CTR079591 Breinholt - Demolition Schedule.xlsx

XLSX spreadsheet 22 KB Posted

Attached to
Master Agreement AZ|CTR079591
Contract number
CTR079591
Issued by
Arizona

About this file

The document appears to be a demolition project schedule (CTR079591) for Parcel 7-12289, specifically detailing a site demolition timeline. The file contains a detailed Gantt chart-style breakdown of project activities at a location identified as 17063 W. Cocopah Street, with precise scheduling of sequential tasks including NESHAP compliance, dust permitting, equipment mobilization, and site wall painting.

The project schedule spans approximately 60 days, commencing on 5/14/19, with specific activities allocated discrete time periods. Key project phases include initial NESHAP and dust permit preparations (10 days each), equipment mobilization (1 day), site work at 17063 W. Cocopah Street, equipment demobilization, and painting of a Homeowners Association (HOA) site wall. While detailed pricing and comprehensive contract terms are not explicitly presented in this document, the schedule suggests a structured, methodical approach to a localized demolition project with precise task sequencing and timing.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

project

Demolition of Parcel 7-12289
Period Highlight:1Plan
PLANPLAN
ACTIVITYSTARTDURATIONPERIODS
Days1234567891011121314151617181920212223242526272829303132333435363738394041424344454647
Start
5/14/19
Demo NESHAP110
Dust Permit110

Mobilize Equipment 11 1

17063 W. Cocopah Street 11 2

De-Mobilize Equipment 12 1

Paint HOA Site Wall 13 1