVESTIGATE BEFORE YOU EXCAVATE
SUNSHINE STATE
ONE CALL
OF FLORIDA
www.callsunshine.com
(800) 432-4770
MIN. 48 HOURS
BEFORE YOU EXCAVATE
CITY OF CLEARWATER, FLORIDA
PUBLIC UTILITIES
100 S. MYRTLE AVE.
CLEARWATER, FL 33756
OF
RO1 CHEMICAL STORAGE AND FEED
SYSTEM IMPROVEMENTS
23-0051-UT
NA NA
04/2026 DBT
RRF SM
N/A
N/A
Mead and Hunt, Inc.
NOTES:
1. INSTALLER MUST NOT ALLOW CONTINUOUS WEIGHT ON THE TANK AND ITS
FITTINGS. ALL PIPE, VALVES, AND ACCESSORIES TO BE SUPPORTED FROM
THE GROUND OR SEPARATE STRUCTURE.
2. DO NOT CONNECT ANY PIPING TO THE TANK THAT IS NOT FREE TO MOVE
FOR EXPANSION OR CONTRACTION.
3. ALL PIPING CONNECTIONS BOLTED TO THE TANK TO BE TORQUED TO NO
MORE THAN THE MANUFACTURER REQUIREMENTS.
4. TANK TO BE ISOLATED FROM ANY VIBRATION SOURCE USING ISOLATION
DEVICES, E.G. EXPANSION JOINTS.
5. LOCATE FITTINGS FROM PLAN VIEW.
6. TANK(S) MUST BE INSTALLED PER TANK MANUFACTURER'S USAGE &
GUIDELINES.
7. TANKS TO BE BUILT PER ASTM D 1998.
8. TANKS SHALL BE HIGH-DENSITY POLYETHYLENE TANKS
9. ALL FLANGES TO BE FACTORY INSTALLED.
10. WASHERS TO BE USED TO PROTECT PLASTIC FITTINGS AND FLANGES
11. PIPING IS NOT TO BE INSTALLED UNTIL TANKS ARE SET AND SECURED IN
THEIR PERMANENT LOCATION.
12. HOUSEKEEPING PADS TO BE INSPECTED AND APPROVED BY TANK VENDOR
PRIOR TO INSTALLATION OF TANKS.
13. TANK VENDOR TO CONFIRM SIZE AND PROJECTION OF ALL TANK
CONNECTIONS.
M-004
9 21
PROPOSED LIQUID AMMONIUM SULFATE (LAS)
RECORD DRAWINGS
SURVEYED BY:
APPROVED BY:
REVIEWED BY:
PROJECT ENGINEER
DRAWN BY:
DATE
DATE
REVISION BY DATE
CALL 811
SHEET NO.:
CONTRACT NO.: DATE DRAWN:
DESIGNED BY:
SURVEYED BY:
APPROVED BY
HORIZ.
DRAWN BY:
VERT.
SCALE:DWG NAME: FIELD BOOK:
CHECKED BY:
DATE
JOB NO.:
INVESTIGATE BEFORE YOU EXCAVATE
SUNSHINE STATE
ONE CALL
OF FLORIDA
www.callsunshine.com
(800) 432-4770
MIN. 48 HOURS
BEFORE YOU EXCAVATE
CITY OF CLEARWATER, FLORIDA
PUBLIC UTILITIES
100 S. MYRTLE AVE.
CLEARWATER, FL 33756
OF
RO1 CHEMICAL STORAGE AND FEED
SYSTEM IMPROVEMENTS
23-0051-UT
NA NA
04/2026 DBT
RRF SM
N/A
N/A
Mead and Hunt, Inc.
NOTES:
1. INSTALLER MUST NOT ALLOW CONTINUOUS WEIGHT ON THE TANK AND ITS
FITTINGS. ALL PIPE, VALVES, AND ACCESSORIES TO BE SUPPORTED FROM
THE GROUND OR SEPARATE STRUCTURE.
2. DO NOT CONNECT ANY PIPING TO THE TANK THAT IS NOT FREE TO MOVE
FOR EXPANSION OR CONTRACTION.
3. ALL PIPING CONNECTIONS BOLTED TO THE TANK TO BE TORQUED TO NO
MORE THAN THE MANUFACTURER REQUIREMENTS.
4. TANK TO BE ISOLATED FROM ANY VIBRATION SOURCE USING ISOLATION
DEVICES, E.G. EXPANSION JOINTS.
5. LOCATE FITTINGS FROM PLAN VIEW.
6. TANK(S) MUST BE INSTALLED PER TANK MANUFACTURER'S USAGE &
GUIDELINES.
7. TANKS TO BE BUILT PER ASTM D 1998.
8. TANKS SHALL BE HIGH-DENSITY POLYETHYLENE TANKS
9. ALL FLANGES TO BE FACTORY INSTALLED.
10. WASHERS TO BE USED TO PROTECT PLASTIC FITTINGS AND FLANGES
11. PIPING IS NOT TO BE INSTALLED UNTIL TANKS ARE SET AND SECURED IN
THEIR PERMANENT LOCATION.
12. HOUSEKEEPING PADS TO BE INSPECTED AND APPROVED BY TANK VENDOR
PRIOR TO INSTALLATION OF TANKS.
13. TANK VENDOR TO CONFIRM SIZE AND PROJECTION OF ALL TANK
CONNECTIONS.
FUTURE
BUILDING
EXTENSION
20,000GAL.
BLENDING
TANK
COVERED
ENTRANCE
BLENDED
WATER
PUMPS
GENERATOR
ENCLOSURE
(8'-6"x25'-0")
FU
EL
T
AN
K (9
'-8 "x
'-8
DRYER
COMPRESSOR
REVERSE OSMOSIS
BUILDING
F.E. EL. 70.50
EXIST. 20'x10'
CONCRETE PAD
21.5'x8' CONC.
LANDING
DRYWELL
COMPRESSOR
ON CONC. PAD
M-005
10 21
PROPOSED SODIUM HYDROXIDE INJECTION POINT
RECORD DRAWINGS
SURVEYED BY:
APPROVED BY:
REVIEWED BY:
PROJECT ENGINEER
DRAWN BY:
DATE
DATE
REVISION BY DATE
CALL 811
SHEET NO.:
CONTRACT NO.: DATE DRAWN:
DESIGNED BY:
SURVEYED BY:
APPROVED BY
HORIZ.
DRAWN BY:
VERT.
SCALE:DWG NAME: FIELD BOOK:
CHECKED BY:
DATE
JOB NO.:
INVESTIGATE BEFORE YOU EXCAVATE
SUNSHINE STATE
ONE CALL
OF FLORIDA
www.callsunshine.com
(800) 432-4770
MIN. 48 HOURS
BEFORE YOU EXCAVATE
CITY OF CLEARWATER, FLORIDA
PUBLIC UTILITIES
100 S. MYRTLE AVE.
CLEARWATER, FL 33756
OF
RO1 CHEMICAL STORAGE AND FEED
SYSTEM IMPROVEMENTS
23-0051-UT
NA NA
04/2026 DBT
RRF SM
N/A
N/A
Mead and Hunt, Inc.
NOTES:
1. CONTRACTOR TO INSTALL INSULATION AROUND CASING PIPE
2. CONTRACTOR WILL BE RESPONSIBLE FOR RELOCATING ALL
EXISTING EQUIPMENT NECESSARY FOR NEW INJECTION QUILL
LOCATION.
NEW CAUSTIC INJECTION LINE
AND INJECTION QUILL INTO EXISTING
VERTICAL PERMEATE PIPE
CONTRACTOR TO INSTALL NEW
SODIUM HYDROXIDE INJECTION
QUILL IN SAFETY ENCLOSURE
48" ABOVE FLOOR
A M-
CAUSTIC INJECTION - PLAN VIEW
NTS
B M-
C M-006
PROPOSED CAUSTIC INJECTION POINT
NTS
M-006
11 21
PROPOSED SODIUM HYDROXIDE INJECTION POINT
RECORD DRAWINGS
SURVEYED BY:
APPROVED BY:
REVIEWED BY:
PROJECT ENGINEER
DRAWN BY:
DATE
DATE
REVISION BY DATE
CALL 811
SHEET NO.:
CONTRACT NO.: DATE DRAWN:
DESIGNED BY:
SURVEYED BY:
APPROVED BY
HORIZ.
DRAWN BY:
VERT.
SCALE:DWG NAME: FIELD BOOK:
CHECKED BY:
DATE
JOB NO.:
INVESTIGATE BEFORE YOU EXCAVATE
SUNSHINE STATE
ONE CALL
OF FLORIDA
www.callsunshine.com
(800) 432-4770
MIN. 48 HOURS
BEFORE YOU EXCAVATE
CITY OF CLEARWATER, FLORIDA
PUBLIC UTILITIES
100 S. MYRTLE AVE.
CLEARWATER, FL 33756
OF
RO1 CHEMICAL STORAGE AND FEED
SYSTEM IMPROVEMENTS
23-0051-UT
NA NA
04/2026 DBT
RRF SM
N/A
N/A
Mead and Hunt, Inc.
NOTES:
1. EXISTING SUPPORTS TO BE INSPECTED BY ENGINEER AND APPROVED FOR REUSE PRIOR TO
REINSTALLING
2. CONTRACTOR TO INSTALL NEW SS316 PIPE SUPPORTS WHERE REQUIRED FOR NEW ROUTING
3. MAX SPACING FOR 4" PVC PIPE IS AS FOLLOWS: 4' FOR HORIZONTAL HANGERS, 10' FOR VERTICAL
SUPPORTS
4. CONTRACTOR TO INSTALL NEW FIBERGLASS INSULATION WITH ADHESIVE FLAP OVER 4" CASING
PIPE. INSULATION TO BE OWENS CORNING OR EQUAL
5. LB CONDUIT BODIES TO BE INSTALLED ON CASING PIPE AT EACH CHANGE OF DIRECTION
6. 4" TEE WITH BUSHING AND 12" DRAIN VALVE TO BE INSTALLED AT EACH LOW POINT
7. 1' MIN CLEAR PVC TO BE INSTALLED AT EACH LOW POINT
8. CASING PIPE TO BE SECURED TO WALL ADJACENT TO INJECTION POINT
9. INJECTION QUILL AND ENCLOSURE TO BE INSTALLED PER MANUFACTURER'S RECOMMENDATIONS
PIPE SUPPORT STRUT. SEE
DETAIL 2 ON SHEET M-007
PIPE/TUBING CONNECTION. SEE
DETAIL 5 ON SHEET M-007
4" SCH40 PVC CASING. BOTTOM
1' MIN TO BE CLEAR PVC.
4"x1
2" BUSHING WITH 12"
DRAIN VALVE
SECTION A - CONNECTION TO
NEW CASED TUBING
NTS
EXISTING CHEMICAL FEED
LINES TO REMAIN
4" LB PVC CONDUIT BODY FOR
PULLING TUBING
PIPE SUPPORT HANGER. SEE
DETAILS 13 & 14 ON SHEET M-008
12"x4" SADDLE WITH 4"x3
4" BUSHING
INJECTION QUILL ENCLOSURE. SEE
DETAILS 15 & 16 ON SHEET M-008
SECTION B - CHANGE OF DIRECTION
OF CASING PIPE
NTS
SECTION C - CHEMICAL INJECTION POINT
NTS
INJECTION POINT TO BE
INSTALLED 48" ABOVE FLOOR
4" SCH40 PVC WITH
INSULATION
A
C D
A
6"
M-007
12 21
MECHANICAL DETAILS
RECORD DRAWINGS
SURVEYED BY:
APPROVED BY:
REVIEWED BY:
PROJECT ENGINEER
DRAWN BY:
DATE
DATE
REVISION BY DATE
CALL 811
SHEET NO.:
CONTRACT NO.: DATE DRAWN:
DESIGNED BY:
SURVEYED BY:
APPROVED BY
HORIZ.
DRAWN BY:
VERT.
SCALE:DWG NAME: FIELD BOOK:
CHECKED BY:
DATE
JOB NO.:
INVESTIGATE BEFORE YOU EXCAVATE
SUNSHINE STATE
ONE CALL
OF FLORIDA
www.callsunshine.com
(800) 432-4770
MIN. 48 HOURS
BEFORE YOU EXCAVATE
CITY OF CLEARWATER, FLORIDA
PUBLIC UTILITIES
100 S. MYRTLE AVE.
CLEARWATER, FL 33756
OF
RO1 CHEMICAL STORAGE AND FEED
SYSTEM IMPROVEMENTS
23-0051-UT
NA NA
04/2026 DBT
RRF SM
N/A
N/A
Mead and Hunt, Inc.
STRUT FITTING - SQUARE POST BASE3 N.T.S.
NON-METALLIC PIPE SUPPORT STANCHION4 N.T.S.
FRP PIPE CLAMP
HEAVY DUTY CHANNEL.
AICKINSTRUT 20V-2000
OR EQUAL
AICKINSTRUT
50PU-2636 CHANNEL
FITTINGS OR EQUAL AICKINSTRUT 20V-2000
CHANNEL OR EQUAL
ARRANGED
BACK-TO-BACK
AICKINSTRUT POST BASE
20PU-5904 OR EQUAL. MOUNT
WITH 12" DIA x 6" SS316
EXPANSION ANCHORS
NOTES:
1. UNISTRUT STAND SUPPORT MATERIAL TO BE SS316
UNLESS OTHERWISE SPECIFIED
2. MINIMUM SUPPORT HEIGHT TO BE 3-1/2"
3. SUPPORT TO BE FASTENED TO CONCRETE FLOOR
USING 12" x 6" ss316 ANCHORS
4. WASHERS AND NUTS TO BE SS316
EXISTING CONCRETE OR
MASONRY WALL, FLOOR
OR CEILING
NON-METALLIC PIPE CLAMS.
AICKINCLAMP 200-3100 CLAMPS
WITH STOP LOCKS OR EQUAL.
CLAMPS TO BE FASTENED PER
MANUFACTURER'S EQUIREMENTS.
NOTES:
1. PROVIDE PVC SLEEVE AROUND INSULATION FOR
INSULATED PIPE
2. STRUT TO BE VINYL ESTER FRP FOR HYPOCHLORITE
APPLICATIONS
3. STRUT LENGTH TO ACCOMMODATE PIPES
SUPPORTED
STOP LOCK
1-5/8" HEAVY DUTY FRP CHANNEL
STRUT. AICKINSTRUT SERIES
20V-2000 OR EQUAL.
8" DIAMETER x 6" SS316
EXPANSION ANCHORS AT 2'
O.C. (MIN. 2)
STRUT TYPE PIPE SUPPORT - NON METALLIC1 N.T.S.
STRUT TYPE PIPE SUPPORT2 N.T.S.
3" MIN CLEARANCE EACH
END
8" DIAMETER x 6" SS316
EXPANSION ANCHORS
AT 2' O.C. (MIN. 2)
EXISTING CONCRETE
WALL, TRENCH, OR
SLAB STOP LOCK ASSEMBLY.
AICKINSTRUT 200-4219 OR
EQUAL
SS316 LOAD BEARING
STRUT CLAMP
CHANNEL FRAMING.
AICKINSTRUT 20P-1500 OR
EQUAL
3" MIN EDGE TO EDGE
SEPARATION (PIPE
DIAMETER 4" AND SMALLER)
6" MIN EDGE TO EDGE
SEPARATION (PIPE
DIAMETER 5" AND LARGER)
NOTES:
1. PIPE SIZE TO BE AS INDICATED IN THE DRAWINGS (8"
MAX PIPE SIZE)
2. NUMBER OF PIPES SUPPORTED TO BE AS INDICATED
IN THE DRAWINGS
3. SUPPORT CHANNEL THE BE SS316 OR FRP AS
INDICATED IN THE DRAWINGS AND AS APPROPRIATE
FOR SERVICE
4. SUPPORT CHANNES AND ACCESSORIES FOR
HYPOCHLORITE SERVICE TO BE VINYL ESTER FRP
CHEMICAL FEED PIPE/TUBE TRANSITION5 N.T.S.
3" OR 4" PVC SOCKET END CAP.
DRILL HOLE(S) THROUGH CENTER
FOR FLEXIBLE CHEMICAL TUBING
PFA TUBING
ADAPTER
FNPT PVC
ADAPTER
PFA CARRIER
TUBING4" SCH80 PVC (OR AS
APPROPRIATE FOR
CHEMICAL SERVICE)
CONTAINMENT PIPE
SCH80 PVC
CHEMICAL PIPE
FNPT PVC
ADAPTER
PFA TUBING
ADAPTER
PFA CARRIER
TUBING
SS316 FLANGE
BOLTS
SOLVENT WELD
SCHE80 PVC
CHEMICAL PIPE
SCH80 PVC UNION
PVC BUSHING DRILLED OUT SO
INSIDE DIAMETER IS FLUSH
ELASTOMERIC GASKET
INSTALL MINIMUM 1' SECTION OF CLEAR PVC PIPE AT LOW POINT OF PIPING.
CLEAR PVC SECTION TO BE IN AREA PROTECTED FROM SUN, OR
CONTRACTOR TO INSTALL SHADE COVER.
3" OR 4"
SCH80 PVC
PUSH-ON
FLANGE
INTERIOR TRANSITION
EXTERIOR TRANSITION
PIPE/TUBE TRANSITION BOX6 N.T.S.
CHEMICAL
CARRIER
TUBING
SLIP X MNPT
PVC ADAPTER
PFA TUBING
ADAPTER
FNPT X FNPT
PVC ADAPTER
NOTES:
1. INSTALL PTFE TAPE ON THREADED CONNECTIONS
TO ACHIEVE SEAL
2. NUT MATERIAL TO BE COMPATIBLE WITH CHEMICAL
SERVICE
3. INSTALL BUSHING ON CARRIER TRANSITION FITTING
MNPT NUTSLIP X MNPT
PVC ADAPTER
SCH40 PVC
CASING PIPE
TRANSITION BOX
DOOR
CHEMICAL CONTAINMENT PULL BOX7 N.T.S.
PLAN
SECTION
DOUBLE DOOR WATER
TIGHT HATCH, H20 LOAD
RATED COVER. HALLIDAY,
BILCO, OR EQUAL
FLEXIBLE CARRIER TUBING IN
PVC CONTAINMENT CASING PIPE
3'W x 3'L x 4'd ID
CHEMICAL
CONTAINMENT
PULL BOX
A OPENING IN CONCRETE WALL TO ACCOMMODATE DIAMETER OF PVC CONTAINMENT CASING PIPE. FILL
VOID USING NON-SHRINK GROUT
LOOP OR COIL TUBING USING AT LEAST 10% MORE THAN THE MINIMUM ALLOWABLE RADIUS BEND AND SUPPORT LOOP USING NON-METAL PIPE SUPPORTS AND PLASTIC STRAPS OR CABLE TIES. DO
NOT KINK TUBING
COAT INTERIOR OF CONCRETE SURFACES OF CHEMICAL CONTAINMENT PULL BOX WITH SYSTEM
TNEMEC SYSTEM NO.39 OR EQUAL. APPLY PER MANUFACTURER'S RECOMMENDATIONS
REFER TO DRAWINGS TO CONFIRM SIZE OF FLEXIBLE CARRIER TUBING AND CONTAINMENT PIPE
3'W x 3'L x 4'd ID PRE-CAST
CONCRETE, DESIGNED TO
RESIST FLOTATION WITH
GROUNDWATER AT SURFACE
FLEXIBLE CARRIER TUBING IN
PVC CONTAINMENT CASING PIPE
B
C
D
PROPOSED
STORAGE
TANK
M-008
13 21
MECHANICAL DETAILS
RECORD DRAWINGS
SURVEYED BY:
APPROVED BY:
REVIEWED BY:
PROJECT ENGINEER
DRAWN BY:
DATE
DATE
REVISION BY DATE
CALL 811
SHEET NO.:
CONTRACT NO.: DATE DRAWN:
DESIGNED BY:
SURVEYED BY:
APPROVED BY
HORIZ.
DRAWN BY:
VERT.
SCALE:DWG NAME: FIELD BOOK:
CHECKED BY:
DATE
JOB NO.:
INVESTIGATE BEFORE YOU EXCAVATE
SUNSHINE STATE
ONE CALL
OF FLORIDA
www.callsunshine.com
(800) 432-4770
MIN. 48 HOURS
BEFORE YOU EXCAVATE
CITY OF CLEARWATER, FLORIDA
PUBLIC UTILITIES
100 S. MYRTLE AVE.
CLEARWATER, FL 33756
OF
RO1 CHEMICAL STORAGE AND FEED
SYSTEM IMPROVEMENTS
23-0051-UT
NA NA
04/2026 DBT
RRF SM
N/A
N/A
Mead and Hunt, Inc.
TANK FILL LINE DETAIL9 N.T.S.
2" SCH80 PVC
RISER FASTENED
TO BUILDING WALL
2" SCH80 PVC FILL LINE
FROM FILL PEDESTAL
316SS PIPE SUPPORTS AT 4 FT. O.C. MIN. & EACH
BEND OR TEE. SUPPORTS TO BE KINDORF
MODULAR SUPPORT SYSTEM OR EQUAL.
2" SPA-FLEX PVC PIPE
TANK FILL/QUICK CONNECT DETAIL8 N.T.S.
PLAN
TOP VIEW
2" SCH80 PVC TO
STORAGE TANK
(TYP OF 2)
10"x 10"x 38" HIGH
CONCRETE PEDESTAL
316 S.S. PIPE CLAMP
SECURE WITH 316
S.S. EXP. BOLTS
2" "CAM-LOCK"
QUICK CONNECT
HOSE FITTING
316 S.S. PIPE CLAMP SECURE
WITH 316 (S.S. EXP. BOLTS
(TYP EACH FILL LINE)
2" SCH80 PVC BALL VALVE
(TYP EACH FILL LINE)
316 SS PIPE CLAMP SECURE
WITH 316 SS EXP BOLTS
(TYP EACH FILL LINE)
FILL PIPE SUPPORT10 N.T.S.
PVC FILL LINE
ATTACH TO MTG. ANGLE
WITH SS316 STRAPS AND
SS316 BOLTS, NUTS AND
WASHERS
SS316 ANGLE
ATTACH TO WALL WITH
SS316 EXPANSION
ANCHORS
NFPA HAZARD DIAMOND FOR LAS11 NTS
BLUE BACKGROUND
RED BACKGROUND
YELLOW BACKGROUND
WHITE BACKGROUND
10" x 10"
FIBERGLASS SIGN
2" HIGH LETTERS
"LIQUID AMMONIUM SULFATE"
DIAMOND
CHEMICAL WARNING SIGN
TO BE INSTALLED ADJACENT TO
ENTRANCE DOOR OF AMMONIA AREA
NOTE:
CHEMICAL WARNING
SIGN SHALL COMPLY
WITH NFPA 704, CHPT. 6
MASONRY WALL
APPLY 1" DEPTH OF GUN
GRADE ELASTOMERIC
SEALANT IN ANNULAR SPACE
ON BOTH SIDES OF WALL
1" NON SHRINK
GROUT
CARRIER PIPE (SEE
PLANS FOR SIZE)
1" MIN
ANNULAR
SPACE ALL
AROUND
TIGHT-PACKED LAYERS OF
EXPANDED POLYURETHANE
OR POLYURETHANE
ROPE-TYPE FILLER
SCH80 PVC SPOOL
PIECE CUT TO LENGTH
MASONRY WALL PENETRATION12 N.T.S.
CLEVIS PIPE HANGER DETAIL13 N.T.S.
SS316 ADJUSTABLE CLEVIS
PIPE HANGER. SIZE DEPENDENT
UPON PIPE SIZE AS SPECIFIED IN
THE DRAWINGS.
SS316 HANGER ROD. LENGTH TO MEET
PIPE GRAD AS SHOWN ON DRAWINGS.
DIAMETER TO BE COORDINATED WITH CLEVIS
ATTACHMENT PLATE.
UFS BEAM CLAMP
EXISTING BEAM
EXISTING
CONCRETE
CEILING
SS316 WEDGE ANCHORS.
TO BE SIZED BASED ON ROD
AND LOAD
CARBON STEEL
CONCRETE ROD
ATTACHMENT
PLATE. HOT-DIP
GALVANIZE AND
PAINT TO MATCH
CEILING. GRINNEL
FIG 52 OR EQUAL
SS316 UNISTRUT P2785 BOLT
BEAM CLAMP OR EQUAL
GAP BETWEEN ROD
AND BACK OF CHANNEL
CHANNEL NUT
SQUARE WASHER
HEX NUT
THREADED ROD
NOTES:
1. TWO (2) CLAMPS REQUIRED FOR EACH BEAM CROSSED
2. FASTEN TO MINIMUM TWO BEAMS
3. ADJUST THREADED ROD AS REQUIRED TO FOR PIPE INSTALLATION
MASONRY WALL PENETRATION14 N.T.S.
NOTES:
1. ENCLOSURE TO BE SIZED TO CONTAIN QUILL, VALVE, AND ALL ACCESSORIES.
2. ENCLOSURE MOC TO BE SS316
3. ENCLOSURE TO BE MOUNTED PER MANUFACTURER'S RECOMMENDATIONS
4. CONTRACTOR TO PROVIDE MOUNTING HARDWARE
CHEMICAL INJECTOR SAFETY ENCLOSURE15 N.T.S.
LOCK SECURELY FASTEN
INJECTOR IN CORP. STOP
316 SST BALL VALVE
W/ HANDLE OPERATOR
PERMEATE PIPE (SEE
MECHANICAL DWGS)
INSERTION LENGTH
(SEE NOTE 3)
CHAIN LOCK
MALE NPT, SIZE BY
DIFFUSER MANUFACTURER
CHEMICAL INJECTOR
INJECTOR TIP
NOTES:
1. INJECTOR SHALL BE RETRACTABLE INJECTION QUILL WITH
BALL VALVE.
2. DIFFUSER, SOLUTION TUBE, AND CONNECTIONS TO BE
SS316
3. TUBING TO BE PFA. PIPING TO BE SCH80 PVC
4. SEALS AND GASKETS TO BE VITON
5. INSERTION LENGTH SHALL BE 1/3 OF THE PROCESS PIPE
DIAMETER.
CONNECT TO EXISTING
1/2" OD CHEMICAL TUBING
CHEMICAL INJECTOR16 N.T.S.
AutoCAD SHX Text
LIQUID AMMONIUM SULFATE
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
6" MIN.
AutoCAD SHX Text
CMU WALL
E-001
14 21
LEAK DETECTION - FLUORIDE
RECORD DRAWINGS
SURVEYED BY:
APPROVED BY:
REVIEWED BY:
PROJECT ENGINEER
DRAWN BY:
DATE
DATE
REVISION BY DATE
CALL 811
SHEET NO.:
CONTRACT NO.: DATE DRAWN:
DESIGNED BY:
SURVEYED BY:
APPROVED BY
HORIZ.
DRAWN BY:
VERT.
SCALE:DWG NAME: FIELD BOOK:
CHECKED BY:
DATE
JOB NO.:
INVESTIGATE BEFORE YOU EXCAVATE
SUNSHINE STATE
ONE CALL
OF FLORIDA
www.callsunshine.com
(800) 432-4770
MIN. 48 HOURS
BEFORE YOU EXCAVATE
CITY OF CLEARWATER, FLORIDA
PUBLIC UTILITIES
100 S. MYRTLE AVE.
CLEARWATER, FL 33756
OF
RO1 CHEMICAL STORAGE AND FEED
SYSTEM IMPROVEMENTS
23-0051-UT
NA NA
03/2026 DBT
--- RF
N/A
N/A
Mead and Hunt, Inc.
4" SCH.80
PVC CONDUIT
FLUORIDE CHEMICAL SYSTEM
3/4 = 1'-0"
BAR SCALE
0 6" 1' 2'
SECTION B
NTS
SECTION C
NTS
4" FLEX
CONDUIT
CUT HOLE IN GRATING
FOR CONDUIT3
4" THREADED
PVC SCH 80 COUPLING
4" ELECTRICAL LB
CONDUIT BODY
4" SCH 80 PVC
CONDUIT
1 58" FRP UNISTRUT
ONE (1) LEVEL SWITCH 6"
CONTROL
PANEL
TRANSITION COUPLING
FROM FLEX CONDUIT TO
PVC CONDUIT 1 58" FRP UNISTRUT CLAMP
CONTAINMENT WALL AND FLOOR TO BE
COATED PER SPECIFICATION 09 96 00
SUMP
SECTION A
NTS
1 58" FRP UNISTRUT
AND CLAMP
4" SCH 80 PVC
CONDUIT
A E-
C E-
E-001
E-002
15 21
LEAK DETECTION - ANTISCALANT
RECORD DRAWINGS
SURVEYED BY:
APPROVED BY:
REVIEWED BY:
PROJECT ENGINEER
DRAWN BY:
DATE
DATE
REVISION BY DATE
CALL 811
SHEET NO.:
CONTRACT NO.: DATE DRAWN:
DESIGNED BY:
SURVEYED BY:
APPROVED BY
HORIZ.
DRAWN BY:
VERT.
SCALE:DWG NAME: FIELD BOOK:
CHECKED BY:
DATE
JOB NO.:
INVESTIGATE BEFORE YOU EXCAVATE
SUNSHINE STATE
ONE CALL
OF FLORIDA
www.callsunshine.com
(800) 432-4770
MIN. 48 HOURS
BEFORE YOU EXCAVATE
CITY OF CLEARWATER, FLORIDA
PUBLIC UTILITIES
100 S. MYRTLE AVE.
CLEARWATER, FL 33756
OF
RO1 CHEMICAL STORAGE AND FEED
SYSTEM IMPROVEMENTS
23-0051-UT
NA NA
03/2026 DBT
--- RF
N/A
N/A
Mead and Hunt, Inc.
EXISTING CONTROL
PANEL
ONE (1) LEVEL SWITCH
4" FLEX
CONDUIT
4" SCH 80
PVC CONDUIT
ANTISCALANT CHEMICAL SYSTEM
3/4 = 1'-0"
BAR SCALE
0 6" 1' 2' SECTION B
NTS
BEACON
SEE NOTE 4
TRANSITION COUPLING FROM
FLEX CONDUIT TO PVC
CONDUIT
SUMP
A E-
4" THREADED
PVC SCH 80 COUPLING
CONTAINMENT WALL AND FLOOR TO BE
COATED PER SPECIFICATION 09 96 00
1 58" SS316 UNISTRUT
AND CLAMP
4" SCH 80 PVC
CONDUIT
CUT HOLE IN GRATING
FOR CONDUIT
4" ELECTRICAL LB
CONDUIT BODY
B E-002
SECTION A
NTS
UNISTRUT STAND
SUPPORT WITH
PROTECTIVE CAP
E-003
16 21
LEAK DETECTION - SODIUM BISULFITE
RECORD DRAWINGS
SURVEYED BY:
APPROVED BY:
REVIEWED BY:
PROJECT ENGINEER
DRAWN BY:
DATE
DATE
REVISION BY DATE
CALL 811
SHEET NO.:
CONTRACT NO.: DATE DRAWN:
DESIGNED BY:
SURVEYED BY:
APPROVED BY
HORIZ.
DRAWN BY:
VERT.
SCALE:DWG NAME: FIELD BOOK:
CHECKED BY:
DATE
JOB NO.:
INVESTIGATE BEFORE YOU EXCAVATE
SUNSHINE STATE
ONE CALL
OF FLORIDA
www.callsunshine.com
(800) 432-4770
MIN. 48 HOURS
BEFORE YOU EXCAVATE
CITY OF CLEARWATER, FLORIDA
PUBLIC UTILITIES
100 S. MYRTLE AVE.
CLEARWATER, FL 33756
OF
RO1 CHEMICAL STORAGE AND FEED
SYSTEM IMPROVEMENTS
23-0051-UT
NA NA
04/2026 DBT
RRF SM
N/A
N/A
Mead and Hunt, Inc.
EXISTING
CONTROL
PANEL
4" FLEX
CONDUIT
ONE (1)
LEVEL
SWITCH
4" SCH 80
PVC CONDUIT
SODIUM BISULFITE CHEMICAL SYSTEM
3/4 = 1'-0"
BAR SCALE
0 6" 1' 2'
SECTION B
NTS
NEW
GRATTING
BEACON
SEE NOTE 4
TRANSITION COUPLING FROM
FLEX CONDUIT TO PVC
CONDUIT
NEW 1 14" FRP
GRATING
L3X3X1 4"
FRP ANGLE
8"X6" ANCHOR BOLT
FIELD VERIFY ANGLE
LOCATION HEIGHT WITH NEW
FRP GRATING
FRP SUPPORT DETAIL 1
N.T.S.
FRP SUPPORT
(SEE FRP SUPPORT DETAIL 1
THIS SHEET)
FRP SINGLE UNISTRUT
BASE
1 58" FRP UNISTRUT
FRP UNISTRUT
ANGLE CLIP (4) 3
8" HEX HEAD BOLT AND UNISTRUT
CHANNEL NUT
2'-0"
FRP SUPPORT DETAIL 2
N.T.S.
1 8"
(F
IL
ED
V
ER
IF
Y)
FRP SUPPORT
(SEE FRP SUPPORT DETAIL
2 THIS SHEET)
FRP SUPPORT (SEE FRP
SUPPORT DETAIL 2 THIS
SHEET)
4" ELECTRICAL LB
CONDUIT BODY
SUMP
CONDUIT BENDS TO AVOID
SUPPORTS
4" THREADED PVC
SCH 80 COUPLING
CONTAINMENT WALL AND FLOOR TO BE
COATED PER SPECIFICATION 09 96 00
1 58" FRP UNISTRUT
AND CLAMP
4" SCH 80 PVC
CONDUIT
CUT HOLE IN GRATING
FOR CONDUIT
SECTION A
NTS
SECTION C
NTS
A E-
B
E-003
C E-
E-004
17 21
LEAK DETECTION - SODIUM HYDROXIDE
RECORD DRAWINGS
SURVEYED BY:
APPROVED BY:
REVIEWED BY:
PROJECT ENGINEER
DRAWN BY:
DATE
DATE
REVISION BY DATE
CALL 811
SHEET NO.:
CONTRACT NO.: DATE DRAWN:
DESIGNED BY:
SURVEYED BY:
APPROVED BY
HORIZ.
DRAWN BY:
VERT.
SCALE:DWG NAME: FIELD BOOK:
CHECKED BY:
DATE
JOB NO.:
INVESTIGATE BEFORE YOU EXCAVATE
SUNSHINE STATE
ONE CALL
OF FLORIDA
www.callsunshine.com
(800) 432-4770
MIN. 48 HOURS
BEFORE YOU EXCAVATE
CITY OF CLEARWATER, FLORIDA
PUBLIC UTILITIES
100 S. MYRTLE AVE.
CLEARWATER, FL 33756
OF
RO1 CHEMICAL STORAGE AND FEED
SYSTEM IMPROVEMENTS
23-0051-UT
NA NA
04/2026 DBT
RRF SM
N/A
N/A
Mead and Hunt, Inc.
ONE (1)
LEVEL
SWITCH
4" ELECTRICAL LB
CONDUIT BODY
EXISTING
CONTROL
PANEL
4" FLEX
CONDUIT
4" SCH 80
PVC CONDUIT
TRANSITION COUPLING
FROM FLEX CONDUIT
TO PVC CONDUIT
BEACON
SEE NOTE 4
SUMP
A E-
B E-004
1 58" SS316 UNISTRUT
AND CLAMP
CUT HOLE IN GRATING FOR
CONDUIT
1 58" SS316 UNISTRUT
AND CLAMP
SECTION B
NTS
SECTION A
NTS
SODIUM HYDROXIDE CHEMICAL SYSTEM
3/4 = 1'-0"
BAR SCALE
0 6" 1' 2'
E-005
18 21
LEAK DETECTION - LIQUID AMMONIUM SULFATE
RECORD DRAWINGS
SURVEYED BY:
APPROVED BY:
REVIEWED BY:
PROJECT ENGINEER
DRAWN BY:
DATE
DATE
REVISION BY DATE
CALL 811
SHEET NO.:
CONTRACT NO.: DATE DRAWN:
DESIGNED BY:
SURVEYED BY:
APPROVED BY
HORIZ.
DRAWN BY:
VERT.
SCALE:DWG NAME: FIELD BOOK:
CHECKED BY:
DATE
JOB NO.:
INVESTIGATE BEFORE YOU EXCAVATE
SUNSHINE STATE
ONE CALL
OF FLORIDA
www.callsunshine.com
(800) 432-4770
MIN. 48 HOURS
BEFORE YOU EXCAVATE
CITY OF CLEARWATER, FLORIDA
PUBLIC UTILITIES
100 S. MYRTLE AVE.
CLEARWATER, FL 33756
OF
RO1 CHEMICAL STORAGE AND FEED
SYSTEM IMPROVEMENTS
23-0051-UT
NA NA
04/2026 DBT
RRF SM
N/A
N/A
Mead and Hunt, Inc.
4" SCH80 PVC CONDUIT
4" ELECTRICAL LB
ALARM
BEACON
LIGHT
LEVEL SWITCH
6" FROM BOTTOM OF
SUMP
CONTROL
PANEL
4" FLEX CONDUIT
FROM LB ELBOW TO
BOTTOM OF CONTROL
PANEL
1 58" SS316 UNISTRUT
EVERY 30" MAX FOR
CONDUIT SUPPORT
4" ELECTRICAL LB
CONDUIT BODY
1 58" SS316 UNISTRUT
EVERY 30" MAX FOR CONDUIT
SUPPORT
4" SCH80 PVC CONDUIT
4" FLEX CONDUIT
FROM LB ELBOW TO
BOTTOM OF CONTROL
PANEL
FENCE GATE
OPENING
SAFETY
SHOWER
PUMP SKID
DAY TANK
TWO (2) STORAGE TANKS
TWO (2)
TRANSFER
PUMPS
A E-005
ONE (1)
LEVEL
SWITCH
1 58" SS316
UNISTRUT
AND CLAMP
CUT HOLE IN GRATING FOR
CONDUIT
4" ELECTRICAL LB
CONDUIT BODY
SECTION B
NTS
SECTION A
NTS
LIQUID AMMONIUM SULFATE
STORAGE AND FEED AREA
SS316 STRUT
SUPPORT
4" ELEC. LB
BEACON LIGHT
E-005
SPARE DIGITAL INPUT:
1) 120V INPUT FOR FLUORIDE, ANTISCALANT, SODIUM
BISULFITE, SODIUM HYDROXIDE.
2) 24V DG INPUT FOR NEW LAS (OLD NH3)
LEVEL SWITCH CONNECTION DETAIL
E-006
19 22
LEAK DETECTION - LEVEL SWITCH DETAIL
RECORD DRAWINGS
SURVEYED BY:
APPROVED BY:
REVIEWED BY:
PROJECT ENGINEER
DRAWN…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .